Business Description synthesis.

Despite achieving financial stabilization and significant progress toward decarbonization goals, PG&E's business model is undergoing a fundamental structural pivot driven by the energy transition. While aggressive capital investment in grid modernization has successfully increased GHG-free generation capacity, sustained upward pressure on customer rates reflects the cost of this massive undertaking. This shift simultaneously highlights the diminishing viability of its natural gas sector as electrification trends accelerate, replacing acute disaster risk with complex systemic challenges.

FY2021 → FY2025 L2 Comparitive Synthesis
  symbology.online l2 SYNTHESIS 

Pg&e Corp - Business Description synthesis.

Analysis of PG&E Filing Trends (2021–2025)

This report synthesizes the evolution of PG&E Corporation’s business model, financial performance, strategic priorities, and risk profile across successive filing periods from 2021 through 2025. The company has demonstrated significant progress in financial recovery and decarbonization while managing persistent structural challenges related to regulatory dependency, climate risk, and declining fossil fuel demand.

Financial and Quantitative Shifts

Revenue Mix and Growth

PG&E’s overall revenue growth has been robust, driven primarily by increasing rates and favorable regulatory balancing account recoveries rather than volume increases in the electric segment. Electric operating revenues grew consistently from $15.1 billion in 2021 to approximately $18.3 billion in 2025.

The natural gas sector has experienced significant volatility:

  • Early Growth (2021–2022): Gas revenue saw a substantial jump, rising from $5.5 billion in 2021 to $6.62 billion in 2022, partly fueled by skyrocketing commodity prices ($7.42/Mcf in 2022).
  • Structural Decline (2023–2025): The segment has since faced a structural decline risk due to electrification trends and plummeting natural gas prices. Gas revenues decreased from $7.0 billion in 2023 to approximately $6.6 billion in 2024, reflecting the sharp drop in commodity costs ($1.99/Mcf in 2024).

Capital Investment and Rate Pressure

The company has maintained an aggressive capital expenditure (CAPEX) program throughout this period, escalating from $8.6 billion in 2021 to a projected ramp-up of over $13 billion annually through 2029. This massive investment is focused heavily on grid modernization, wildfire mitigation, and energy storage deployment.

This heavy CAPEX load has resulted in sustained upward pressure on customer rates:

  • The average residential electric rate rose steadily from $0.2125/kWh in 2021 to a peak of $0.2888/kWh in 2024, before stabilizing slightly at $0.2836/kWh in 2025.
  • This continuous rate increase is cited as the primary driver of customer attrition and competitive pressure from Community Choice Aggregators (CCAs) and Direct Access (DA) providers.

Financial Recovery Milestones

The company has moved significantly toward financial stabilization post-Chapter 11 bankruptcy in 2020:

  • Debt Reduction: PG&E successfully utilized $7.5 billion in wildfire recovery bonds (issued in 2022) to retire substantial Utility debt ($6.0–$5.0 billion). The commitment remains to reduce corporate debt by at least $2 billion by the end of 2026.
  • Credit Rating: All three major credit rating agencies have upgraded PG&E's issuer ratings since 2020, signaling improved financial health.
  • Dividends: After a suspension dating back to December 2017, common stock dividends were reinstated in mid-to-late 2022 and reaffirmed in late 2023, reflecting the company's improving cash flow stability.

Strategy Pivots and Operational Changes

Decarbonization and Clean Energy Profile

PG&E has aggressively aligned its strategy with California’s decarbonization mandates (100% GHG-free by 2045). The clean energy profile has improved substantially:

  • The percentage of GHG-free electricity delivered rose from 93% in 2021 to over 98% in 2022, and continued strong performance into 2025.
  • Nuclear Continuity: Initially a significant risk due to impending license expirations (2024/2025), the Diablo Canyon Nuclear Plant's operations were secured through regulatory extensions (SB 846 in 2023). This provides stable, baseload GHG-free generation revenue.
  • Storage and Renewables: The focus has shifted from simple procurement to massive deployment; contracted battery energy storage capacity grew dramatically from an initial target of >3,330 MW in 2021/2022 to over 4.6 GW by 2024, with further expansion planned through 2025 and beyond.

Grid Modernization and Electrification

The strategic priority has been the massive undergrounding of distribution lines (a 10,000-mile goal), accelerating from a small initial program in 2021 to over 364 miles completed in 2023, and nearly 260 miles in 2024.

The company has pivoted its long-term gas strategy to support broader electrification:

  • PG&E is actively supporting electric vehicle (EV) adoption and building electrification. The Utility anticipates that EV adoption and data center expansion will drive increased electric load, while simultaneously accelerating the structural decline in natural gas demand.
  • In response, PG&E has introduced initiatives like targeting 15% renewable natural gas for residential use by 2030.

Evolution of Risks and Liabilities

Wildfire Liability Mitigation vs. Climate Reality

Wildfire liability remains an existential risk, but the nature of the risk has evolved:

  • Mitigation Progress: The Utility has made measurable progress in reducing physical ignitions (e.g., zero major ignitions attributed to Utility equipment in 2023 and 2025). Mitigation programs like Enhanced Powerline Safety Settings (EPSS) and Public Safety Power Shutoffs (PSPS) have been deployed and refined.
  • Climate Escalation: Despite mitigation success, the risk itself is escalating due to climate change. Filings repeatedly note that hotter, drier conditions are expanding High Fire Threat Districts (HFTDs), and CPUC-reportable ignitions increased in 2024 due to these intensifying conditions.
  • Financial Burden: A critical financial constraint has emerged: $2.85 billion of fire risk mitigation CAPEX is explicitly excluded from the equity rate base under state law, representing a direct cost burden to shareholders despite the safety improvements.

Structural and Operational Risks

The overall risk profile has shifted from being dominated solely by catastrophic wildfire liability (pre-2023) to facing complex structural challenges:

  • Natural Gas Stranding: The long-term decline in gas demand due to electrification is now identified as a key weakness, threatening the viability of its natural gas segment over time.
  • Regulatory Uncertainty: Earnings remain fundamentally dependent on favorable outcomes from multi-year General Rate Case (GRC) proceedings with multiple regulatory bodies (CPUC, FERC).
  • Labor Risk: While workforce stability improved in 2023 and 2024, the expiration of collective bargaining agreements across a significant portion of the workforce by December 2025 introduced a new near-term labor negotiation risk.

Side-by-side against the previous Business Descriptions.

  FY2024 → FY2025 Text Diffs 

escalated ITEM 1. BUSINESS

FY 2024 10-K
Removed
Filed Feb 13, 2025

ITEM 1. BUSINESS PG&E Corporation, incorporated in California in 1995, is a holding company whose primary operating subsidiary is Pacific Gas and Electric Company, a public utility operating in Northern and Central California. The Utility was incorporated in California in 1905. PG&E Corporation became the holding company of the Utility and its subsidiaries in 1997. The Utility generates revenues mainly through the sale and delivery of electricity and natural gas to customers. The Utility's service area is shown in the graphic below.

FY 2025 10-K
Added
Filed Feb 12, 2026

ITEM 1. BUSINESS PG&E Corporation, incorporated in California in 1995, is a holding company whose primary operating subsidiary is Pacific Gas and Electric Company, a public utility operating in Northern and Central California. The Utility was incorporated in California in 1905. PG&E Corporation became the holding company of the Utility and its subsidiaries in 1997. The Utility generates revenues mainly through the sale and delivery of electricity and natural gas to customers. The Utility's service area is shown in the graphic below. PG&E Corporation's and the Utility's operating revenues, income, and total assets for the most recently completed year can be found below in Item 8. Financial Statements and Supplementary Data. The principal executive offices of PG&E Corporation and the Utility are located at 300 Lakeside Drive, Oakland, California 94612. PG&E Corporation's telephone number is (415) 973-1000 and the Utility's telephone number is (415) 973-7000.

escalated Electricity Resources The disclosure shifted from a general statement about primarily renewable resources to providing specific 2025 data showing that 71% of net deliveries were generated from GHG-free sources while 29% was natural gas. The Utility further explained that its percentage of GHG-free generation decreased in 2025 because DCPP's generation became attributable statewide rather than solely to the Utility's customers, despite no change in ownership.

FY 2024 10-K
Removed
Filed Feb 13, 2025

Electricity Resources The Utility is required to maintain adequate capacity to meet its customers' demand for electricity ("load"), including peak demand and planning and operating reserves, deliverable to the locations and at times as may be necessary to provide reliable electric service. The Utility is responsible for scheduling and bidding electric generation resources, including certain electricity procured from third parties into the wholesale market, to meet customer demand. The following table shows the percentage of the Utility's estimated total net deliveries of electricity to retail customers in 2024 represented by each major electric resource, and further discussed below. The Utility's deliveries were primarily from renewable energy resources that qualify under California's RPS and other GHG-free resources (i.e., nuclear, and large hydroelectric generation). California's RPS requirements and SB 100 goal is to serve 100% of retail electricity sales with GHG-free resources by 2045. For more information about California's RPS requirements and clean energy goals, see further below and in the "Sustainability and Resiliency" section below. 26

FY 2025 10-K
Added
Filed Feb 12, 2026

Electricity Resources The Utility is required to maintain adequate capacity to meet its customers' demand for electricity ("load"), including peak demand and planning and operating reserves, deliverable to the locations and at times as may be necessary to provide reliable electric service. The Utility is responsible for scheduling and bidding electric generation resources, including certain electricity procured from third parties into the wholesale market, to meet customer demand. In 2025, the Utility estimated total net deliveries of electricity to retail customers were 24,052 GWh. This amount represents the total amount of electricity generated and procured, net of electricity sold into the CAISO open market or to third parties. Utility-owned resources generated approximately 60% of its net delivered electricity. Of the 2025 estimated total net deliveries of electricity to retail customers from generated and procured resources, approximately 71% was generated from GHG-free resources (34% qualifying renewable energy resources, 32% nuclear, and 5% large hydroelectric), and 29% was generated from natural gas generation resources. Consistent with the RPS requirement, the Utility considers qualifying renewable energy resources to include bioenergy such as biogas and biomass, hydroelectric facilities that are 30 MW or less, wind, solar, and geothermal energy. The Utility's percentage of GHG-free generation decreased in 2025, compared to 2024, because DCPP's generation became attributable to all customers statewide (rather than only the Utility's customers). This change does not represent a decrease in the Utility's ownership of the DCPP resource; rather, the generation associated with this resource became attributed among other LSEs' portfolios. For more information about California's clean energy goals, see further below and in the "Sustainability and Resiliency" section below. 23

de-emphasised Environmental Regulation

FY 2024 10-K
Removed
Filed Feb 13, 2025

Environmental Regulation The Utility's operations are subject to extensive federal, state, and local laws and requirements relating to the protection of the environment and the safety and health of the Utility's personnel and the public. These laws and requirements relate to a broad range of activities, including the remediation of hazardous and radioactive substances; the discharge of pollutants into the air, water, and soil; the reporting and reduction of CO2 and other GHG emissions; the transportation, handling, storage and disposal of spent nuclear fuel; and the environmental impacts of land use, including endangered species and habitat protection. The penalties for violation of these laws and requirements can be severe and may include significant fines, damages, and criminal or civil sanctions. These laws and requirements also may require the Utility, under certain circumstances, to interrupt or curtail operations. See Item 1A. Risk Factors. Generally, the Utility recovers most of the costs of complying with environmental laws and regulations through the Utility's rates, subject to reasonableness review. Environmental costs associated with the clean-up of most sites that contain hazardous substances are subject to a ratemaking mechanism described in Note 15 of the Notes to the Consolidated Financial Statements in Item 8.

FY 2025 10-K
Added
Filed Feb 12, 2026

Environmental Regulation The Utility's operations are subject to extensive federal, state, and local laws and requirements relating to the protection of the environment and the safety and health of the Utility's personnel and the public. These laws and requirements relate to a broad range of activities, including the remediation of hazardous and radioactive substances; the discharge of pollutants into the air, water, and soil; the reporting and reduction of CO2 and other GHG emissions; the transportation, handling, storage and disposal of spent nuclear fuel; and the environmental impacts of land use, including endangered species and habitat protection. The penalties for violation of these laws and requirements can be severe and may include significant fines, damages, and criminal or civil sanctions. These laws and requirements also may require the Utility, under certain circumstances, to interrupt or curtail operations. See Item 1A. Risk Factors. Generally, the Utility recovers most of the costs of complying with environmental laws and regulations through the Utility's rates, subject to reasonableness review.

de-emphasised Hazardous Substance Compliance and Remediation The current filing removes the prior period's detailed description of strict liability under CERCLA, which outlined that potentially responsible parties may be jointly and severally liable for cleanup costs, monitoring, and health studies. The remaining content regarding compliance programs, incurred liabilities, and specific contamination issues remains unchanged.

FY 2024 10-K
Removed
Filed Feb 13, 2025

Hazardous Substance Compliance and Remediation The Utility's facilities are subject to various regulations adopted by the EPA, including the Resource Conservation and Recovery Act and the Comprehensive Environmental Response, Compensation and Liability Act of 1980, as amended. The Utility is also subject to the regulations adopted by other federal agencies responsible for implementing federal environmental laws. The Utility also must comply with environmental laws and regulations adopted by the State of California and various state and local agencies. These federal and state laws impose strict liability for the release of a hazardous substance on the (1) owner or operator of the site where the release occurred, (2) on companies that disposed of, or arranged for the disposal of, the hazardous substances, and (3) in some cases, their corporate successors. Under the Comprehensive Environmental Response, Compensation and Liability Act, these persons (known as "potentially responsible parties") may be jointly and severally liable for the costs of cleaning up the hazardous substances, monitoring and paying for the harm caused to natural resources, and paying for the costs of health studies. 19 The Utility has a comprehensive program in place to comply with these federal, state, and local laws and regulations. Under federal and California laws, the Utility may be responsible for remediation of hazardous substances even if it did not deposit those substances on the site. The Utility's remediation activities are overseen by the DTSC, several California regional water quality control boards, and various other federal, state, and local agencies. The Utility has incurred significant environmental remediation liabilities associated with former MGP sites, power plant sites, gas gathering sites, sites where natural gas compressor stations are located, and sites used by the Utility for the storage, recycling, or disposal of potentially hazardous substances. Groundwater at the Utility's Hinkley and Topock natural gas compressor stations contains hexavalent chromium as a result of the Utility's past operating practices. The Utility is responsible for remediating this groundwater contamination and for abating the effects of the contamination on the environment.

FY 2025 10-K
Added
Filed Feb 12, 2026

Hazardous Substance Compliance and Remediation The Utility's facilities are subject to various regulations adopted by the EPA, including the Resource Conservation and Recovery Act and the Comprehensive Environmental Response, Compensation and Liability Act of 1980, as amended. The Utility is also subject to the regulations adopted by other state and federal agencies responsible for implementing environmental laws. The Utility maintains a comprehensive compliance program but may be liable for remediation of hazardous substances even if it did not deposit those substances on the site. The Utility's remediation activities are overseen by the California Department of Toxic Substances Control, several California regional water quality control boards, and various other federal, state, and local agencies. The Utility has incurred significant environmental remediation liabilities associated with former MGP sites, power plant sites, gas gathering sites, sites where natural gas compressor stations are located, and sites used by the Utility for the storage, recycling, or disposal of potentially hazardous substances. Groundwater at the Utility's Hinkley and Topock natural gas compressor stations contains hexavalent chromium as a result of the Utility's past operating practices. The Utility is responsible for remediating this groundwater contamination and for abating the effects of the contamination on the environment.

de-emphasised Program-Specific Memorandum Account and Balancing Account Costs

FY 2024 10-K
Removed
Filed Feb 13, 2025

Program-Specific Memorandum Account and Balancing Account Costs Periodically, costs arise outside of the CPUC's GRC proceedings or that have been deliberately excluded from such proceedings. These costs may result from catastrophic events, changes in regulation, new programs, or extraordinary changes in operating practices. The Utility may seek authority to track incremental costs in a memorandum account, and the CPUC may authorize recovery of costs tracked in memorandum accounts if the costs are deemed reasonable. For instance, these accounts allow the Utility to track the costs associated with work related to disaster and wildfire response, and other wildfire prevention-related costs. Recovery of the costs tracked in these memorandum accounts through rates requires CPUC authorization in separate proceedings, the outcome of which the Utility may be unable to predict. Alternatively, the Utility may seek authority to track incremental costs related to these non-GRC programs in balancing accounts. The CPUC may authorize recovery of costs tracked in the balancing accounts on either a "one-way" basis, which typically only allows actual costs to be recovered up to a pre-established cap, or a "two-way" basis, which typically allows actual costs to be recovered, and in some cases subject to further CPUC review. For more information, see "Regulatory Matters - Cost Recovery Proceedings" in Item 7. MD&A and Note 3 of the Notes to the Consolidated Financial Statements in Item 8.

FY 2025 10-K
Added
Filed Feb 12, 2026

Program-Specific Memorandum Account and Balancing Account Costs Periodically, costs arise outside of the CPUC's GRC proceedings or that have been deliberately excluded from such proceedings. These costs may result from catastrophic events, changes in regulation, new programs, or extraordinary changes in operating practices. The Utility may seek authority to track incremental costs in a memorandum account, and the CPUC may authorize recovery of costs tracked in memorandum accounts if the costs are deemed reasonable. Recovery of the costs tracked in these memorandum accounts through rates requires CPUC authorization in separate proceedings, the outcome of which the Utility may be unable to predict. Alternatively, the Utility may seek authority to track incremental costs related to these non-GRC programs in balancing accounts. For more information, see "Regulatory Matters - Cost Recovery Proceedings" in Item 7. MD&A and Note 3 of the Notes to the Consolidated Financial Statements in Item 8.

de-emphasised Electricity Procurement Costs The disclosure significantly reduced detail regarding regulatory oversight by removing a comprehensive section detailing the annual CPUC review process, forecasted revenue requirements, and rate adjustment triggers based on collection variances. Furthermore, the description of the Central Procurement Entity (CPE) function was simplified, eliminating language that protected the Utility from fines or penalties for deferring local procurement to CAISO backstop mechanisms.

FY 2024 10-K
Removed
Filed Feb 13, 2025

Revenues to Recover Energy Procurement and Other Pass-Through Costs Electricity Procurement Costs California IOUs are responsible for procuring electrical capacity required to meet bundled customer demand, plus applicable reserve margins. The utilities are responsible for scheduling and bidding electric generation resources, including certain electricity procured from third parties, into the wholesale market to meet customer demand according to which resources are the least expensive (i.e., using the principles of "least-cost dispatch"). In addition, the utilities are required to obtain CPUC approval of their BPPs based on long-term demand forecasts. In October 2015, the CPUC approved the Utility's most recent comprehensive BPP. It has been revised since its initial approval, and the revised version will remain in effect, subject to any further revisions, until superseded by a subsequent CPUC-approved plan. 22 California law allows electric utilities to recover the costs incurred in compliance with their CPUC-approved BPPs without further after-the-fact reasonableness review by the CPUC. The CPUC may disallow costs associated with electricity purchases if the costs were not incurred in compliance with the CPUC-approved plan or if the CPUC determines that the utility failed to follow the principles of least-cost dispatch. Additionally, the CPUC may disallow the value of lost generation due to unplanned outages at utility-owned generation facilities. The Utility recovers its electric procurement costs annually primarily through balancing accounts. See Note 3 of the Notes to the Consolidated Financial Statements in Item 8. Each year, the CPUC reviews the Utility's forecasted procurement costs related to power purchase agreements, derivative instruments, GHG emissions costs, and generation fuel expense, and approves a forecasted revenue requirement. The CPUC may adjust the Utility's retail electric rates more frequently if the forecasted aggregate over-collections or under-collections in the Energy Resource Recovery Account, net of bundled service customer Portfolio Allocation Balancing Account balances, exceed five percent of its prior year electric procurement and Utility-owned generation revenues. The CPUC performs an annual compliance review of the procurement transactions recovered in various balancing accounts, including the Energy Resource Recovery Account and the Portfolio Allocation Balancing Account. The CPUC has approved various power purchase agreements into which the Utility has entered with third parties in accordance with the Utility's CPUC-approved BPP, to meet mandatory renewable energy targets, and to comply with RA requirements. For more information, see "Electric Utility Operations - Electricity Resources" below as well as Note 15 of the Notes to the Consolidated Financial Statements in Item 8. The Utility is also responsible, as the central procurement entity ("CPE") for its distribution service area, for seeking to procure the entire amount of required local RA on behalf of all CPUC-jurisdictional LSEs in its distribution service area. CPUC decisions grant the Utility, acting as CPE, discretion to defer procurement of local resources to the CAISO's backstop mechanisms if bid costs are deemed unreasonably high. The Utility, as the CPE, will not be assessed fines or penalties for failing to procure resources to meet the local RA requirements and deferring local procurement to the CAISO backstop mechanism, so long as the CPE exercised reasonable efforts to secure capacity and certain specified requirements are met. In addition, the Utility, as the CPE, has been ordered or authorized to seek to procure specific local capacity products pursuant to CPUC decisions. In connection with its CPE function, the Utility is responsible for making compliance demonstrations to the CPUC and the CAISO. The Utility recovers its administrative and procurement costs associated with its CPE function through a balancing account. The CPUC may disallow costs associated with the CPE function that were not incurred in compliance with the CPUC's decisions and guidance. The CPUC has also approved the Power Charge Indifference Adjustment ("PCIA"). The PCIA is a cost recovery mechanism to ensure that customers who switch from the Utility's bundled service to a non-Utility provider, such as a DA or CCA provider, pay their share of the above-market costs associated with long-term power purchase commitments and Utility-owned generation made on their behalf.

FY 2025 10-K
Added
Filed Feb 12, 2026

Revenues to Recover Energy Procurement and Other Pass-Through Costs Electricity Procurement Costs California IOUs are responsible for procuring electrical capacity required to meet bundled customer demand, plus applicable reserve margins. The utilities are responsible for scheduling and bidding electric generation resources, including certain electricity procured from third parties, into the wholesale market to meet customer demand according to which resources are the least expensive. In addition, the utilities are required to obtain CPUC approval of their bundled procurement plans ("BPPs"), which are based on customer demand forecasts. California law allows electric utilities to recover the costs incurred in compliance with their CPUC-approved BPPs without further after-the-fact reasonableness review by the CPUC. The Utility recovers its electric procurement costs annually primarily through balancing accounts. See Note 3 of the Notes to the Consolidated Financial Statements in Item 8. The CPUC may disallow costs associated with electricity purchases if the costs were not incurred in compliance with the CPUC-approved plan or if the CPUC determines that the utility failed to follow the principles of least-cost dispatch. Additionally, the CPUC may disallow the value of lost generation due to unplanned outages at utility-owned generation facilities. The CPUC has approved various power purchase agreements into which the Utility has entered with third parties in accordance with the Utility's CPUC-approved BPP, to meet mandatory renewable energy targets, and to comply with RA requirements. For more information, see "Electric Utility Operations - Electricity Resources" below as well as Note 15 of the Notes to the Consolidated Financial Statements in Item 8. 20 The Utility is also responsible, as the central procurement entity ("CPE") for its distribution service area, for seeking to procure the entire amount of required local RA on behalf of all CPUC-jurisdictional LSEs in its distribution service area. The Utility may defer procurement of local resources to the CAISO's backstop mechanisms if bid costs are deemed unreasonably high. In addition, the CPUC can order the Utility to seek to procure specific local capacity products, which are included as energy procurement costs. The Utility recovers its administrative and procurement costs associated with its CPE function through a balancing account, subject to demonstrating compliance to the CPUC. The CPUC has also approved the Power Charge Indifference Adjustment ("PCIA"). The PCIA is a cost recovery mechanism to ensure that customers who switch from the Utility's bundled service to a non-Utility provider, such as a DA or CCA provider, pay their share of the above-market costs associated with long-term power purchase commitments and Utility-owned generation made on their behalf.

de-emphasised The Utility recovers the cost of gas used in generation facilities as a cost of electricity that is recovered annually through retail electric rates. The detailed description of the Core Procurement Incentive Mechanism (CPIM) was significantly shortened; specifically, the prior period included a discussion that the Utility retains incentive revenues up to a 1.5% cap when costs are below benchmark, which has been removed in the current filing. The current version simplifies this by only stating the recovery percentages for costs falling outside the 99% to 102% tolerance band.

FY 2024 10-K
Removed
Filed Feb 13, 2025

Natural Gas Procurement, Storage, and Transportation Costs The Utility recovers the cost of gas used in generation facilities as a cost of electricity that is recovered annually through retail electric rates. The Utility sets the natural gas procurement rate for small commercial and residential customers (referred to as "core" customers) monthly, based on the forecasted costs of natural gas, core pipeline capacity and storage costs. The Utility recovers the cost of gas purchased on behalf of core customers as well as the cost of derivative instruments for its core gas portfolio, through its retail gas rates, subject to limits as set forth in its Core Procurement Incentive Mechanism ("CPIM") described below. The Utility reflects the difference between actual natural gas purchase costs and forecasted natural gas purchase costs in several natural gas balancing accounts, with adjustments for under-collections and over-collections made in subsequent monthly rate changes. 23 The CPIM protects the Utility against after-the-fact reasonableness reviews of its gas procurement costs for its core gas portfolio. Under the CPIM, the Utility's natural gas purchase costs for a fixed 12-month period are compared to an aggregate market-based benchmark based on a weighted average of published monthly and daily natural gas price indices at the points where the Utility typically purchases natural gas. Costs that fall within a tolerance band, which is 99% to 102% of the commodity benchmark, are considered reasonable and are fully recovered through rates. One-half of the costs above 102% of the benchmark are recoverable through rates, and the Utility's customers receive in their rates 80% of any savings resulting from the Utility's cost of natural gas that is less than 99% of the benchmark. The Utility retains the remaining amount of these savings as incentive revenues, subject to a cap equal to 1.5% of total natural gas commodity costs. While this mechanism remains in place, changes in the price of natural gas, consistent with the market-based benchmark, are not expected to materially impact net income. The Utility incurs transportation costs under various agreements with interstate and Canadian third-party transportation service providers. These providers transport natural gas from the points at which the Utility takes delivery of natural gas (typically in Canada, the U.S. Rocky Mountains, and the southwestern United States) to the points at which the Utility's natural gas transportation system begins. These agreements are governed by FERC-approved tariffs that detail rates, rules, and terms of service for the provision of natural gas transportation services to the Utility on interstate and Canadian pipelines. The FERC approves the United States tariffs governing payments by shippers (including the Utility) for pipeline service, and the Canada Energy Regulator, the Canadian regulatory agency, approves the applicable Canadian tariffs. The transportation costs the Utility incurs under these agreements are recovered through CPUC-approved rates as core natural gas procurement costs or as a cost of electricity.

FY 2025 10-K
Added
Filed Feb 12, 2026

Natural Gas Procurement, Storage, and Transportation Costs The Utility recovers the cost of gas used in generation facilities as a cost of electricity that is recovered annually through retail electric rates. The Utility generally recovers the cost of gas purchased on behalf of small commercial and residential customers, as well as the cost of derivative instruments for its core gas portfolio, through its retail gas rates. If the Utility's costs average less than 99% of a market-based benchmark, then the Utility returns 80% of such savings to customers, subject to a cap; if the Utility's costs average more than 102% of the benchmark, the Utility recovers 50% of such excess costs. As a result, changes in the price of natural gas are not expected to materially impact net income. The Utility incurs transportation costs under various agreements with interstate and Canadian third-party transportation service providers. These providers transport natural gas from the points at which the Utility takes delivery of natural gas (typically in Canada, the U.S. Rocky Mountains, and the southwestern United States) to the points at which the Utility's natural gas transportation system begins. These agreements are governed by FERC-approved tariffs that detail rates, rules, and terms of service for the provision of natural gas transportation services to the Utility on interstate and Canadian pipelines. The FERC approves the United States tariffs governing payments by shippers (including the Utility) for pipeline service, and the Canada Energy Regulator, the Canadian regulatory agency, approves the applicable Canadian tariffs. The transportation costs the Utility incurs under these agreements are recovered through CPUC-approved rates as core natural gas procurement costs or as a cost of electricity.

de-emphasised Planet

FY 2024 10-K
Removed
Filed Feb 13, 2025

For more information, see "Human Capital" below. Planet The planet element of the triple bottom line represents PG&E Corporation's and the Utility's commitment to protect and serve the environment. This commitment extends beyond compliance with various state and federal environmental, health, and safety laws and regulations. PG&E Corporation and the Utility believe that integrating and managing climate change and other environmental considerations in the companies' business strategies creates long-term value for PG&E Corporation and the Utility, and for their customers, communities, employees, and other stakeholders. The Utility is committed to delivering a safe, reliable, sustainable, and climate-resilient energy system at the lowest possible cost in the face of increasingly severe and extreme climate-driven natural hazards. To build resilience to these hazards, the Utility is working to systematically integrate forward-looking climate data and tools into its decision-making. PG&E Corporation and the Utility also work with policymakers and regulators to advance effective climate change policy in California, and work directly with local governments and communities on adaptation solutions. PG&E Corporation and the Utility are also committed to helping heal the planet. PG&E Corporation's and the Utility's 2022 Climate Strategy Report, which is available to the public, describes the companies' climate goals and plans to meet those goals. To meet their longer-term climate goals, PG&E Corporation and the Utility intend to scale their efforts to decarbonize the energy system to accommodate a shift to vehicle electrification, integrate a proliferation of distributed energy resources, and achieve increased utilization of renewable energy combined with investments in the grid and energy storage. PG&E Corporation and the Utility continue to pursue policies and programs that enable safe, reliable, affordable, clean, and resilient energy for their customers. As a result of actions already taken by PG&E Corporation and the Utility, the companies have:

FY 2025 10-K
Added
Filed Feb 12, 2026

For more information, see "Human Capital" below. Planet The planet element of the triple bottom line represents PG&E Corporation's and the Utility's commitment to protect and serve the environment. PG&E Corporation and the Utility believe that integrating and managing climate change and other environmental considerations in the companies' business strategies creates long-term value for PG&E Corporation and the Utility, and for their customers, communities, employees, and other stakeholders. The Utility is adapting to severe and extreme climate-driven natural hazards. To build resilience to these hazards, the Utility is working to systematically integrate forward-looking climate data and tools into its decision-making. PG&E Corporation and the Utility also work with policymakers and regulators to advance effective climate change policy in California, and work directly with local governments and communities on adaptation solutions. PG&E Corporation's and the Utility's 2022 Climate Strategy Report, which is available to the public, describes the companies' climate goals and plans to meet those goals. To meet their longer-term climate goals, PG&E Corporation and the Utility intend to scale their efforts to decarbonize the energy system to accommodate increased vehicle and building electrification, integrate a proliferation of distributed energy resources, and achieve increased utilization of renewable energy combined with investments in the grid and energy storage. PG&E Corporation and the Utility continue to pursue policies and programs that enable safe, reliable, affordable, clean, and resilient energy for their customers. As a result of actions already taken by PG&E Corporation and the Utility, the companies have:

de-emphasised Inclusion and Belonging

FY 2024 10-K
Removed
Filed Feb 13, 2025

Diversity, Equity, Inclusion, and Belonging PG&E Corporation's and the Utility's goal is to foster a diverse, equitable, and inclusive workforce culture where all employees find it enjoyable to work with and for PG&E Corporation and the Utility and feel they belong. These efforts are led by PG&E Corporation's and the Utility's Executive Vice President, Chief People Officer, in partnership with the executive team. The People and Compensation Committee of PG&E Corporation's Board of Directors reviews the companies' diversity, equity, inclusion, and belonging strategy, practices, and performance. Key elements of PG&E Corporation's and the Utility's approach to diversity, equity, inclusion, and belonging include integrating inclusion and belonging into the employee experience with a focus on equity and interrupting bias in hiring, promotion, retention and compensation, heightened cultural awareness programming to encourage understanding and importance of inclusion and belonging, and integrating useful content into training, development, and performance support resources. Additionally, the Utility's 12 Employee Resource Groups and three Engineering Network Groups execute enterprise-wide employee programming, nominated employees lead efforts within their departments, and across the companies. Specialized teams facilitate awareness, education and dialogue and support the groups at the enterprise level. In 2024, women, minorities, and military veterans accounted for approximately 26%, 50%, and 7%, respectively, of total PG&E Corporation and Utility employees. The Utility's employees represent five generations, most of whom are Millennials (49%), Generation X (37%), and Boomers (10%). Generational data refers to "Millennials" for individuals born between 1981 and 1996, "Generation X" between 1965 and 1980, and "Boomers" between 1946 and 1964.

FY 2025 10-K
Added
Filed Feb 12, 2026

Inclusion and Belonging PG&E Corporation's and the Utility's goal is to foster a workplace culture of inclusion and belonging where all employees find it enjoyable to work with and for PG&E Corporation and the Utility and feel they belong. These efforts are led by PG&E Corporation's and the Utility's Executive Vice President, Chief People Officer, in partnership with the executive team. The People and Compensation Committee of PG&E Corporation's Board of Directors reviews the companies' inclusion and belonging strategy, practices, and performance. Key elements of PG&E Corporation's and the Utility's approach to inclusion and belonging include integrating inclusion and belonging into the employee experience with a focus on equity and interrupting bias in hiring, promotion, retention and compensation, heightened cultural awareness programming to encourage understanding and importance of inclusion and belonging, and integrating useful content into training, development, and performance support resources. Additionally, the Utility's 12 Employee Resource Groups and three Engineering Network Groups execute enterprise-wide employee engagement programming and recognize employees' contributions to organizational culture among the Utility's workforce, communities, and customers. The Employee Resource Groups are open to all employees. Specialized teams facilitate awareness, education, and dialogue and support enterprise inclusion and belonging efforts.

de-emphasised Electricity Distribution

FY 2024 10-K
Removed
Filed Feb 13, 2025

Decisions about expansions and maintenance of the transmission system can be influenced by decisions of the Utility's regulators and the CAISO. Electricity Distribution Distribution lines allow electricity to travel at lower voltages from substations directly to customers. The Utility's electric distribution network consists of approximately 108,000 circuit miles of distribution lines (of which, as of December 31, 2024, approximately 27% are underground and approximately 73% are overhead), 59 transmission and distribution substations, and 603 distribution substations with a capacity of approximately 33,000 MVA. The Utility's distribution network interconnects with its transmission system, primarily at switching and distribution substations, where equipment reduces the high-voltage transmission voltages to lower voltages, suitable for distribution to the Utility's customers. These distribution substations serve as the central hubs for the Utility's electric distribution network. Emanating from each substation are primary and secondary distribution lines connected to local transformers and switching equipment that link distribution lines and provide delivery to customers. In some cases, third parties, such as municipal and other utilities, who generate or procure their own power rely upon the Utility's distribution facilities to deliver their power to them, so that they are able to resell the electricity. The Utility operates electric distribution control center facilities in Concord, Rocklin, and Fresno, California; these control centers form a key part of the Utility's efforts to create a smarter, more resilient grid. 29

FY 2025 10-K
Added
Filed Feb 12, 2026

Decisions about expansions and maintenance of the transmission system can be influenced by decisions of the Utility's regulators and the CAISO. Electricity Distribution Distribution lines allow electricity to travel at lower voltages from substations directly to customers. The Utility's electric distribution network consists of approximately 109,000 circuit miles of distribution lines (of which, as of December 31, 2025, approximately 27% are underground and approximately 73% are overhead), 59 transmission and distribution substations, and 601 distribution substations. The Utility's distribution network interconnects with its transmission system, primarily at switching and distribution substations, where equipment reduces the high-voltage transmission voltages to lower voltages, suitable for distribution to the Utility's customers. These distribution substations serve as the central hubs for the Utility's electric distribution network. Emanating from each substation are primary and secondary distribution lines connected to local transformers and switching equipment that link distribution lines and provide delivery to customers. In some cases, third parties, such as municipal and other utilities, who generate or procure their own power rely upon the Utility's distribution facilities to deliver their power to them, so that they are able to resell the electricity.

de-emphasised Natural Gas System Assets

FY 2024 10-K
Removed
Filed Feb 13, 2025

Natural Gas System Assets The Utility owns and operates an integrated natural gas transmission, storage, and distribution system that includes most of northern and central California. On December 31, 2024, the Utility's natural gas system consisted of approximately 45,200 miles of distribution pipelines, approximately 5,700 miles of backbone and local transmission pipelines, and various storage facilities. The Utility owns and operates eight natural gas compressor stations on its backbone transmission system and one compressor station on its local transmission system that are used to move gas through the Utility's pipelines. The Utility's backbone transmission system is used to transport gas from the Utility's interconnection with interstate pipelines, other local distribution companies, and California gas fields to the Utility's local transmission and distribution systems. The Utility has firm transportation agreements for the transportation of natural gas from various natural gas supply points and interconnection points to the Utility's natural gas transportation system. These agreements provide transportation service from western Canada to the United States-Canada border, from the United States-Canada border to an interconnection point with the Utility's natural gas transportation system at the Oregon-California border, from the U.S. Rocky Mountains to an interconnection point with the Utility's natural gas transportation system at the Oregon-California border, and from supply points in the southwestern United States to interconnection points with the Utility's natural gas transportation system in the area of California near Topock, Arizona. (For more information regarding the Utility's natural gas transportation agreements, see Note 15 of the Notes to the Consolidated Financial Statements in Item 8.) The Utility owns and operates three underground natural gas storage fields and has a 25% interest in a fourth storage field, all of which are connected to the Utility's gas transmission system. In 2019, the CPUC approved the discontinuation, through closure or sale, of operations at two of the Utility's owned and operated gas storage fields, Pleasant Creek and Los Medanos. The sale of Pleasant Creek is currently pending CPUC review and approval and the Utility anticipates to close on the sale in 2025. The Utility continues to operate and rely on the Los Medanos storage field as filed and approved in the 2023 GRC. The Utility owns and operates compressors and other facilities at these storage fields that are used to inject gas into the fields for storage and later for withdrawal. In addition, four independent storage operators are interconnected to the Utility's Northern California gas transmission system.

FY 2025 10-K
Added
Filed Feb 12, 2026

Natural Gas System Assets The Utility owns and operates an integrated natural gas transmission, storage, and distribution system that includes most of northern and central California. On December 31, 2025, the Utility's natural gas system consisted of approximately 45,400 miles of distribution pipelines, approximately 5,500 miles of backbone and local transmission pipelines, and various storage facilities. The Utility owns and operates seven natural gas compressor stations on its backbone transmission system and one compressor station on its local transmission system that are used to move gas through the Utility's pipelines. The Utility's backbone transmission system is used to transport gas from the Utility's interconnection with interstate pipelines, other local distribution companies, and California gas fields to the Utility's local transmission and distribution systems. The Utility has firm transportation agreements for the transportation of natural gas from various natural gas supply points and interconnection points to the Utility's natural gas transportation system. These agreements provide transportation service from western Canada to the United States-Canada border, from the United States-Canada border to an interconnection point with the Utility's natural gas transportation system at the Oregon-California border, from the U.S. Rocky Mountains to an interconnection point with the Utility's natural gas transportation system at the Oregon-California border, and from supply points in the southwestern United States to interconnection points with the Utility's natural gas transportation system in the area of California near Topock, Arizona. (For more information regarding the Utility's natural gas transportation agreements, see Note 15 of the Notes to the Consolidated Financial Statements in Item 8.) The Utility owns and operates three underground natural gas storage fields and has a 25% interest in a fourth storage field, all of which are connected to the Utility's gas transmission system. The Utility owns and operates compressors and other facilities at these storage fields that are used to inject gas into the fields for storage and later for withdrawal.

de-emphasised Competitive Conditions in the Electricity Industry A substantial portion detailing the impact of increasing distributed generation and energy storage, specifically referencing NEM and NBT tariffs and resulting upward rate pressure on certain customer groups, was removed from this section.

FY 2024 10-K
Removed
Filed Feb 13, 2025

Competition Trends in Market Demand and Competitive Conditions in the Electricity Industry The Utility expects customer electric load to increase in coming years primarily as a result of electric vehicle adoption, data centers, and building electrification. The Utility is not able to predict how quickly this electrification will occur. The Utility expects customer demand for gas to decrease in the coming years, primarily in response to policies supporting California's climate goals. California law allows qualifying non-residential electric customers of IOUs to purchase electricity from energy service providers rather than from the utilities up to certain annual limits specified for each utility. This arrangement is known as DA. In addition, California law permits cities, counties, and certain other public agencies that have qualified to become a CCA to generate or purchase electricity for their local residents and businesses. By law, a CCA can procure electricity for all of its residents and businesses that do not affirmatively elect to continue to receive electricity generated or procured by a utility. The Utility continues to provide transmission, distribution, metering, and billing services to DA customers at the election of their energy service provider. The CCA customers continue to obtain transmission, distribution, metering, and billing services from the Utility. In addition to collecting charges for transmission, distribution, metering, and billing services that it provides, the Utility is able to collect charges intended to recover the generation-related costs that the Utility incurred on behalf of DA and CCA customers while they were the Utility's customers. The Utility remains the electricity provider of last resort for these customers. Section 387 of the Public Utilities Code allows for a request to transfer the responsibilities of the provider of last resort obligation from IOUs to other entities. The Utility is also impacted by an increasing quantity of distributed generation and energy storage. The levels of self-generation of electricity by customers (primarily solar installations) and customer enrollment in NEM, which allows self-generating customers employing qualifying renewable resources to receive bill credits at the full retail rate, put upward rate pressure on non-NEM customers. The successor to the NEM tariffs, the NBT provides bill credits at a lower rate, which reduces the level of upward rate pressure on non-NEM or non-NBT customers, but does not eliminate the upward rate pressure. NEM and NBT customers are required to pay an interconnection fee, utilize time of use rates, and pay certain non-bypassable charges to help fund some of the costs of low income, energy efficiency, and other programs that other customers pay. Significantly higher bills for non-NEM or non-NBT customers may result in a decline of the number of such customers as they may seek alternative energy providers or adopt self-generation technologies. See "Concerns about high rates for the Utility's customers could negatively impact PG&E Corporation's and the Utility's financial condition, results of operations, liquidity, and cash flows" in Item 1A. Risk Factors and "Regulatory Matters - Order Instituting Rulemaking ("OIR") to Revisit Net Energy Metering Tariffs" in Item 7. MD&A. Further, in some circumstances, governmental entities such as cities and irrigation districts may have authority under the state constitution or state statute to provide retail electric service directly to consumers, in some cases bypassing the Utility's electric infrastructure entirely. Those entities may also rely upon FERC open access tariffs and Utility infrastructure to deliver their energy for resale at retail to existing or potential new Utility customers. These entities may also seek to acquire the Utility's transmission or distribution facilities through eminent domain for use in serving electricity at retail to existing or potential new Utility customers. As a result, the Utility could lose customers (residential, commercial, and industrial) or experience limited growth in the municipality. See "Jurisdictions attempt to acquire the Utility's assets through eminent domain, and third parties attempt to acquire the Utility's customers by bypassing the Utility's electric infrastructure system" in Item 1A. Risk Factors. It is also expected that some publicly-owned utilities will build new or duplicate transmission or distribution facilities to serve existing or potential new Utility customers, bypassing the Utility's electric infrastructure. In some instances, microgrid formation is a key factor in a community's choice to engage governmental entities. Some private companies have also called for changes in law that could allow those companies to privately serve electricity to retail customers without being regulated by the CPUC as public utilities. To the extent such changes occur and result in large customers reducing the share of transmission, distribution, and non-bypassable charges they pay, PG&E Corporation's and the Utility's financial condition and results of operations could be materially impacted. The effect of such types of retail competition generally is to reduce the number of utility customers, leading to decreased growth or a reduction in the Utility's rate base. The Utility also competes for the opportunity to develop and construct certain types of electric transmission facilities within, or interconnected to, its service area through a competitive bidding process managed by the CAISO.

FY 2025 10-K
Added
Filed Feb 12, 2026

The Utility expects customer demand for gas to decrease in the coming years, primarily in response to policies supporting California's climate goals. Competitive Conditions in the Electricity Industry California law allows qualifying non-residential electric customers of IOUs to purchase electricity from energy service providers rather than from the utilities up to certain annual limits specified for each utility. This arrangement is known as DA. In addition, California law permits cities, counties, and certain other public agencies that have qualified to become CCAs to generate or purchase electricity for their local residents and businesses. By law, a CCA can procure electricity for all of its residents and businesses that do not affirmatively elect to continue to receive electricity generated or procured by a utility. The Utility continues to provide transmission, distribution, metering, and billing services to DA customers at the election of their energy service provider. The CCA customers continue to obtain transmission, distribution, metering, and billing services from the Utility. In addition to collecting charges for transmission, distribution, metering, and billing services that it provides, the Utility collects charges intended to recover the generation-related costs that the Utility incurred on behalf of DA and CCA customers while they were the Utility's customers. The Utility remains the electricity provider of last resort for these customers. Further, in some circumstances, governmental entities such as cities and irrigation districts may have authority under the state constitution or state statute to provide retail electric service directly to consumers, in some cases bypassing the Utility's electric infrastructure entirely. Those entities may also rely upon FERC open access tariffs and Utility infrastructure to deliver their energy for resale at retail to existing or potential new Utility customers. These entities may also seek to acquire the Utility's transmission or distribution facilities through eminent domain for use in serving electricity at retail to existing or potential new Utility customers. As a result, the Utility could lose customers (residential, commercial, and industrial) or experience limited growth in the applicable municipality. See "Jurisdictions attempt to acquire the Utility's assets through eminent domain, and third parties attempt to acquire the Utility's customers by bypassing the Utility's electric infrastructure system" in Item 1A. Risk Factors. It is also expected that some publicly-owned utilities will build new or duplicate transmission or distribution facilities to serve existing or potential new Utility customers, bypassing the Utility's electric infrastructure. In some instances, microgrid formation is a key factor in a community's choice to engage governmental entities. Some private companies have also called for changes in law that could allow those companies to privately serve electricity to retail customers without being regulated by the CPUC as public utilities. The effect of such types of retail competition generally is to reduce the number of utility customers, leading to decreased growth or a reduction in the Utility's rate base. 28 The Utility also competes for the opportunity to develop and construct certain types of electric transmission facilities within, or interconnected to, its service area through a competitive bidding process managed by the CAISO.

de-emphasised •Renewable and zero-carbon resources supplying 90% of utilities' retail electricity sales to customers by 2035, 95% by 2040, and 100% by 2045. The state-wide cap-and-trade program was updated to be authorized through 2045 under new state law, and the prior period's detailed description of the utility’s specific compliance obligation as a natural gas supplier has been significantly condensed. Additionally, the discussion regarding uncertainty related to federal climate change actions by the Trump administration was removed.

FY 2024 10-K
Removed
Filed Feb 13, 2025

•Renewable and zero-carbon resources supplying 90% of utilities' retail sales to customers by 2035, 95% by 2040, and 100% by 2045. The CARB has also approved GHG emissions reporting and a state-wide, comprehensive cap-and-trade program that sets gradually declining limits (or "caps") on the amount of GHGs that may be emitted by major GHG emission sources within different sectors of the economy. The cap-and-trade program has been extended through 2030. The CARB plans to update the cap-and-trade regulation in 2025 and is considering reforms that would reduce overall allowance budgets to align with CARB's 2022 Climate Change Scoping Plan. 34 During each year of the program, the CARB issues emission allowances (i.e., the rights to emit GHGs) equal to the amount of GHG emissions allowed for that year. Entities with a compliance obligation can obtain allowances from the CARB at quarterly auctions or from third parties or exchanges. Complying entities may also satisfy a portion of their compliance obligation through the purchase of offset credits (e.g., credits for GHG reductions achieved by third parties, such as landowners, livestock owners, and farmers, that occur outside of the entities' facilities through CARB-qualified offset projects such as reforestation or methane capture projects). The Utility expects all costs and revenues associated with the GHG cap-and-trade program to be passed through to customers. The cap-and-trade program applies to the electric generation, large industrial, natural gas, and transportation sectors. The Utility's compliance obligation as a natural gas supplier applies to the GHG emissions attributable to the combustion of natural gas delivered to the Utility's customers other than large natural gas delivery customers that are separately regulated as covered entities and have their own compliance obligations. The federal administration of President Trump has led to uncertainty with regard to what further actions may occur regarding climate change at the federal level.

FY 2025 10-K
Added
Filed Feb 12, 2026

•Renewable and zero-carbon resources supplying 90% of utilities' retail electricity sales to customers by 2035, 95% by 2040, and 100% by 2045. 29 The CARB has also approved GHG emissions reporting and a state-wide, comprehensive program that sets gradually declining limits (or "caps") on the amount of GHGs that may be emitted by major GHG emission sources within different sectors of the economy under a program known as the cap-and-trade program. In 2025, the changes to state law authorized the program through 2045. Entities with a compliance obligation, including entities that supply electricity and natural gas to California consumers, can obtain allowances from the CARB at quarterly auctions or from third parties or exchanges. Complying entities may also satisfy a portion of their compliance obligation through the purchase of offset credits.

de-emphasised PG&E Corporation and the Utility track and report their annual environmental performance results across a broad spectrum of areas.

FY 2024 10-K
Removed
Filed Feb 13, 2025

Emissions Data PG&E Corporation and the Utility track and report their annual environmental performance results across a broad spectrum of areas. The Utility reports its GHG emissions to the CARB and the EPA on a mandatory basis. On a voluntary basis, the Utility reports a more comprehensive emissions inventory to The Climate Registry, a non-profit organization. The following table shows the Utility's third-party verified voluntary GHG inventory reported to The Climate Registry for 2023, which is the most recent data available.

FY 2025 10-K
Added
Filed Feb 12, 2026

Emissions Data PG&E Corporation and the Utility track and report their annual environmental performance results across a broad spectrum of areas. The following table shows the Utility's third-party verified voluntary GHG inventory for 2024, which is the most recent data available. Measuring emissions data involves complex estimates and assumptions, which may change as a result of methodology changes.

reworded Triple Bottom Line

FY 2024 10-K
Removed
Filed Feb 13, 2025

Triple Bottom Line PG&E Corporation's and the Utility's purpose is to deliver for their hometowns, serve the planet, and lead with love. In support of this purpose, the companies employ a Lean operating model designed to drive more effective and responsive decision-making, reduce the difficulties many employees face in their day-to-day work, and deliver better outcomes for customers and communities. PG&E Corporation and the Utility measure their progress toward the purpose by considering their impact on the "triple bottom line" of people, planet, and prosperity, which is underpinned by performance; this consideration takes into account not only the economic value they create for customers and investors, but also their responsibility to social and environmental goals. The triple bottom line is designed to balance the interests of the companies' many stakeholders, and it reflects the broader societal impacts of the companies' activities. PG&E Corporation and the Utility will continue to consider the impact on the triple bottom line of people, planet, and prosperity in their daily operations as well as in their long-term strategic decisions. The Utility will continue to seek fair and timely regulatory treatment to support its customer-driven investment plan while pursuing cost-control measures that would allow it to maintain the affordability of its service. The Lean operating system is an important means of realizing PG&E Corporation's and the Utility's objective of achieving world-class performance while delivering hometown service.

FY 2025 10-K
Added
Filed Feb 12, 2026

This is a combined Annual Report on Form 10-K for PG&E Corporation and the Utility. PG&E Corporation and the Utility are separate entities. Triple Bottom Line PG&E Corporation's and the Utility's purpose is to deliver for their hometowns, serve the planet, and lead with love. In support of this purpose, the companies employ a Lean operating model designed to drive more effective and responsive decision-making, reduce the difficulties many employees face in their day-to-day work, and deliver better outcomes for customers and communities. PG&E Corporation and the Utility measure their progress toward this purpose by considering their impact on the "triple bottom line" of people, planet, and prosperity, which is underpinned by performance; this consideration takes into account not only the economic value they create for customers and investors, but also their responsibility to social and environmental goals. The triple bottom line is designed to balance the interests of the companies' many stakeholders, and it reflects the broader societal impacts of the companies' activities. PG&E Corporation and the Utility will continue to consider the impact on the triple bottom line of people, planet, and prosperity in their daily operations as well as in their long-term strategic decisions. The Utility will continue to seek fair and timely regulatory treatment to support its customer-driven investment plan while pursuing cost-control measures that would allow it to maintain the affordability of its service. The Lean operating system is an important means of realizing PG&E Corporation's and the Utility's objective of achieving world-class performance while delivering hometown service.

reworded Regulatory Environment

FY 2024 10-K
Removed
Filed Feb 13, 2025

Regulatory Environment The Utility's business is subject to the regulatory jurisdiction of various agencies at the federal, state, and local levels. At the state level, the Utility is regulated primarily by the CPUC. At the federal level, the Utility is regulated primarily by the FERC and the NRC. The Utility is also subject to the requirements of other federal, state and local regulatory agencies, including with respect to safety, the environment, and health, such as the NTSB and the OEIS. This section and the "Environmental Regulation" and the "Ratemaking Mechanisms" sections below summarize some of the more significant laws, regulations, and regulatory proceedings affecting the Utility. For more information, see Item 1A. Risk Factors and "Regulatory Matters" in Item 7. MD&A. PG&E Corporation is subject to the Public Utility Holding Company Act as a public utility holding company. The Public Utility Holding Company Act primarily obligates PG&E Corporation and its utility subsidiaries to provide access to their books and records to the FERC and the CPUC for ratemaking purposes.

FY 2025 10-K
Added
Filed Feb 12, 2026

Regulatory Environment The Utility's business is subject to the regulatory jurisdiction of various agencies at the federal, state, and local levels. The Utility is regulated primarily at the state level by the CPUC and at the federal level by the FERC and the NRC. The Utility is also subject to the requirements of other federal, state and local regulatory agencies, including with respect to safety, the environment, and health, such as the NTSB and the OEIS. This section and the "Environmental Regulation" and the "Ratemaking Mechanisms" sections below summarize some of the more significant laws, regulations, and regulatory proceedings affecting the Utility. For more information, see Item 1A. Risk Factors and "Regulatory Matters" in Item 7. MD&A. PG&E Corporation is subject to the Public Utility Holding Company Act as a public utility holding company. The Public Utility Holding Company Act primarily obligates PG&E Corporation and its utility subsidiaries to provide access to their books and records to the FERC and the CPUC for ratemaking purposes.

reworded People

FY 2024 10-K
Removed
Filed Feb 13, 2025

People The people element of the triple bottom line represents PG&E Corporation's and the Utility's commitment to their workforce, their customers, the residents of local communities in which the companies do business, and other stakeholders. 12 PG&E Corporation's and the Utility's goal is to continually reduce risk to keep customers, the communities they serve, and their workforce (both employees and contractors) safe. Their focus is on continuously building an organization where every work activity is designed to facilitate safe performance, every worker knows and practices safe behaviors, and every individual is encouraged to speak up and stop work if they see unsafe or risky behavior, and has confidence that their concerns and ideas will be heard and pursued. PG&E Corporation and the Utility are committed to significantly improving their safety performance by understanding their risks, prioritizing their work, using controls to reduce risks, and continuously measuring and improving risk reduction. PG&E Corporation's and the Utility's human capital resource objectives are to build and retain an engaged, well trained, diverse, and equitably-paid workforce. Their focus is on making it enjoyable to work with and for PG&E Corporation and the Utility. PG&E Corporation and the Utility place a high priority on delivering customer value and providing a hometown customer experience. The Utility's customer-driven investment program is aimed at improving safety, increasing electric and gas service reliability, and improving customer satisfaction.

FY 2025 10-K
Added
Filed Feb 12, 2026

People The people element of the triple bottom line represents PG&E Corporation's and the Utility's commitment to their workforce, their customers, the residents of local communities in which the companies do business, and other stakeholders. 11 PG&E Corporation's and the Utility's goal is to continually reduce risk to keep customers, the communities they serve, and their workforce (both employees and contractors) safe. Their focus is on continuously building an organization where every work activity is designed to facilitate safe performance, every worker knows and practices safe behaviors, and every individual is encouraged to speak up and stop work if they see unsafe or risky behavior, and has confidence that their concerns and ideas will be heard and pursued. PG&E Corporation and the Utility are committed to significantly improving their safety performance by understanding their risks, prioritizing their work, using controls to reduce risks, and continuously measuring and improving risk reduction. PG&E Corporation's and the Utility's human capital resource objectives are to build and retain an engaged, well trained, and equitably-paid workforce. PG&E Corporation and the Utility place a high priority on delivering customer value and providing a hometown customer experience. The Utility's customer-driven investment program is aimed at improving safety, increasing electric and gas service reliability, and improving customer satisfaction.

reworded Ratemaking Mechanisms

FY 2024 10-K
Removed
Filed Feb 13, 2025

Ratemaking Mechanisms The Utility operates under a "cost-of-service" ratemaking model, which means that rates for electric and natural gas utility services are generally set at levels that are intended to allow the Utility to recover its costs of providing service and to earn a return on invested capital. To set rates, the CPUC and the FERC conduct proceedings to determine the amount that the Utility will be authorized to collect from its customers ("revenue requirements"). In the GRC proceedings, the CPUC also generally approves the level of spending on a forecasted basis. Revenue authorized by the CPUC through GRC proceedings is intended to provide the Utility a reasonable opportunity to recover its costs and earn a return on its investments in generation and distribution assets and general plant (also referred to as "rate base"). The Utility's revenue requirements consist primarily of a base amount set to enable the Utility to recover its reasonable operating expenses (e.g., maintenance, administration, and general expenses) and capital costs (e.g., depreciation, and financing expenses).

FY 2025 10-K
Added
Filed Feb 12, 2026

Ratemaking Mechanisms The Utility operates under a "cost-of-service" ratemaking model, which means that rates for electric and natural gas utility services are generally set at levels that are intended to allow the Utility to recover its costs of providing service and have a reasonable opportunity to earn a return on invested capital. To set rates, the CPUC and the FERC conduct proceedings to determine the amount that the Utility will be authorized to collect from its customers ("revenue requirements"). The Utility's revenue requirements consist primarily of a base amount set to enable the Utility to recover its reasonable operating expenses (e.g., maintenance, administration, and general expenses) and capital costs (e.g., depreciation, and financing expenses). The Utility's costs of operating and maintaining the utility system are generally approved in the GRC, and costs of equity and long-term debt are generally approved in the CPUC's cost of capital proceedings.

reworded •taxes; and

FY 2024 10-K
Removed
Filed Feb 13, 2025

•taxes; and •the product of the Utility's rate of return (i.e., the cost of capital for long-term debt and equity) and its rate base. In addition to the Utility's revenue requirement, the CPUC authorizes the Utility to collect revenues to recover costs that the Utility is allowed to "pass through" to customers, including its costs to procure electricity and natural gas for customers and to administer public purpose and customer programs. FERC revenue requirements are set through a FERC-approved formula rate. The Utility's rate of return on electric transmission assets is determined in the FERC TO proceedings. Customer rates are determined by dividing the revenues that the Utility is authorized to collect from customers by the amount of power that the Utility is forecasted to sell. Increases in load spread the Utility's revenue requirement over a larger usage base, which reduces customer rates, but also increases fuel costs, which are passed through to customers. Other than certain gas transmission and storage revenues, the Utility's base revenues are "decoupled" from its sales volume through regulatory balancing accounts, or revenue adjustment mechanisms, that are designed to allow the Utility to collect its authorized base revenue requirements regardless of sales volume. As a result, the Utility's base revenues are not impacted by fluctuations in sales resulting from, for example, weather or economic conditions. The Utility's earnings primarily depend on its ability to manage its base operating and capital costs within its authorized base revenue requirements. Due to the seasonal nature of the Utility's business and rate design, customer electric bills are generally higher during summer months (May to October) because of higher demand, driven by air conditioning loads. Customer bills related to gas service are generally higher during winter months (November to March) because of higher demand due to heating. From time to time, the CPUC may use incentive ratemaking mechanisms that provide the Utility an opportunity to earn additional revenues. For example, the Utility has earned incentives for the successful implementation of energy efficiency programs.

FY 2025 10-K
Added
Filed Feb 12, 2026

As a result, the Utility's CPUC-jurisdictional revenue requirement is the sum of the following: •expenses; •depreciation; •taxes; and •the product of the Utility's rate of return (i.e., the cost of capital for long-term debt and equity) and its rate base (i.e. the value of the Utility's investments in generation and distribution assets and general plant). In addition to the Utility's revenue requirement, the CPUC authorizes the Utility to collect revenues to recover costs that the Utility is allowed to "pass through" to customers, including its costs to procure electricity and natural gas for customers and to administer public purpose and customer programs. FERC revenue requirements are set through a FERC-approved formula rate. The Utility's rate of return on electric transmission assets is determined in the FERC TO proceedings. 18 Customer rates are determined by dividing the revenues that the Utility is authorized to collect from customers by the amount of power that the Utility is forecasted to sell. Increases in load spread the Utility's revenue requirement over a larger usage base, which reduces customer rates, but also increases fuel costs, which are passed through to customers. Other than certain gas transmission and storage revenues, the Utility's base revenues are "decoupled" from its sales volume through regulatory balancing accounts, or revenue adjustment mechanisms, that are designed to allow the Utility to collect its authorized base revenue requirements regardless of sales volume. As a result, the Utility's net income is not impacted by fluctuations in sales. The Utility's earnings primarily depend on its ability to manage its base operating and capital costs within its authorized base revenue requirements. Due to the seasonal nature of the Utility's business and rate design, customer electric bills are generally higher during summer months (May to October) because of higher demand, driven by air conditioning loads. Customer bills related to gas service are generally higher during winter months (November to March) because of higher demand due to heating. From time to time, the CPUC may use incentive ratemaking mechanisms that provide the Utility an opportunity to earn additional revenues. For example, the Utility has earned incentives for the successful implementation of energy efficiency programs.

reworded General Rate Cases

FY 2024 10-K
Removed
Filed Feb 13, 2025

See "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC proceedings. Base Revenues General Rate Cases The GRC is the primary proceeding in which the CPUC determines the amount of base revenue requirements that the Utility is authorized to collect from customers to recover the Utility's anticipated costs related to its electric distribution, natural gas distribution, and Utility-owned electric generation operations and return on rate base. The CPUC conducts a GRC every four years that includes the Utility's costs of its gas transmission and storage facilities. The CPUC approves the annual revenue requirements for the first year (or "test year") of the GRC period and typically authorizes the Utility to receive annual increases in revenue requirements for the subsequent years of the GRC period (known as "attrition years"). Attrition year rate adjustments are generally authorized for cost increases related to invested capital and inflation. Parties to the Utility's GRC include the Public Advocates Office of the CPUC (formerly known as Office of Ratepayer Advocates or ORA) and TURN, which generally represent the interests of residential customers, as well as numerous intervenors that represent other business, community, customer, environmental, and union interests. For more information about the Utility's GRC, see "Regulatory Matters - 2023 General Rate Case" in Item 7. MD&A.

FY 2025 10-K
Added
Filed Feb 12, 2026

See "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC proceedings. Base Revenues General Rate Cases The GRC is the primary proceeding in which the CPUC determines the amount of base revenue requirements that the Utility is authorized to collect from customers to recover the Utility's anticipated costs related to its electric distribution, natural gas distribution, Utility-owned electric generation operations, gas transmission and storage facilities, and an opportunity to earn authorized rate of return from the cost of capital decision. The CPUC conducts a GRC for the Utility every four years. The CPUC approves the annual revenue requirements for the first year (or "test year") of the GRC period and typically authorizes the Utility to receive annual increases in revenue requirements for the subsequent years of the GRC period (known as "attrition years"). Attrition year rate adjustments are generally authorized for cost increases related to invested capital and inflation. Parties to the Utility's GRC include the Public Advocates Office of the CPUC (formerly known as Office of Ratepayer Advocates or ORA) and TURN, which generally represent the interests of residential customers, as well as numerous intervenors that represent other business, community, customer, environmental, and union interests. For more information about the Utility's GRC, see "Regulatory Matters - 2027 General Rate Case" in Item 7. MD&A.

reworded Nuclear Decommissioning Costs

FY 2024 10-K
Removed
Filed Feb 13, 2025

Nuclear Decommissioning Costs The Utility's nuclear power facilities consist of two units at DCPP and the Humboldt Bay independent spent fuel installation. Nuclear decommissioning requires the safe removal of nuclear facilities from service and the reduction of residual radioactivity to a level that permits termination of the NRC license and release of the property for unrestricted use. Nuclear decommissioning costs are generally collected in advance through rates and are held in nuclear decommissioning trusts to be used for the eventual decommissioning of each nuclear unit. The Utility files an application with the CPUC, generally every three years, requesting approval of the Utility's updated estimated decommissioning costs and any rate change necessary to fully fund the nuclear decommissioning trusts to the levels needed to decommission the Utility's nuclear facilities. If the nuclear decommissioning trusts are overfunded, the amount of such overfunding will be returned to customers. Pursuant to Public Utilities Code Section 8325, to the extent the monies available for decommissioning are insufficient to pay for all reasonable and prudent decommissioning costs, the CPUC must authorize the electric utility to collect these charges from its customers.

FY 2025 10-K
Added
Filed Feb 12, 2026

Nuclear Decommissioning Costs The Utility's nuclear power facilities consist of two units at DCPP and the Humboldt Bay independent spent fuel installation. Nuclear decommissioning requires the safe removal of nuclear facilities from service and the reduction of residual radioactivity to a level that permits termination of the NRC license and release of the property for unrestricted use. Nuclear decommissioning costs are generally collected in advance through rates and are held in nuclear decommissioning trusts to be used for the eventual decommissioning of each nuclear unit. The Utility files an application with the CPUC, generally every three years, requesting approval of the Utility's updated estimated decommissioning costs and any rate change necessary to fully fund the nuclear decommissioning trusts to the levels needed to decommission the Utility's nuclear facilities. If the nuclear decommissioning trusts are overfunded, the amount of such overfunding will be returned to customers, and if the nuclear decommissioning trusts are underfunded, the CPUC must authorize the electric utility to collect these charges from its customers.

reworded Employees and Contractors

FY 2024 10-K
Removed
Filed Feb 13, 2025

Employees and Contractors As of December 31, 2024, PG&E Corporation had 10 employees and the Utility had approximately 28,400 regular employees. Of the Utility's regular employees, approximately 17,600 are covered by collective bargaining agreements with the local chapters of three labor unions: the International Brotherhood of Electrical Workers ("IBEW") Local 1245; the Engineers and Scientists of California ("ESC") IFPTE 20; and the Service Employees International Union Local 24/7 ("SEIU"). The collective bargaining agreements in effect for the IBEW Local 1245, ESC Local 20, and SEIU United Service Workers West, are set to expire on December 31, 2025. The agreements increase wages annually by 3.75% from 2022 through 2025 and maintain current contributions to specified benefits. The IBEW, ESC, and SEIU represent approximately 62% of the Utility's employee workforce and support several areas of the Utility's business, including gas and electric operations. The Utility enjoys stable and productive relationships with its unions and did not experience any work stoppages in 2024. 24 PG&E Corporation's employees are primarily at the executive management level. The Utility generally has a stable workforce. The Utility's turnover rate for each of 2024 and 2023 was 4.0%. Approximately 44% of PG&E Corporation's and the Utility's employees have a tenure of more than 10 years, with an average tenure of 11 years. Approximately 18% of PG&E Corporation's and the Utility's employees are eligible to retire. (PG&E Corporation and the Utility define retirement age as 55 years and older.)

FY 2025 10-K
Added
Filed Feb 12, 2026

Employees and Contractors As of December 31, 2025, PG&E Corporation had 10 employees, and the Utility had approximately 29,000 regular employees. Of the Utility's regular employees, approximately 17,500 are covered by collective bargaining agreements with the local chapters of three labor unions: the International Brotherhood of Electrical Workers ("IBEW") Local 1245; the Engineers and Scientists of California ("ESC") International Federation of Professional and Technical Engineers 20; and the Service Employees International Union Local 24/7 ("SEIU"). The collective bargaining agreements in effect for the IBEW Local 1245, ESC Local 20, and SEIU United Service Workers West expired on December 31, 2025, and have been automatically extended for at least one year while the parties negotiate successor agreements. The automatic extension does not cover general wage increases, which must be separately bargained and agreed to for 2026 and beyond. Under prior agreements, wages increased annually by 3.75% from 2022 through 2025. The IBEW, ESC, and SEIU represent approximately 60% of the Utility's employee workforce and support several areas of the Utility's business, including gas and electric operations. The Utility enjoys stable and productive relationships with its unions and did not experience any work stoppages in 2025. PG&E Corporation's employees are primarily at the executive management level. The Utility generally has a stable workforce. The Utility's turnover rate for 2025 was 3.8%. Approximately 46% of PG&E Corporation's and the Utility's employees have a tenure of more than 10 years, with an average tenure of 11 years. Approximately 19% of PG&E Corporation's and the Utility's employees are eligible to retire. (PG&E Corporation and the Utility define retirement age as 55 years and older.)

reworded Human Capital Management

FY 2024 10-K
Removed
Filed Feb 13, 2025

The Utility's contractors and subcontractors include approximately 35,000 individuals from approximately 1,200 contractor companies. Human Capital Management PG&E Corporation's and the Utility's human capital resource objectives are to build and retain an engaged, well trained, diverse, and equitable workforce. PG&E Corporation's and the Utility's Boards of Directors are responsible for overseeing management's development and execution of PG&E Corporation's and the Utility's human capital strategy. To build employee engagement, the Utility has a variety of both executive-level and employee-led initiatives and programs. PG&E Corporation's and the Utility's executive teams meet regularly to discuss and evaluate the state of employee talent, determine which programs are driving engagement and performance, and clarify the specific skills, behaviors, and virtues that should be cultivated. Each year, the Utility honors employees whose work embodies safety, diversity, equity, inclusion, belonging, environmental leadership, innovation, and community service. The Utility conducts an annual employee survey to measure and improve employee engagement. Every year, PG&E Corporation and the Utility offer or require technical, leadership, and employee training, which includes a range of technical training for employees on the knowledge and skills required to perform their jobs safely using approved tools and work procedures. In addition, employees are required to complete annual compliance and ethics training and a Code of Conduct training, both of which are intended to promote a culture in which employees are encouraged to speak up with any concerns or ideas for continuous improvement. In addition, the Utility offers a variety of other trainings and education opportunities. The Utility continues its expanded training for supervisors. Among other programs, the Utility provides career opportunities through its PowerPathway™ workforce development program. Launched in 2008, PowerPathway is a workforce development model to enlarge the talent pool of local, qualified, diverse candidates for skilled craft and utility industry jobs through training program partnerships with educational, community-based and government organizations. PowerPathway helps people throughout the Utility's service area, including women and military veterans, prepare and compete for high demand jobs in the utility and energy industry. Students receive approximately eight weeks of industry-informed curriculum to ensure the academic, job specific, employability skills and physical training necessary to effectively compete for entry-level employment. Programs may also include hands-on training and on-the-job training. PG&E Corporation and the Utility also provide integrated solutions and programs for employee health and wellness that encompass physical, mental, and financial health. These resources include several on-site or near-site health clinics, annual health screenings, health management tools, ergonomic support, and injury management programs, in addition to more traditional programs. PG&E Corporation's and the Utility's financial incentives offered to employees include a Short-Term Incentive Plan ("STIP"), an at-risk part of employee compensation designed to reward eligible employees for achieving specific performance goals. The 2024 STIP was focused on company objectives of safety, customer impact, and financial health.

FY 2025 10-K
Added
Filed Feb 12, 2026

The Utility's contractors and subcontractors include approximately 39,000 individuals from approximately 1,200 contractor companies. Human Capital Management PG&E Corporation's and the Utility's human capital resource objectives are to build and retain an engaged, well trained and equitably-paid workforce. PG&E Corporation's and the Utility's Boards of Directors are responsible for overseeing management's development and execution of PG&E Corporation's and the Utility's human capital strategy. To build employee engagement, the Utility has a variety of both executive-level and employee-led initiatives and programs. PG&E Corporation's and the Utility's executive teams meet regularly to discuss and evaluate the state of employee talent, determine which programs are driving engagement and performance, and clarify the specific skills, behaviors, and virtues that should be cultivated. Each year, the Utility honors employees whose work embodies safety, inclusion and belonging, environmental leadership, innovation, and community service. The Utility conducts employee surveys to measure and improve employee engagement. PG&E Corporation and the Utility offer or require technical, leadership, and employee training, which includes a range of technical training for employees on the knowledge and skills required to perform their jobs safely using approved tools and work procedures. In addition, employees are required to complete annual compliance and ethics training and a Code of Conduct training, both of which are intended to promote a culture in which employees are encouraged to speak up with any concerns or ideas for continuous improvement. In addition, the Utility offers a variety of other trainings and education opportunities. Among other programs, the Utility provides career opportunities through its PowerPathway™ workforce development program. Launched in 2008, PowerPathway is a workforce development model to enlarge the talent pool of local and qualified candidates that reflect the communities the Utility serves for skilled craft and utility industry jobs through training program partnerships with educational, community-based and government organizations. Students receive approximately eight weeks of industry-informed curriculum to ensure the academic, job specific, employability skills and physical training necessary to effectively compete for entry-level employment. PG&E Corporation and the Utility also provide integrated solutions and programs for employee health and wellness that encompass physical, mental, and financial health. These resources include several on-site or near-site health clinics, annual health screenings, health management tools, ergonomic support, and injury management programs, in addition to more traditional programs. PG&E Corporation's and the Utility's financial incentives offered to employees include a Short-Term Incentive Plan ("STIP"), an at-risk part of employee compensation designed to reward eligible employees for achieving specific performance goals. The 2025 STIP was focused on company objectives of safety, customer impact, and financial health. 22

reworded As of December 31, 2025, the Utility owned the following generation facilities, all located in California, listed by energy source and further described below:

FY 2024 10-K
Removed
Filed Feb 13, 2025

Owned Generation Facilities At December 31, 2024, the Utility owned the following generation facilities, all located in California, listed by energy source and further described below:

FY 2025 10-K
Added
Filed Feb 12, 2026

As of December 31, 2025, the Utility owned the following generation facilities, all located in California, listed by energy source and further described below:

reworded Total121 7,815

FY 2024 10-K
Removed
Filed Feb 13, 2025

Elkhorn Battery Energy Storage SystemMonterey County1 183 Photovoltaic (3): Various12 152 Total121 7,815 (1) The Utility's DCPP consists of two nuclear power reactor units, Units 1 and 2. The NRC operating license for Unit 1 expired in 2024. Unit 2 will expire in 2025. Both remain in effect pending completion of the ongoing federal relicensing review. For more information, see "Extension of Diablo Canyon Operations" in Item 7. MD&A below. (2) The Utility's hydroelectric system consists of 94 generating units at 58 powerhouses. All of the Utility's powerhouses are licensed by the FERC (except for one small powerhouse not subject to the FERC's licensing requirements), with license terms between 30 and 50 years. (3) The Utility's large photovoltaic facilities are Cantua solar station (20 MW), Five Points solar station (15 MW), Gates solar station (20 MW), Giffen solar station (10 MW), Guernsey solar station (20 MW), Huron solar station (20 MW), Stroud solar station (20 MW), West Gates solar station (10 MW), and Westside solar station (15 MW). All of these facilities are located in Fresno County, except for Guernsey solar station, which is located in Kings County. 28

FY 2025 10-K
Added
Filed Feb 12, 2026

Elkhorn Battery Energy Storage SystemMonterey County1 183 Photovoltaic (3): Various12 152 Total121 7,815 (1) DCPP consists of two nuclear power reactor units, Units 1 and 2. The NRC operating license for Unit 1 expired in 2024, and the operating license for Unit 2 expired in 2025. Both remain in effect pending completion of the ongoing federal relicensing review. For more information, see "Extension of Diablo Canyon Operations" in Item 7. MD&A below. (2) The Utility's hydroelectric system consists of 94 generating units at 58 powerhouses. All of the Utility's powerhouses are licensed by the FERC (except for one small powerhouse not subject to the FERC's licensing requirements), with license terms between 30 and 50 years. (3) The Utility's large photovoltaic facilities are Cantua solar station (20 MW), Five Points solar station (15 MW), Gates solar station (20 MW), Giffen solar station (10 MW), Guernsey solar station (20 MW), Huron solar station (20 MW), Stroud solar station (20 MW), West Gates solar station (10 MW), and Westside solar station (15 MW). All of these facilities are located in Fresno County, except for Guernsey solar station, which is located in Kings County.

reworded Energy Storage

FY 2024 10-K
Removed
Filed Feb 13, 2025

Energy Storage Energy storage improves system reliability and supports California's decarbonization goals by integrating increased levels of renewable energy. The CPUC has established a multi-year energy storage procurement framework, under which the Utility met its requirements to make 580 MW of qualifying storage capacity operational by 2024. As of December 31, 2024, the Utility owned 183 MW and has contracted for another 2,435 MW of operational energy storage capacity. The Utility has also procured 2,168 MW of battery energy storage to be deployed over the next several years and is working to procure additional battery energy storage to meet its remaining reliability requirements. Separately, the Utility is soliciting long-duration storage, which is storage with at least eight hours of discharge capacity, to have these resources online between 2028 and 2031. In order to address both its bundled portfolio need and to help to meet state planning and policy objectives to increase long-duration storage capacity, the Utility is pursuing regulatory approval to increase the nameplate generating capacity of its Helms Pumped Storage Facility.

FY 2025 10-K
Added
Filed Feb 12, 2026

Energy Storage Energy storage improves system reliability, supports California's decarbonization goals by integrating increased levels of renewable energy, and assists in the event of customer demand growth. The CPUC has established a multi-year energy storage procurement framework, under which the Utility met its requirements to make 580 MW of qualifying storage capacity operational by 2025. As of December 31, 2025, the Utility owned 183 MW and has contracted for another 3,024 MW of operational energy storage capacity. The Utility has also procured 1,884 MW of battery energy storage to be deployed over the next several years and is working to procure additional battery energy storage to meet its remaining reliability requirements. Separately, the Utility solicited and executed an agreement for long-duration storage, which is storage with at least eight hours of discharge capacity, in order to have this resource online by 2031. In September 2025 the CPUC also conditionally authorized the Utility to recover the costs, up to a cap, associated with increasing the nameplate generating capacity of its Helms Pumped Storage Facility.

reworded Electricity Transmission

FY 2024 10-K
Removed
Filed Feb 13, 2025

Electricity Transmission Transmission lines deliver electricity at high voltages and over long distances from power sources to transmission substations closer to customers. A strong transmission system supports reliable and affordable service, ability to meet state energy policy goals, and support for a diverse generation mix, including renewable energy. As of December 31, 2024, the Utility owned approximately 18,000 circuit miles of interconnected transmission lines operating at voltages ranging from 60 kV to 500 kV. The Utility also operated 33 electric transmission substations with a capacity of approximately 67,000 MVA. The Utility's electric transmission system is interconnected with electric power systems in the Western Electricity Coordinating Council, which includes many western states, the Canadian provinces of Alberta and British Columbia, and parts of Mexico.

FY 2025 10-K
Added
Filed Feb 12, 2026

Electricity Transmission Transmission lines deliver electricity at high voltages and over long distances from power sources to transmission substations closer to customers. A strong transmission system supports reliable and affordable service, ability to meet state energy policy goals, and support for a diverse generation mix, including renewable energy. 24 As of December 31, 2025, the Utility owned approximately 18,000 circuit miles of interconnected transmission lines. The Utility also operated 33 electric transmission substations. The Utility's electric transmission system is interconnected with electric power systems in the Western Electricity Coordinating Council, which includes many western states, the Canadian provinces of Alberta and British Columbia, and parts of Mexico.

reworded Electricity Operating Statistics

FY 2024 10-K
Removed
Filed Feb 13, 2025

Electricity Operating Statistics The following table shows certain of the Utility's operating statistics from 2022 to 2024 for electricity sold or delivered, including the classification of revenues by type of service. No single customer of the Utility accounted for 10% or more of consolidated revenues for electricity sold in 2024, 2023, or 2022.

FY 2025 10-K
Added
Filed Feb 12, 2026

Electricity Operating Statistics The following table shows certain of the Utility's operating statistics from 2023 through 2025 for electricity sold or delivered, including the classification of revenues by type of service. No single customer of the Utility accounted for 10% or more of consolidated revenues for electricity sold in 2025, 2024, or 2023.

reworded (1) These amounts include electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers.

FY 2024 10-K
Removed
Filed Feb 13, 2025

Industrial0.1475 0.1294 0.1177 Agricultural0.3597 0.2984 0.2435 Net plant investment per customer$11,460 $10,720 $9,967 (1) These amounts include electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers.

FY 2025 10-K
Added
Filed Feb 12, 2026

Industrial0.1403 0.1475 0.1294 Agricultural0.3636 0.3597 0.2984 Net plant investment per customer$12,710 $11,460 $10,720 (1) These amounts include electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers.

reworded Natural Gas Operating Statistics

FY 2024 10-K
Removed
Filed Feb 13, 2025

In 2024, the Utility continued upgrading transmission pipelines to allow for the use of in-line inspection tools. 31 Natural Gas Operating Statistics The following table shows the Utility's operating statistics from 2022 through 2024 (excluding subsidiaries) for natural gas, including the classification of revenues by type of service. No single customer of the Utility accounted for 10% or more of consolidated revenues for bundled gas sales in 2024, 2023 or 2022.

FY 2025 10-K
Added
Filed Feb 12, 2026

In 2025, the Utility continued upgrading transmission pipelines to allow for the use of in-line inspection tools. 26 Natural Gas Operating Statistics The following table shows the Utility's operating statistics from 2023 through 2025 (excluding subsidiaries) for natural gas, including the classification of revenues by type of service. No single customer of the Utility accounted for 10% or more of consolidated revenues for bundled gas sales in 2025, 2024 or 2023.

reworded Average annual residential usage (Mcf)37 37 37

FY 2024 10-K
Removed
Filed Feb 13, 2025

Subtotal6,047 6,196 6,055 Regulatory balancing accounts (2) 561 808 565 Total operating revenues$6,608 $7,004 $6,620 Selected Statistics: Average annual residential usage (Mcf)37 37 37

FY 2025 10-K
Added
Filed Feb 12, 2026

Subtotal6,763 6,047 6,196 Regulatory balancing accounts (2) (146)561 808 Total operating revenues$6,617 $6,608 $7,004 Selected Statistics: Average annual residential usage (Mcf)37 37 37

reworded Competitive Conditions in the Natural Gas Industry

FY 2024 10-K
Removed
Filed Feb 13, 2025

For risks in connection with increasing competition, see Item 1A. Risk Factors. 33 Competition in the Natural Gas Industry The Utility competes with other natural gas pipeline companies for customers transporting natural gas into the southern California market on the basis of transportation rates, access to competitively priced supplies of natural gas, and the quality and reliability of transportation services. The Utility also competes for storage services with other third-party storage providers, primarily in Northern California.

FY 2025 10-K
Added
Filed Feb 12, 2026

For risks in connection with increasing competition, see Item 1A. Risk Factors. Competitive Conditions in the Natural Gas Industry The Utility competes with other natural gas pipeline companies for customers transporting natural gas into the southern California market on the basis of transportation rates, access to competitively priced supplies of natural gas, and the quality and reliability of transportation services. The Utility also competes for storage services with other third-party storage providers, primarily in Northern California.

reworded See "Ratemaking Mechanisms" below and "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC and FERC proceedings.

FY 2024 10-K
Removed
Filed Feb 13, 2025

Under cost-of-service ratemaking, a utility's earnings depend on the outcomes of its ratemaking proceedings and its ability to manage costs. See "Ratemaking Mechanisms" below and "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC and FERC proceedings. Generally, differences between forecast costs and actual costs can occur for numerous reasons, including the volume of work required and the impact of market forces on the cost of labor and materials. Differences in costs can also arise from changes in laws and regulations at both the state and federal level. Costs can also decrease due to improved efficiencies or waste elimination. PG&E Corporation and the Utility are committed to taking steps to improve their credit ratings and metrics over time, including by reducing PG&E Corporation's debt by $2 billion by the end of 2026. All three credit ratings agencies have increased PG&E Corporation's and the Utility's issuer credit ratings since 2020. In December 2024, PG&E Corporation announced a new dividend policy entailing consistent dividend increases targeting a dividend payout ratio of approximately 20% of core earnings by 2028. For more information, see "Liquidity and Financial Resources - Dividends" in Item 7, MD&A and Note 6 of the Notes to the Consolidated Financial Statements. Total capital expenditures recorded in 2024 were $10.6 billion. The Utility's total capital expenditures (including accruals) are forecasted to be $12.9 billion for 2025, $12.0 billion for 2026, $13.6 billion for 2027, and $14.0 billion for 2028. The Utility has identified additional opportunities for investment in the coming years in addition to its forecast, including investments in transportation electrification capacity, FERC-jurisdictional assets, electric distribution capacity, hydroelectric facilities, energy storage, information technology, and automation. The Utility also plans to submit a cost recovery application for its 10-year distribution undergrounding program pursuant to SB 884. Some of these investments depend on the Utility's ability to generate or obtain the cash to support such investments over this period of time. The completion of projects, the timing of expenditures, and the associated cost recovery may be affected by permitting requirements and delays, construction schedules, availability of labor, equipment and materials, financing, legal and regulatory approvals and developments, community requests or protests, weather, and other unforeseen conditions. The Utility expects to make additional capital expenditures, the recovery of which will be subject to future regulatory approval. These expenditures include capital expenditures exceeding amounts authorized in the 2023 GRC final decision and expenditures to be included in a later filing or separate applications. These expenditures are expected to be primarily for wildfire mitigation and electrification. Additionally, $3.21 billion of fire risk mitigation capital expenditures has been excluded from the Utility's equity base rate pursuant to AB 1054. 14 PG&E Corporation and the Utility are committed to building a safe, reliable, sustainable, and climate-resilient energy system at the lowest possible cost for customers. The Utility's capital investment plan, increasing procurement of renewable power and energy storage, increasing environmental regulations, and the cumulative impact of other public policy requirements collectively place continuing upward pressure on customer rates. Certain CPUC proceedings could impact different types of customers differently. The Utility has set a goal to increase customer capital investments while also limiting customer bill impacts, including by achieving operating cost savings, seeking efficient financing, and benefiting from electric load growth. The Utility plans to meet its cost savings goal through increased efficiencies including waste elimination through the Lean operating system. The Utility expects electric vehicle adoption, data centers, and building electrification to drive load growth. However, the scale of this growth will depend on the Utility's ability to construct necessary infrastructure and the extent of customer demand. The Utility has a number of programs in place to assist low-income customers, such as the CARE program. Under the CARE program, income-qualified customers can receive a monthly discount of 20% or more on their natural gas and electric bill. PG&E Corporation's and the Utility's Corporate Sustainability Report, which is available to the public, describes the companies' progress toward world-class performance measured with the triple bottom line framework.

FY 2025 10-K
Added
Filed Feb 12, 2026

Under cost-of-service ratemaking, a utility's earnings depend on the outcomes of its ratemaking proceedings and its ability to manage costs. 12 See "Ratemaking Mechanisms" below and "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC and FERC proceedings. Generally, differences between forecast costs and actual costs can occur for numerous reasons, including the volume of work required and the impact of market forces on the cost of labor and materials. Differences in costs can also arise from changes in laws and regulations at both the state and federal level. Costs can also decrease due to improved efficiencies or waste elimination. PG&E Corporation and the Utility are committed to taking steps to improve their credit ratings and metrics over time. All three credit ratings agencies have increased PG&E Corporation's and the Utility's issuer credit ratings since 2020. PG&E Corporation's dividend policy entails consistent dividend increases targeting a dividend payout ratio of approximately 20% of core earnings (a non-GAAP financial measure) by 2028. For more information, see Note 6 of the Notes to the Consolidated Financial Statements. Total capital expenditures recorded in 2025 were $13.4 billion. The Utility's total capital expenditures (including accruals) are forecasted to be $12.4 billion for 2026, $13.4 billion for 2027, $15.4 billion for 2028, $16.3 billion for 2029, and $16.0 billion for 2030. The Utility has identified opportunities for investment in the coming years in addition to its forecast, including investments in transmission for data centers and system investments, transportation electrification capacity, hydroelectric facilities, energy storage, information technology, and automation. The Utility plans to submit a 10-year Electric Undergrounding Plan to the OEIS for review. The Utility will then submit an application requesting conditional approval of the plan's costs to the CPUC. Some of these investments depend on the Utility's ability to generate or obtain the cash to support such investments over this period of time. The completion of projects, the timing of expenditures, and the associated cost recovery may be affected by permitting requirements and delays, construction schedules, availability of labor, equipment and materials, financing, legal and regulatory approvals and developments, community requests or protests, weather, and other unforeseen conditions. Additionally, $2.85 billion of fire risk mitigation capital expenditures will be excluded from the Utility's equity rate base pursuant to SB 254. The Utility expects to make additional capital expenditures, the recovery of which will be subject to future regulatory approval. These expenditures include capital expenditures exceeding amounts authorized in the 2023 GRC final decision and expenditures to be included in a later filing or separate applications. These expenditures are expected to be primarily for wildfire mitigation and electrification. PG&E Corporation and the Utility are committed to building a safe, reliable, sustainable, and climate-resilient energy system at an affordable cost for customers. The Utility's capital investment plan, increasing procurement of renewable power and energy storage, increasing environmental regulations, and the cumulative impact of other public policy requirements collectively place continuing upward pressure on customer rates. Certain CPUC proceedings could impact different types of customers differently. The Utility has set a goal to increase customer capital investments while also limiting customer bill impacts, including by achieving operating cost savings, seeking efficient financing, and benefiting from electric load growth that reduces other customers' bills. The Utility plans to meet its cost savings goal through increased efficiencies including waste elimination through the Lean operating system. The Utility expects data centers, electric vehicle adoption, and building electrification to drive load growth. For more information see "Competition" below. The Utility has a number of programs in place to assist low-income customers, such as the CARE program. Under the CARE program, income-qualified customers can receive a monthly discount of 20% or more on their natural gas and electric bill. The Utility has set a goal to limit average annual customer rate increases to 3%. PG&E Corporation's and the Utility's Corporate Sustainability Report, which is available to the public, describes the companies' progress toward world-class performance measured with the triple bottom line framework. 13

reworded •Economy-wide State carbon neutrality by 2045, with net negative emissions thereafter.

FY 2024 10-K
Removed
Filed Feb 13, 2025

•50% of retail energy sales to customers from renewable energy sources by 2026 and 60% by 2030. •Economy-wide State carbon neutrality by 2045, with net negative emissions thereafter.

FY 2025 10-K
Added
Filed Feb 12, 2026

•60% of retail electricity sales to customers from renewable energy sources by 2030. •Economy-wide State carbon neutrality by 2045, with net negative emissions thereafter.

reworded Adapting to the Physical Impacts of Climate Change

FY 2024 10-K
Removed
Filed Feb 13, 2025

Adapting to the Physical Impacts of Climate Change Effectively managing physical climate risk will become increasingly critical as the physical impacts of climate change become increasingly frequent and severe over the coming years in California. The Utility's climate resilience efforts continue to focus on characterizing and mitigating the physical impacts of climate change to the Utility's infrastructure, assets, and operations. The Utility is making substantial investments to build a more resilient system that can better withstand extreme weather and related emergencies. For more information on such investments, see "Performance: Underpinning the Triple Bottom Line" above. A key element of preparing the Utility for the physical risks of climate change is a system-wide CAVA of the Utility's assets, operations, and services, filed with the CPUC in May 2024. The CAVA improves the Utility's understanding of its exposure to climate hazards and the sensitivity of assets and operations to these hazards, and provides the basis for necessary climate resilience investments. The Utility is using the CAVA to inform changes to design and construction standards for equipment and facilities, in order to increase infrastructure resilience. The Utility plans to continue identifying priority adaptive actions by incorporating results from the CAVA into its risk management, planning, and asset management functions. The Utility works to incorporate into its operations scientific information by reviewing relevant scientific literature and to incorporate customer and community perspectives based on its engagement with CPUC-designated disadvantaged and vulnerable communities in the CAVA process. The Utility's commitment to increasing resilience to climate change includes aligning its resources and business strategy with California's clean energy goals, and advocating for policies and programs that enable safe and reliable energy for the Utility's customers in light of climate change. For example, the Utility believes its strategies to reduce GHG emissions through a portfolio of customer programs, infrastructure improvements, and the use of renewable energy and energy storage will help it adapt to the expected increases in demand for electricity. PG&E Corporation and the Utility are also making progress on transitioning the gas system to cleaner fuels and supporting efforts to accelerate building electrification. The objective is to do so in an orderly manner to achieve a positive customer and community experience, while reducing natural gas system investments in targeted electrified communities.

FY 2025 10-K
Added
Filed Feb 12, 2026

Adapting to the Physical Impacts of Climate Change Effectively managing physical climate risk will become increasingly critical as the physical impacts of climate change become increasingly frequent and severe over the coming years in California. The Utility's climate resilience efforts continue to focus on characterizing and mitigating the physical impacts of climate change to the Utility's infrastructure, assets, and operations. The Utility is making substantial investments to build a more resilient system that can better withstand extreme weather and related emergencies. For more information on such investments, see "Performance: Underpinning the Triple Bottom Line" above. A key element of preparing the Utility for the physical risks of climate change is a system-wide CAVA of the Utility's assets, operations, and services, filed with the CPUC in 2024. The CAVA improves the Utility's understanding of its exposure to climate hazards and the sensitivity of assets and operations to these hazards, and provides the basis for necessary climate resilience investments. The Utility is currently developing the next CAVA, which is expected to be more granular than the previous climate vulnerability assessment and will be submitted to the CPUC in 2027. The Utility is using the CAVA to inform changes to design and construction standards for equipment and facilities in order to increase infrastructure resilience. The Utility plans to continue identifying priority adaptive actions by incorporating results from the CAVA into its risk management, planning, and asset management functions. The Utility works to incorporate scientific information into its operations by reviewing relevant scientific literature. The Utility also works to incorporate customer and community perspectives in the CAVA process based on its engagement with CPUC-designated disadvantaged and vulnerable communities. The Utility's commitment to increasing resilience to climate change includes aligning its resources and business strategy with California's clean energy goals and advocating for policies and programs that enable safe and reliable energy for the Utility's customers in light of climate change. For example, the Utility believes its strategies to reduce GHG emissions through a portfolio of customer programs, infrastructure improvements, and the use of renewable energy and energy storage will help it adapt to the expected increases in demand for electricity. PG&E Corporation and the Utility are also making progress on transitioning the gas system to cleaner fuels and supporting efforts to accelerate building electrification. Their objective is to do so in an orderly manner to achieve a positive customer and community experience, while reducing natural gas system investments in targeted electrified communities.

reworded 36,445,372

FY 2024 10-K
Removed
Filed Feb 13, 2025

Scope 1 and 2 emissions (1) 4,026,490 Scope 3 emissions (2) 39,446,426 (1) Scope 1 emissions are direct emissions from the Utility's operations and Scope 2 emissions are indirect emissions from facility electricity use and electric line losses. 36 (2) Scope 3 emissions are emissions resulting from downstream value chain activities not owned or controlled by the Utility but that which can be indirectly impacted by the Utility's actions. The majority of these emissions came from customer natural gas use. The Utility utilized the CEC's Power Source Disclosure program methodology to calculate the CO2 emissions rate associated with the electricity delivered to retail customers in 2023. This resulted in a third-party verified CO2 emissions rate of 12 pounds of CO2 per MWh.

FY 2025 10-K
Added
Filed Feb 12, 2026

Scope 1 and 2 emissions (1) 3,391,499 Scope 3 emissions (2) 36,445,372 (1) Scope 1 emissions are direct emissions from the Utility's operations and Scope 2 emissions are indirect emissions from facility electricity use and electric line losses. (2) Scope 3 emissions are emissions resulting from downstream value chain activities not owned or controlled by the Utility but that which can be indirectly impacted by the Utility's actions. The majority of these emissions came from customer natural gas use. 31 The Utility achieved a third-party verified CO2 emissions rate of 16 pounds of CO2 per MWh for electricity delivered to retail customers in 2024, using the CEC's Power Source Disclosure program methodology.

  FY2023 → FY2024 Text Diffs 

escalated Electricity Transmission Owner Rate Cases The current filing adds detail explaining that the FERC typically authorizes new rates subject to refund before a final decision, requiring the Utility to bill based on requested amounts in its rate case filing and record a reserve for probable refunds.

FY 2023 10-K
Removed
Filed Feb 22, 2024

Electricity Transmission Owner Rate Cases The FERC determines the amount of authorized revenue requirements, including the rate of return on electric transmission assets, that the Utility may collect through rates in the TO rate case. In its TO rate cases, the Utility uses a formula rate methodology, which includes an authorized revenue requirement and rate base for a given year but also provides for an annual update of the previous year's revenue requirement and rates in accordance with the terms of the FERC-approved formula. Under the formula rate mechanism, transmission revenue requirements are updated to the actual cost of service annually as part of the true-up process. Differences between amounts collected and determined under the formula rate are either collected from or refunded to customers. These FERC-approved rates are included by the CPUC in the Utility's retail electric rates and by the CAISO in its transmission access charges to wholesale customers. For more information, see "Regulatory Matters - Transmission Owner Rate Cases" in Item 7. MD&A. The Utility also recovers a portion of its revenue requirements for its wholesale electric transmission costs through charges collected under specific contracts with wholesale transmission customers that the Utility entered into before the CAISO began its operations. These wholesale customers are charged individualized rates based on the terms of their contracts. 24

FY 2024 10-K
Added
Filed Feb 13, 2025

Electricity Transmission Owner Rate Cases The FERC determines the amount of authorized revenue requirements, including the rate of return on electric transmission assets, that the Utility may collect through rates in TO rate cases. In its TO rate cases, the Utility uses a formula rate methodology, which includes an authorized revenue requirement and rate base for a given year but also provides for an annual update of the previous year's revenue requirement and rates in accordance with the terms of the FERC-approved formula. Under the formula rate mechanism, transmission revenue requirements are updated to the actual cost of service annually as part of the true-up process. Differences between amounts collected and determined under the formula rate are either collected from or refunded to customers. The FERC typically authorizes the Utility to charge new rates based on the requested revenue requirement, subject to refund, before the FERC has issued a final decision. The Utility bills and records revenue based on the amounts requested in its rate case filing and records a reserve for its estimate of the amounts that are probable of refund. These FERC-approved rates are included by the CPUC in the Utility's retail electric rates and by the CAISO in its transmission access charges to wholesale customers. For more information, see "Regulatory Matters - Transmission Owner Rate Cases" in Item 7. MD&A. The Utility also recovers a portion of its revenue requirements for its wholesale electric transmission costs through charges collected under specific contracts with wholesale transmission customers that the Utility entered into before the CAISO began its operations. These wholesale customers are charged individualized rates based on the terms of their contracts.

escalated Diversity, Equity, Inclusion, and Belonging The company expanded its approach by adding a focus on integrating inclusion and belonging into the employee experience, specifically targeting equity and interrupting bias in hiring, promotion, retention, and compensation. Furthermore, the demographic reporting was updated from age ranges to generational data for 2024, noting that Millennials (49%), Generation X (37%), and Boomers (10%) are the largest groups.

FY 2023 10-K
Removed
Filed Feb 22, 2024

Diversity, Equity, Inclusion, and Belonging PG&E Corporation's and the Utility's goal is to foster a diverse, equitable, and inclusive workforce culture where all employees find it enjoyable to work with and for PG&E Corporation and the Utility and feel they belong. These efforts are led by PG&E Corporation's and the Utility's Executive Vice President, Chief People Officer, in partnership with the executive team. The People and Compensation Committee of PG&E Corporation's Board of Directors reviews the companies' diversity, equity, inclusion, and belonging strategy, practices, and performance. Key elements of PG&E Corporation's and the Utility's approach include active programming to heighten cultural awareness, encourage understanding and appreciation of diversity, and integrate thoughtful content into training, development, and performance support resources. Additionally, the Utility's 12 Employee Resource Groups and three Engineering Network Groups execute enterprise-wide employee programming, nominated employees lead efforts within their departments, and other specialized teams facilitate dialogue across the companies. In 2023, women, minorities, and military veterans accounted for approximately 26%, 50%, and 7%, respectively, of total PG&E Corporation and Utility employees. Approximately 9% of the Utility's employees are younger than 30, 62% are between the ages of 30 and 49, and 29% are 50 or older. 28

FY 2024 10-K
Added
Filed Feb 13, 2025

Diversity, Equity, Inclusion, and Belonging PG&E Corporation's and the Utility's goal is to foster a diverse, equitable, and inclusive workforce culture where all employees find it enjoyable to work with and for PG&E Corporation and the Utility and feel they belong. These efforts are led by PG&E Corporation's and the Utility's Executive Vice President, Chief People Officer, in partnership with the executive team. The People and Compensation Committee of PG&E Corporation's Board of Directors reviews the companies' diversity, equity, inclusion, and belonging strategy, practices, and performance. Key elements of PG&E Corporation's and the Utility's approach to diversity, equity, inclusion, and belonging include integrating inclusion and belonging into the employee experience with a focus on equity and interrupting bias in hiring, promotion, retention and compensation, heightened cultural awareness programming to encourage understanding and importance of inclusion and belonging, and integrating useful content into training, development, and performance support resources. Additionally, the Utility's 12 Employee Resource Groups and three Engineering Network Groups execute enterprise-wide employee programming, nominated employees lead efforts within their departments, and across the companies. Specialized teams facilitate awareness, education and dialogue and support the groups at the enterprise level. In 2024, women, minorities, and military veterans accounted for approximately 26%, 50%, and 7%, respectively, of total PG&E Corporation and Utility employees. The Utility's employees represent five generations, most of whom are Millennials (49%), Generation X (37%), and Boomers (10%). Generational data refers to "Millennials" for individuals born between 1981 and 1996, "Generation X" between 1965 and 1980, and "Boomers" between 1946 and 1964.

escalated (1) This amount excludes electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers.

FY 2023 10-K
Removed
Filed Feb 22, 2024

(1) This amount excludes electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers. (2) The allocation of "Others, net" in the "CEC Reporting Methodology Adjustment" and "Power Content Label" columns is consistent with current CEC guidelines as an adjustment mechanism to apply, as specified. Total reported generation and procurement volumes equate to actual electric retail sales. (3) Amounts include biopower (e.g., biogas, biomass), solar, wind, certain hydroelectric (i.e., 30MW or less), and geothermal facilities. The eligible renewable percentages above do not reflect RPS compliance, which is determined using a different methodology.

FY 2024 10-K
Added
Filed Feb 13, 2025

TOTAL100 %- %100 % Total renewable energy resources (3) 23 %- %23 % GHG-free resources (6) 98 %- %98 % (1) This amount excludes electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers. (2) The allocation of "Others, net" in the "CEC Reporting Methodology Adjustment" and "Power Content Label" columns is consistent with current CEC guidelines as an adjustment mechanism to apply, as specified. Total reported generation and procurement volumes equate to actual electric retail sales. (3) Amounts include biopower (e.g., biogas, biomass), solar, wind, certain hydroelectric (i.e., 30MW or less), and geothermal facilities. The eligible renewable percentages above do not reflect RPS compliance, which is determined using a different methodology.

escalated Performance: Underpinning the Triple Bottom Line The most substantial change is the introduction of a new "System hardening" effort, which involves repairing and replacing equipment in high fire risk areas, including undergrounding 259 miles of lines and bringing online 11 remote grids. Furthermore, the Utility expanded the EPSS program to all high fire risk areas and transitioned asset inspections to use aerial drones for circuits in HFTD areas.

FY 2023 10-K
Removed
Filed Feb 22, 2024

In 2022, the Utility spent $4.79 billion with certified diverse suppliers, representing 39.3% of its total spend. 14 Performance: Underpinning the Triple Bottom Line PG&E Corporation and the Utility use the Lean operating system, which includes five basic "plays": visual management; operating reviews; problem solving; standard work; and waste elimination. Visual management allows teams to see how they are performing against their most important metrics using real-time data. Teams throughout PG&E Corporation and the Utility hold daily, weekly, and monthly operating reviews designed to align the performance of workers closest to the work with the goals and objectives of senior leadership. These brief meetings help the Utility identify gaps and quickly develop plans to support the teams performing the work and give the Utility more visibility, control and predictability in its operations. Problem solving involves a structured approach to identifying, containing, analyzing, and solving problems in order to capitalize on opportunities. Standard work reduces costs and increases productivity by establishing a consistent company-wide method for completing a task. For instance, the Lean operating system helped the Utility identify patterns in the conditions of ignitions and led to the implementation of EPSS, which drove a significant reduction in facility ignitions. PG&E Corporation's and the Utility's performance is also driven by an increased focus on alignment of shared outcomes among its leadership and within the organization. Waste elimination, the fifth Lean play, was deployed in 2023 and enables the companies to identify and eliminate inefficiencies in both process and workflow in a sustainable manner and drive the continued adoption of consistent processes and improvements to financial visibility and controls. In 2023, the Utility implemented PG&E's Safety Excellence Management System, which is a more systematic approach to assess risk and evaluate or implement controls for safe operation based on industry standards. PG&E Corporation and the Utility have implemented a regional service model to bring the Utility closer to the hometowns it serves. Through the regional service model, the Utility has restructured its service area into five regions, with leaders assigned for each region to deliver improved public and employee safety, customer service, and operational reliability outcomes. PG&E Corporation and the Utility are committed to designing an electric system that is resilient to climate change, decarbonized, and optimized to local and system needs. California has experienced unprecedented weather conditions in recent years and the Utility's service area remains susceptible to additional wildfire activity. In response, the Utility has implemented operational changes and investments that reduce wildfire risk, including: •Enhanced Powerline Safety Settings: EPSS adjusts the sensitivity of circuit protection devices on selected power lines to de-energize them in less than one-tenth of a second in the event of a disturbance to help prevent potential ignitions. After EPSS was initiated, both the size and number of CPUC-reportable ignitions were reduced substantially on EPSS-enabled circuits, compared to the prior three-year average. •Public Safety Power Shutoffs: The PSPS program proactively de-energizes power lines in response to forecasted weather conditions. Since its inception in late 2017, the PSPS program has become more targeted through the use of more granular risk models, including incorporating more detailed data inputs. The Utility has also installed sectionalizers for more targeted de-energizations of circuits and transmission lines. These more targeted scoping criteria are engineered to reduce the number of customers impacted by any particular PSPS event. In 2023, the Utility had two PSPS events impacting a total of 5,099 customers. •Vegetation management: The Utility inspects its overhead electric distribution and transmission facilities on an annual basis to identify and clear vegetation that might grow or fall into utility equipment. The Utility is also increasing oversight and engagement with the contractors supporting vegetation management work. •Asset inspections: Since 2018, the Utility has reoriented its asset inspections programs toward asset condition and consequence risk, particularly wildfire risk, and these programs have become more thorough, standardized, digitized, and verifiable. The Utility uses risk-informed inspection cycles. In 2023, the Utility continued to refine its risk modeling, including further incorporating data from asset inspections. As a result of the improved inspection program, the Utility's inspections in recent years have begun to more thoroughly identify equipment conditions. 15

FY 2024 10-K
Added
Filed Feb 13, 2025

In 2023, the Utility spent $4.18 billion with certified diverse suppliers, representing 36.6% of its total spend. Performance: Underpinning the Triple Bottom Line PG&E Corporation and the Utility use the Lean operating system, which includes five basic "plays": visual management; operating reviews; problem solving; standard work; and waste elimination. Visual management allows teams to see how they are performing against their most important metrics using real-time data. Teams throughout PG&E Corporation and the Utility hold daily, weekly, and monthly operating reviews designed to align the performance of employees closest to the work with the goals and objectives of senior leadership. These brief meetings help the Utility identify gaps and quickly develop plans to support the teams performing the work and give the Utility more visibility, control and predictability in its operations. Problem solving involves a structured approach to identifying, containing, analyzing, and solving problems in order to capitalize on opportunities. Standard work reduces costs and increases productivity by establishing a consistent company-wide method for completing a task. For instance, the Lean operating system helped the Utility identify patterns in the conditions of ignitions and led to the implementation of EPSS, which drove a significant reduction in facility ignitions. PG&E Corporation's and the Utility's performance is also driven by an increased focus on alignment of shared outcomes among its leadership and within the organization. Waste elimination, the fifth Lean play, was deployed in 2023 and enables the companies to identify and eliminate inefficiencies in both process and workflow in a sustainable manner and drive the continued adoption of consistent processes and improvements to financial visibility and controls. In 2023, the Utility implemented PG&E's Safety Excellence Management System, which is a more systematic approach to assess risk and evaluate or implement controls for safe operation based on industry standards. PG&E Corporation and the Utility have implemented a regional service model to bring the Utility closer to the hometowns it serves. Through the regional service model, the Utility has restructured its service area into five regions, with leaders assigned for each region to deliver improved public and employee safety, customer service, and operational reliability outcomes. California has experienced unprecedented weather conditions in recent years and the Utility's service area remains susceptible to additional wildfire activity. In response, the Utility has implemented operational changes and investments that reduce wildfire risk, including: •Enhanced Powerline Safety Settings: EPSS adjusts the sensitivity of circuit protection devices on selected power lines to de-energize them in less than one-tenth of a second in the event of a disturbance to help prevent potential ignitions. In recent years, the Utility expanded the EPSS program to all high fire risk areas and reviewed and adjusted settings to improve coordination among devices on a circuit to reduce the number of customers impacted by an outage. After EPSS was initiated, both the size and number of CPUC-reportable ignitions were reduced substantially on EPSS-enabled circuits, compared to the prior three-year average. •Public Safety Power Shutoffs: The PSPS program proactively de-energizes power lines in response to forecasted weather conditions. Since its inception in late 2017, the PSPS program has become more targeted through the use of more granular risk models, including incorporating more detailed data inputs. The Utility has also installed sectionalizers for more targeted de-energizations of circuits and transmission lines. These more targeted scoping criteria are engineered to reduce the number of customers impacted by any particular PSPS event. In 2024, the Utility executed six PSPS events impacting a total of approximately 50,000 customers. 15 •Vegetation management: The Utility inspects its overhead electric distribution and transmission facilities on an annual basis to identify and clear vegetation that might grow or fall into utility equipment. •Asset inspections: Since 2018, the Utility has reoriented its asset inspections programs toward asset condition and consequence risk, particularly wildfire risk, and these programs have become more thorough, standardized, digitized, and verifiable. The Utility uses risk-informed inspection cycles. In 2024, the Utility continued to refine its inspection techniques, transitioning to the use of aerial drones to perform inspections on circuits located in HFTD areas. As a result of the improved inspection program, the Utility's inspections in 2024 have further enhanced its ability to identify equipment conditions. •System hardening: System hardening entails repairing, replacing, or eliminating existing power lines in HFTD areas and installing stronger and more resilient equipment. As the Utility's asset inspections have identified less resilient equipment, the Utility has hardened its system by fixing significantly more equipment than in prior years. Hardening methods also include replacing bare overhead conductor with covered conductor and installing stronger poles, removing lines, and serving customers through remote grids, or converting lines from overhead to underground. The Utility has set a goal to underground 10,000 miles of electric distribution lines in high wildfire risk areas. Undergrounding can substantially reduce ignition risk and improve reliability during storms or periods of high wildfire risk. In 2024, the Utility undergrounded 259 miles of lines. When feasible, remote grids can be a more cost-effective option to reduce fire risks by permanently disconnecting end-of-line customers from the grid and serving them with utility owned, locally sited resources. The Utility brought online five additional remote grids in 2024, for a total of 11 remote grids overall.

de-emphasised PG&E Corporation's and the Utility's operating revenues, income, and total assets can be found below in Item 8. Financial Statements and Supplementary Data.

FY 2023 10-K
Removed
Filed Feb 22, 2024

PG&E Corporation's and the Utility's operating revenues, income, and total assets can be found below in Item 8. Financial Statements and Supplementary Data. The principal executive offices of PG&E Corporation and the Utility are located at 300 Lakeside Drive, Oakland, California 94612. PG&E Corporation's telephone number is (415) 973-1000 and the Utility's telephone number is (415) 973-7000. This is a combined Annual Report on Form 10-K for PG&E Corporation and the Utility. Each of PG&E Corporation and the Utility is a separate entity. This 2023 Form 10-K contains forward-looking statements that are necessarily subject to various risks and uncertainties. For a discussion of the significant risks that could affect the outcome of these forward-looking statements and PG&E Corporation's and the Utility's future financial condition, results of operations, liquidity, and cash flows, see Item 1A. Risk Factors and "Forward-Looking Statements" above.

FY 2024 10-K
Added
Filed Feb 13, 2025

PG&E Corporation's and the Utility's operating revenues, income, and total assets can be found below in Item 8. Financial Statements and Supplementary Data. The principal executive offices of PG&E Corporation and the Utility are located at 300 Lakeside Drive, Oakland, California 94612. PG&E Corporation's telephone number is (415) 973-1000 and the Utility's telephone number is (415) 973-7000. This is a combined Annual Report on Form 10-K for PG&E Corporation and the Utility. Each of PG&E Corporation and the Utility is a separate entity.

de-emphasised Planet The disclosure was significantly reduced, removing all detailed discussions regarding physical climate risks such as extreme heat, coastal flooding, and wildfires, including the planned system-wide CVA update. Additionally, the commitment language in Paragraph 2 was strengthened to include "sustainable" and "climate-resilient energy system."

FY 2023 10-K
Removed
Filed Feb 22, 2024

For more information, see "Human Capital" below. Planet The planet element of the triple bottom line represents PG&E Corporation's and the Utility's commitment to protect and serve the environment. This commitment extends beyond compliance with various state and federal environmental, health, and safety laws and regulations. PG&E Corporation and the Utility believe that integrating and managing climate change and other environmental considerations in the companies' business strategies creates long-term value for PG&E Corporation and the Utility, and for their customers, communities, coworkers, and other stakeholders. Mitigating and adapting to the impacts of climate change presents opportunities for growth for the Utility's business and economic opportunity for the communities it serves. The Utility is committed to delivering safe, clean, affordable, and reliable energy in the face of increasingly severe and extreme climate-driven natural hazards. To build resilience to these hazards, the Utility is working to systematically integrate forward-looking climate data and tools into its decision-making. PG&E Corporation and the Utility also work with policymakers and regulators to advance effective climate change policy in California, and work directly with local governments and communities on adaptation solutions. PG&E Corporation and the Utility are also committed to helping heal the planet. PG&E Corporation's and the Utility's Climate Strategy Report, which is available to the public, describes the companies' climate goals and plans to meet those goals. To meet their longer-term climate goals, PG&E Corporation and the Utility intend to scale their efforts to decarbonize the energy system to accommodate a shift to vehicle electrification, integrate a proliferation of distributed energy resources, and achieve increased penetration of renewable energy combined with investments in the grid and energy storage. PG&E Corporation and the Utility are also making progress on transitioning the gas system to cleaner fuels and supporting efforts to accelerate building electrification. The objective is to do so in an orderly manner to achieve a positive customer and community experience, while reducing natural gas system investments in targeted electrified communities. The impacts of climate change on the Utility's infrastructure are already a reality. Record-breaking extreme heat and heat waves are increasingly a regular occurrence throughout California. Peak electric loads are expected to increase with increasing temperatures due to direct impacts of ambient temperatures on equipment and direct impacts on electricity demand driven by rising air conditioning installation and usage, and increasingly driven in the future from widespread progress in adoption of strategic electrification technologies. The Utility's assets on the coast and in or near watersheds face potential increased exposures to coastal, riverine, and precipitation-related flooding because of climate-driven changes in precipitation and sea-level rise. 12 Climate change will also continue to intensify the potential for wildfires throughout California. The worsening conditions across California increase the likelihood and severity of wildfires, including those where the Utility's equipment may be alleged to be associated with the fire's ignition. Reducing risk will be even more important as climate change continues to exacerbate the risks facing the Utility. A key element of preparing the Utility for the physical risks of climate change is an updated and more detailed system-wide CVA of the Utility's assets, operations, and services, which the Utility expects to file with the CPUC in mid-2024. The CVA is expected to improve the Utility's understanding of its exposure to climate hazards and the sensitivity of assets and operations to these hazards. PG&E Corporation and the Utility continue to pursue policies and programs that enable safe, reliable, and affordable clean and resilient energy for their customers. As a result of actions already taken by PG&E Corporation and the Utility, the companies have:

FY 2024 10-K
Added
Filed Feb 13, 2025

For more information, see "Human Capital" below. Planet The planet element of the triple bottom line represents PG&E Corporation's and the Utility's commitment to protect and serve the environment. This commitment extends beyond compliance with various state and federal environmental, health, and safety laws and regulations. PG&E Corporation and the Utility believe that integrating and managing climate change and other environmental considerations in the companies' business strategies creates long-term value for PG&E Corporation and the Utility, and for their customers, communities, employees, and other stakeholders. The Utility is committed to delivering a safe, reliable, sustainable, and climate-resilient energy system at the lowest possible cost in the face of increasingly severe and extreme climate-driven natural hazards. To build resilience to these hazards, the Utility is working to systematically integrate forward-looking climate data and tools into its decision-making. PG&E Corporation and the Utility also work with policymakers and regulators to advance effective climate change policy in California, and work directly with local governments and communities on adaptation solutions. PG&E Corporation and the Utility are also committed to helping heal the planet. PG&E Corporation's and the Utility's 2022 Climate Strategy Report, which is available to the public, describes the companies' climate goals and plans to meet those goals. To meet their longer-term climate goals, PG&E Corporation and the Utility intend to scale their efforts to decarbonize the energy system to accommodate a shift to vehicle electrification, integrate a proliferation of distributed energy resources, and achieve increased utilization of renewable energy combined with investments in the grid and energy storage. PG&E Corporation and the Utility continue to pursue policies and programs that enable safe, reliable, affordable, clean, and resilient energy for their customers. As a result of actions already taken by PG&E Corporation and the Utility, the companies have:

de-emphasised Energy Storage

FY 2023 10-K
Removed
Filed Feb 22, 2024

Energy Storage Energy storage improves system reliability and supports California's decarbonization goals by integrating increased levels of renewable energy. The CPUC has established a multi-year energy storage procurement framework, under which the Utility was required to procure 580 MW of qualifying storage capacity by the end of 2020, with all energy storage projects required to be operational by the end of 2024. As of December 31, 2023, the Utility was on track to meet its storage goals by the end of 2024. Additionally, the Utility has been actively procuring energy storage to meet critical reliability needs. The CPUC previously approved more than 1,100 MW of storage to come online in 2022 and 2023. In January 2022, the Utility also requested CPUC approval for another 1,600 MW of storage to be completed by the summer of 2024, which would bring the Utility's total energy storage system capacity to more than 3,330 MW. Finally, the Utility is soliciting 200 MW of long-duration storage, which is storage with at least eight hours of discharge capacity, to have these resources online between 2026 and 2028. In order to address both its bundled portfolio need and to help to meet State planning and policy objectives to increase long-duration storage capacity after 2028, the Utility is pursuing regulatory approval to increase the nameplate generating capacity of its Helms Pumped Storage Facility. 30

FY 2024 10-K
Added
Filed Feb 13, 2025

Energy Storage Energy storage improves system reliability and supports California's decarbonization goals by integrating increased levels of renewable energy. The CPUC has established a multi-year energy storage procurement framework, under which the Utility met its requirements to make 580 MW of qualifying storage capacity operational by 2024. As of December 31, 2024, the Utility owned 183 MW and has contracted for another 2,435 MW of operational energy storage capacity. The Utility has also procured 2,168 MW of battery energy storage to be deployed over the next several years and is working to procure additional battery energy storage to meet its remaining reliability requirements. Separately, the Utility is soliciting long-duration storage, which is storage with at least eight hours of discharge capacity, to have these resources online between 2028 and 2031. In order to address both its bundled portfolio need and to help to meet state planning and policy objectives to increase long-duration storage capacity, the Utility is pursuing regulatory approval to increase the nameplate generating capacity of its Helms Pumped Storage Facility.

de-emphasised •Helped customers avoid emissions and manage energy costs through robust energy efficiency programs. The Utility significantly increased its deployed capacity, raising managed battery storage contracts from over 3.5 GW to more than 4.6 GW, while also expanding vehicle infrastructure by installing over 3,800 charging ports (up from 475) and growing home battery storage customers from 70,000 to over 120,000; additionally, the disclosure removed the detailed forward-looking section regarding IRP requirements and GHG energy mix projections.

FY 2023 10-K
Removed
Filed Feb 22, 2024

•Delivered electricity to customers in 2023 that was 100% GHG free (see "Electricity Resources" below for more information). •Helped customers avoid emissions and manage energy costs through robust energy efficiency programs. •Managed contracts for more than 3.5 GW of battery energy storage to be deployed over the next several years and operated 183 MW of Utility-owned battery storage, strengthening California's grid efficiency and reliability. •Helped enable the total number of electric vehicles operating in the Utility's service area to exceed 550,000; installed more than 475 charging ports for electric vehicles at schools, public charging locations, and in support of fleets; and launched a first of its kind vehicle-to-grid program enabling customers to leverage their electric vehicles to power their home. •Brought the total number of interconnected private solar customers to more than 800,000 and supported more than 70,000 customers who have installed battery storage at their homes or businesses. •Continued to advance decarbonization initiatives for the Utility's natural gas delivery system, including meeting the CPUC-mandated methane emission reduction target ahead of schedule and accelerated initiatives to meet its voluntary 2030 reduction goal. The Utility also launched an initiative to purchase California-produced renewable natural gas for its natural gas customers, toward a target to procure renewable natural gas to serve 15% of its bundled residential and small commercial demand by 2030. The CPUC coordinates the planning of supply resources through the Integrated Resource Planning ("IRP") proceeding and has determined that replacing the power generated by Diablo Canyon is the responsibility of all LSEs within the CAISO. Looking ahead, the Utility expects its GHG-free energy supply mix of renewable, large hydroelectric, and nuclear generation resources to decrease as, beginning in 2023, the Utility was required to offer, for allocation or sale, renewable sources eligible under California's RPS program that the Utility procured on behalf of customers that subsequently switched to non-Utility providers. These requirements were established to comply with regulatory mandates and to manage customer affordability. Towards the end of the decade and beyond, the Utility's GHG-free energy supply mix is expected to grow relative to 2025 levels as the Utility procures new GHG-free generation and storage to meet California's IRP GHG emissions reduction targets and California's clean energy goals. PG&E Corporation's and the Utility's voluntary goal continues to be to deliver 70% RPS clean electricity by 2030, compared to a state mandate of 60% (see "Air Quality and Climate Change" below for more information).

FY 2024 10-K
Added
Filed Feb 13, 2025

•Delivered electricity to retail customers in 2024 that was over 90% GHG free (see "Electricity Resources" below for more information). •Helped customers avoid emissions and manage energy costs through robust energy efficiency programs. •Managed contracts for more than 4.6 GW of battery energy storage to be deployed over the next several years and operated 183 MW of Utility-owned battery storage, strengthening California's grid efficiency and reliability. •Helped enable the total number of electric vehicles operating in the Utility's service area to exceed 675,000; installed more than 3,800 charging ports for electric vehicles at schools, public charging locations, and in support of fleets; and deployed the first-in-the-nation 100% electric school bus fleet that is also equipped with groundbreaking vehicle-to-grid technology. •Brought the total number of interconnected private solar customers to more than 880,000 and total number of customers who have installed battery storage at their homes or businesses to more than 120,000. These customers use their storage systems as critical backup power and for resiliency. 13 •Continued to advance decarbonization initiatives for the Utility's natural gas delivery system, including meeting the CPUC-mandated methane emission reduction target ahead of schedule and accelerated initiatives to meet its voluntary 2030 reduction goal. The Utility also launched an initiative to purchase California-produced renewable natural gas for its natural gas customers, toward a target to procure renewable natural gas to serve 15% of its bundled residential and small commercial demand by 2030.

de-emphasised Total121 7,815

FY 2023 10-K
Removed
Filed Feb 22, 2024

Elkhorn Battery Energy Storage SystemMonterey County1 183 Photovoltaic (3): Various13 152 Total127 7,820 (1) The Utility's Diablo Canyon power plant consists of two nuclear power reactor units, Units 1 and 2. The NRC operating licenses currently expire in 2024 and 2025, respectively. For more information, see "Extension of Diablo Canyon Operations" in Item 7. MD&A below. (2) The Utility's hydroelectric system consists of 99 generating units at 61 powerhouses. All of the Utility's powerhouses are licensed by the FERC (except for two small powerhouses not subject to the FERC's licensing requirements), with license terms between 30 and 50 years. (3) The Utility's large photovoltaic facilities are Cantua solar station (20 MW), Five Points solar station (15 MW), Gates solar station (20 MW), Giffen solar station (10 MW), Guernsey solar station (20 MW), Huron solar station (20 MW), Stroud solar station (20 MW), West Gates solar station (10 MW), and Westside solar station (15 MW). All of these facilities are located in Fresno County, except for Guernsey solar station, which is located in Kings County. The Utility has applied to transfer its non-nuclear generation assets to Pacific Generation and potentially sell a minority interest in Pacific Generation. (For more information, see "Application with Pacific Generation for Approval to Transfer Non-Nuclear Generation Assets" in Item 7. MD&A below.)

FY 2024 10-K
Added
Filed Feb 13, 2025

Elkhorn Battery Energy Storage SystemMonterey County1 183 Photovoltaic (3): Various12 152 Total121 7,815 (1) The Utility's DCPP consists of two nuclear power reactor units, Units 1 and 2. The NRC operating license for Unit 1 expired in 2024. Unit 2 will expire in 2025. Both remain in effect pending completion of the ongoing federal relicensing review. For more information, see "Extension of Diablo Canyon Operations" in Item 7. MD&A below. (2) The Utility's hydroelectric system consists of 94 generating units at 58 powerhouses. All of the Utility's powerhouses are licensed by the FERC (except for one small powerhouse not subject to the FERC's licensing requirements), with license terms between 30 and 50 years. (3) The Utility's large photovoltaic facilities are Cantua solar station (20 MW), Five Points solar station (15 MW), Gates solar station (20 MW), Giffen solar station (10 MW), Guernsey solar station (20 MW), Huron solar station (20 MW), Stroud solar station (20 MW), West Gates solar station (10 MW), and Westside solar station (15 MW). All of these facilities are located in Fresno County, except for Guernsey solar station, which is located in Kings County. 28

de-emphasised •A 40% reduction in GHGs by 2030 compared to 1990 levels.

FY 2023 10-K
Removed
Filed Feb 22, 2024

State Regulation California laws and regulations have established the following targets: •A 40% reduction in GHGs by 2030 compared to 1990 levels. •50% of retail energy sales to customers from renewable energy sources by 2026 and 60% by 2030.

FY 2024 10-K
Added
Filed Feb 13, 2025

Greenhouse Gas Emissions Regulation California laws and regulations have established the following targets: •A 40% reduction in GHGs by 2030 compared to 1990 levels.

de-emphasised Performance: Underpinning the Triple Bottom Line The Utility reported an increased number of CPUC-reportable ignitions in 2024 compared to 2022 and 2023, attributing the rise to hotter, drier weather conditions, despite its equipment not being involved in any major wildfires that year. Additionally, the description of generation operations shifted from focusing on asset management systems to emphasizing risk-informed decision-making, compliance, and capital improvements aligned with interim risk reduction measures.

FY 2023 10-K
Removed
Filed Feb 22, 2024

•System hardening: System hardening entails repairing, replacing, or eliminating existing power lines in HFTDs and installing stronger and more resilient equipment. As the Utility's asset inspections have identified more equipment conditions, the Utility has hardened its system by correcting significantly more equipment conditions than in prior years. Hardening methods also include replacing bare overhead conductor with covered conductor and installing stronger poles, removing lines, and serving customers through remote grids, or converting lines from overhead to underground. The Utility has set a goal to underground 10,000 miles of electric distribution lines in high wildfire risk areas. Undergrounding can substantially reduce ignition risk and improve reliability during storms or periods of high wildfire risk. In 2023, the Utility undergrounded 364 miles of lines, nearly double the number of miles undergrounded in 2022. Remote grids can also reduce costs and fire risks, while maintaining service to participating customers. The Utility brought online two additional "remote grids" in 2022, which allow distribution lines in HFTDs to be removed and replaced with locally sited resources. The Utility's equipment was not involved in the ignition of any catastrophic wildfires in 2023. The Utility also significantly reduced both the size and number of CPUC-reportable ignitions and number of acres burned in 2023, compared to prior years. In 2023, the Utility introduced or expanded its use of several measures including downed conductor detection, partial voltage force outs, and transmission operational controls which further decreased wildfire ignition risk. These measures built on the Utility's progress in 2022, when it expanded the EPSS program to all high fire risk areas. In addition, the Utility uses multiple weather models on a daily basis that indicate which circuits to enable with safety settings and which to put in normal protection settings, optimizing for wildfire risk reduction when needed and enhancing reliability when wildfire risk is low. In 2022, the Utility reviewed and adjusted settings to improve coordination among devices on a circuit to reduce the number of customers impacted by an outage. In 2022 and 2023, the Utility took additional steps to improve customer reliability through several targeted programs, including vegetation management activities to reduce vegetation caused outages, upgrading the system to improve sectionalization, and installing fault indicators to reduce restoration times. PG&E Corporation and the Utility are continuing to invest in a safe and reliable gas system and are working toward targeted electrification, greening the gas supply, and shaping California energy policy. The Utility has focused on continuously improving its gas operations safety record. Since the San Bruno natural gas pipeline explosion in 2010, the Utility's asset safety efforts have included replacing distribution mains and transmission pipelines, as well as strength testing transmission pipelines. The Utility uses in-line inspections to assess the integrity of transmission pipelines. The Utility also uses safety and control systems to monitor, gather, and process real-time data on its gas system. The Utility's gas system has not had a safety-related incident that affected the public and resulted in a fatality or injury since 2015 or 2018, respectively. In 2023, the NTSB confirmed that the Utility had successfully addressed all 12 safety recommendations relating to the San Bruno explosion. The Utility has engaged in educating employees, contractors, and the public regarding safe digging programs and practices for their awareness during construction and when digging near the Utility's underground gas and electric assets. The Utility also installed safety devices that automatically detect increasing pressure on systems and stop the flow of gas to avoid outages and overpressure events. Additionally, the Utility continues to streamline its efforts to respond to outages on a timely basis. The Utility's outage response is designed to keep the public safe while limiting customer outages and returning service safely and as quickly as possible. The Utility's generation operations have focused on safety and reliability. Winter precipitation and snowpack provided fuel for increased hydro generation in 2023, exceeding the 15-year average. The Utility is focused on continuous improvement of asset management and work management systems to support comprehensive non-nuclear generation asset management. The goal of these efforts is to further improve project execution capabilities and capacity to deliver on asset improvements necessary for long-term safe and reliable generation.

FY 2024 10-K
Added
Filed Feb 13, 2025

The Utility's equipment was not involved in the ignition of any major wildfires in 2024. The Utility experienced an increased number of CPUC-reportable ignitions in 2024, compared to 2022 and 2023, due to hotter, drier weather conditions. In recent years, the Utility has introduced or expanded its use of several measures including downed conductor detection, partial voltage force outs, and transmission operational controls which further decreased wildfire ignition risk and took additional steps to improve customer reliability such as vegetation management activities to reduce vegetation-caused outages, upgrading the system to improve sectionalization, and installing fault indicators to reduce restoration times. The Utility also uses multiple weather models on a daily basis that indicate which circuits to enable with safety settings and which to put in normal protection settings, optimizing for wildfire risk reduction when needed and enhancing reliability when wildfire risk is low. PG&E Corporation and the Utility are continuing to invest in a safe and reliable gas system and are working toward targeted electrification, greening the gas supply, and shaping California energy policy. The Utility has focused on continuously improving its gas operations safety record. Since the San Bruno natural gas pipeline explosion in 2010, the Utility's asset safety efforts have included replacing distribution mains and transmission pipelines, as well as strength testing transmission pipelines. The Utility uses in-line inspections to assess the integrity of transmission pipelines. The Utility also uses safety and control systems to monitor, gather, and process real-time data on its gas system. The Utility has engaged in educating employees, contractors, and the public regarding safe digging programs and practices for their awareness during construction and when digging near the Utility's underground gas and electric assets. The Utility also installed safety devices that automatically detect increasing pressure on systems and stop the flow of gas to avoid outages and overpressure events. Additionally, the Utility continues to streamline its efforts to respond to outages on a timely basis. The Utility's outage response is designed to keep the public safe while limiting customer outages and returning service safely and as quickly as possible. The Utility's non-nuclear generation operations focus on safety, compliance, environmental stewardship, and asset reliability. The Utility focuses on continuous improvement and risk informed decision-making to maximize asset value for customers, while adhering to industry standards for asset risk management and lifecycle optimization. Work management systems enable the execution and tracking of preventative and corrective maintenance strategies for generation assets. Capital improvements are carried out to renew key asset components and are strategically aligned with interim risk reduction measures to ensure long-term safe and reliable generation. 16

reworded Nuclear Regulatory Commission

FY 2023 10-K
Removed
Filed Feb 22, 2024

Nuclear Regulatory Commission The NRC oversees the licensing, construction, operation, and decommissioning of nuclear facilities, including the Utility's two nuclear generating units at Diablo Canyon and the Utility's independent spent fuel storage installation at Humboldt Bay. See "Electricity Resources" below. NRC regulations require extensive monitoring and review of the safety, radiological, seismic, environmental, and security aspects of these facilities. In the event of non-compliance, the NRC has the authority to impose fines or to force a shutdown of a nuclear plant, or both. NRC safety and security requirements have, in the past, necessitated that the Utility incur substantial costs at Diablo Canyon, and substantial costs could be required in the future. For more information about Diablo Canyon, see Item 1A. Risk Factors and Note 15 of the Notes to the Consolidated Financial Statements in Item 8.

FY 2024 10-K
Added
Filed Feb 13, 2025

Nuclear Regulatory Commission The NRC oversees the licensing, construction, operation, and decommissioning of nuclear facilities, including the Utility's two nuclear generating units at DCPP and the Utility's independent spent fuel storage installation at Humboldt Bay. See "Electricity Resources" below. NRC regulations require extensive monitoring and review of the safety, radiological, seismic, environmental, and security aspects of these facilities. In the event of non-compliance, the NRC has the authority to impose fines or to force a shutdown of a nuclear plant, or both. NRC safety and security requirements have, in the past, necessitated that the Utility incur substantial costs at DCPP, and substantial costs could be required in the future. For more information about DCPP, see Item 1A. Risk Factors and Note 15 of the Notes to the Consolidated Financial Statements in Item 8.

reworded Air Quality and the Clean Air Act

FY 2023 10-K
Removed
Filed Feb 22, 2024

For more information about environmental remediation liabilities, see Note 15 of the Notes to the Consolidated Financial Statements in Item 8. Air Quality and Climate Change The Utility's electric generation plants, natural gas pipeline operations, vehicle fleet, and fuel storage tanks are subject to numerous air pollution control laws, including the federal Clean Air Act, as well as state and local statutes. These laws and regulations cover, among other pollutants, those contributing to the formation of ground-level ozone, carbon dioxide (CO2), sulfur dioxide (SO2), nitrogen oxides (NOx), particulate matter, and other emissions.

FY 2024 10-K
Added
Filed Feb 13, 2025

For more information about environmental remediation liabilities, see Note 15 of the Notes to the Consolidated Financial Statements in Item 8. Air Quality and the Clean Air Act The Utility's electric generation plants, natural gas pipeline operations, vehicle fleet, and fuel storage tanks are subject to numerous air pollution control laws, including the federal Clean Air Act, as well as state and local statutes. These laws and regulations cover, among other pollutants, those contributing to the formation of ground-level ozone, carbon dioxide (CO2), sulfur dioxide (SO2), nitrogen oxides (NOx), particulate matter, and other emissions.

reworded As a result, the Utility's CPUC-jurisdictional revenue requirement is the sum of the following:

FY 2023 10-K
Removed
Filed Feb 22, 2024

The Utility's costs of equity and long-term debt are generally approved in the CPUC's cost of capital proceedings. As a result, the Utility's CPUC-jurisdictional revenue requirement is the sum of the following: •expenses; •depreciation;

FY 2024 10-K
Added
Filed Feb 13, 2025

The Utility's costs of equity and long-term debt are generally approved in the CPUC's cost of capital proceedings. As a result, the Utility's CPUC-jurisdictional revenue requirement is the sum of the following: •expenses; •depreciation; 20

reworded General Rate Cases

FY 2023 10-K
Removed
Filed Feb 22, 2024

See "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC proceedings. Base Revenues General Rate Cases The GRC is the primary proceeding in which the CPUC determines the amount of base revenue requirements that the Utility is authorized to collect from customers to recover the Utility's anticipated costs related to its electric distribution, natural gas distribution, and Utility-owned electric generation operations and return on rate base. In the past, the CPUC has generally conducted a GRC every three years. Starting with the 2023 GRC, the CPUC now conducts a GRC every four years that includes the Utility's costs of its gas transmission and storage facilities. The CPUC approves the annual revenue requirements for the first year (or "test year") of the GRC period and typically authorizes the Utility to receive annual increases in revenue requirements for the subsequent years of the GRC period (known as "attrition years"). Attrition year rate adjustments are generally authorized for cost increases related to invested capital and inflation. Parties to the Utility's GRC include the Public Advocates Office of the CPUC (formerly known as Office of Ratepayer Advocates or ORA) and TURN, which generally represent the interests of residential customers, as well as numerous intervenors that represent other business, community, customer, environmental, and union interests. For more information about the Utility's GRC, see "Regulatory Matters - 2023 General Rate Case" in Item 7. MD&A.

FY 2024 10-K
Added
Filed Feb 13, 2025

See "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC proceedings. Base Revenues General Rate Cases The GRC is the primary proceeding in which the CPUC determines the amount of base revenue requirements that the Utility is authorized to collect from customers to recover the Utility's anticipated costs related to its electric distribution, natural gas distribution, and Utility-owned electric generation operations and return on rate base. The CPUC conducts a GRC every four years that includes the Utility's costs of its gas transmission and storage facilities. The CPUC approves the annual revenue requirements for the first year (or "test year") of the GRC period and typically authorizes the Utility to receive annual increases in revenue requirements for the subsequent years of the GRC period (known as "attrition years"). Attrition year rate adjustments are generally authorized for cost increases related to invested capital and inflation. Parties to the Utility's GRC include the Public Advocates Office of the CPUC (formerly known as Office of Ratepayer Advocates or ORA) and TURN, which generally represent the interests of residential customers, as well as numerous intervenors that represent other business, community, customer, environmental, and union interests. For more information about the Utility's GRC, see "Regulatory Matters - 2023 General Rate Case" in Item 7. MD&A.

reworded Cost of Capital Proceedings

FY 2023 10-K
Removed
Filed Feb 22, 2024

Cost of Capital Proceedings The CPUC periodically conducts a cost of capital proceeding to authorize the Utility's capital structure and rates of return for its electric generation, electric and natural gas distribution, and natural gas transmission and storage rate base. The rate of return, or cost of capital, is the weighted average cost of debt, preferred equity, and common stock a utility has issued to finance its utility capital investments. The CPUC's cost of capital proceedings generally take place in a consolidated proceeding with California's other large investor-owned electric and gas utilities. For more information about the cost of capital proceedings, see "Regulatory Matters - Cost of Capital Proceedings" in Item 7. MD&A.

FY 2024 10-K
Added
Filed Feb 13, 2025

Cost of Capital Proceedings The CPUC periodically conducts a cost of capital proceeding to authorize the Utility's ratemaking capital structure (i.e., the relative weightings of common stock, preferred equity, and debt for ratemaking) and rates of return for its electric generation, electric and natural gas distribution, and natural gas transmission and storage rate base. The rate of return, or cost of capital, is the weighted average cost of debt, preferred equity, and common stock a utility has issued to finance its utility capital investments. The CPUC's cost of capital proceedings generally take place in a consolidated proceeding with California's other large investor-owned electric and gas utilities. For more information about the cost of capital proceedings, see "Regulatory Matters - Cost of Capital Proceedings" in Item 7. MD&A. 21

reworded Diablo Canyon Extended Operations

FY 2023 10-K
Removed
Filed Feb 22, 2024

Diablo Canyon Extended Operations During the period of extended operations and in lieu of the traditional rate-based return on investment, SB 846 provides for a fixed payment of $50 million, in 2022 dollars, for each of Diablo Canyon's Unit 1 and Unit 2 for each year of extended operations to be recovered from customers of all CPUC-jurisdictional LSEs, which is potentially subject to adjustment downward in the event of extended unplanned outages. In addition, SB 846 authorizes a volumetric payment totaling $13 (in 2022 dollars) for each MWh generated by Diablo Canyon during the period of extended operations, with the first half recovered from all CPUC-jurisdictional LSEs and the second half from customers in the Utility's service area. The amount of the fixed and volumetric payments will be adjusted annually by the CPUC using CPUC-approved escalation methodologies and adjustment factors. The volumetric payment cannot be realized as shareholder profits or paid out as dividends, to the extent it is not needed for Diablo Canyon. The legislation includes language that limits use of the volumetric payment to investments in the system and for customers that address critical state priorities.

FY 2024 10-K
Added
Filed Feb 13, 2025

Diablo Canyon Extended Operations During the period of extended operations and in lieu of the traditional rate-based return on investment, SB 846 provides for a fixed payment of $50 million, in 2022 dollars, for each of DCPP's Unit 1 and Unit 2 for each year of extended operations to be recovered from customers of all CPUC-jurisdictional LSEs, which is potentially subject to adjustment downward in the event of extended unplanned outages. In addition, SB 846 authorizes a volumetric payment totaling $13 (in 2022 dollars) for each MWh generated by DCPP during the period of extended operations, with the first half recovered from all CPUC-jurisdictional LSEs and the second half from customers in the Utility's service area. The amount of the fixed and volumetric payments will be adjusted annually by the CPUC using CPUC-approved escalation methodologies and adjustment factors. The volumetric payment cannot be realized as shareholder profits or paid out as dividends, to the extent it is not needed for DCPP. The legislation includes language that limits use of the volumetric payment to accelerate, or increase spending on, public purpose priorities enumerated in SB 846.

reworded Electricity Procurement Costs

FY 2023 10-K
Removed
Filed Feb 22, 2024

Revenues to Recover Energy Procurement and Other Pass-Through Costs Electricity Procurement Costs California IOUs are responsible for procuring electrical capacity required to meet bundled customer demand, plus applicable reserve margins. The utilities are responsible for scheduling and bidding electric generation resources, including certain electricity procured from third parties, into the wholesale market to meet customer demand according to which resources are the least expensive (i.e., using the principles of "least-cost dispatch"). In addition, the utilities are required to obtain CPUC approval of their BPPs based on long-term demand forecasts. In October 2015, the CPUC approved the Utility's most recent comprehensive BPP. It has been revised since its initial approval, and the revised version will remain in effect, subject to any further revisions, until superseded by a subsequent CPUC-approved plan. California law allows electric utilities to recover the costs incurred in compliance with their CPUC-approved BPPs without further after-the-fact reasonableness review by the CPUC. The CPUC may disallow costs associated with electricity purchases if the costs were not incurred in compliance with the CPUC-approved plan or if the CPUC determines that the utility failed to follow the principles of least-cost dispatch. Additionally, the CPUC may disallow the value of lost generation due to unplanned outages at utility-owned generation facilities. The Utility recovers its electric procurement costs annually primarily through balancing accounts. See Note 3 of the Notes to the Consolidated Financial Statements in Item 8. Each year, the CPUC reviews the Utility's forecasted procurement costs related to power purchase agreements, derivative instruments, GHG emissions costs, and generation fuel expense, and approves a forecasted revenue requirement. The CPUC may adjust the Utility's retail electric rates more frequently if the forecasted aggregate over-collections or under-collections in the Energy Resource Recovery Account, net of bundled service customer Portfolio Allocation Balancing Account balances, exceed five percent of its prior year electric procurement and Utility-owned generation revenues. The CPUC performs an annual compliance review of the procurement transactions recovered in various balancing accounts, including the Energy Resource Recovery Account and the Portfolio Allocation Balancing Account. The CPUC has approved various power purchase agreements into which the Utility has entered with third parties in accordance with the Utility's CPUC-approved BPP, to meet mandatory renewable energy targets, and to comply with RA requirements. For more information, see "Electric Utility Operations - Electricity Resources" below as well as Note 15 of the Notes to the Consolidated Financial Statements in Item 8. 25 The Utility is also responsible, as the central procurement entity ("CPE") for its distribution service area, for seeking to procure the entire amount of required local RA on behalf of all CPUC-jurisdictional LSEs in its distribution service area. CPUC decisions grant the Utility, acting as CPE, discretion to defer procurement of local resources to the CAISO's backstop mechanisms if bid costs are deemed unreasonably high. The Utility, as the CPE, will not be assessed fines or penalties for failing to procure resources to meet the local RA requirements and deferring local procurement to the CAISO backstop mechanism, so long as the CPE exercised reasonable efforts to secure capacity and certain specified requirements are met. In addition, the Utility, as the CPE, has been ordered or authorized to seek to procure specific local capacity products pursuant to CPUC decisions. In connection with its CPE function, the Utility is responsible for making compliance demonstrations to the CPUC and the CAISO. The Utility recovers its administrative and procurement costs associated with its CPE function through a balancing account. Each year, the CPUC reviews the Utility's forecasted administrative costs related to the CPE function and approves a forecasted revenue requirement associated with the administrative costs. The CPUC performs an annual compliance review of the CPE function, including procurement transactions with terms of five years or less (for which costs incurred in compliance with certain prescribed criteria are deemed reasonable and pre-approved without further after-the-fact reasonableness review). Procurement transactions with terms exceeding five years are reviewed separately. The CPUC may disallow costs associated with the CPE function that were not incurred in compliance with the CPUC's decisions and guidance. The CPUC has also approved the Power Charge Indifference Adjustment ("PCIA"). The PCIA is a cost recovery mechanism to ensure that customers who switch from the Utility's bundled service to a non-Utility provider, such as a DA or CCA provider, pay their share of the above-market costs associated with long-term power purchase commitments and Utility-owned generation made on their behalf.

FY 2024 10-K
Added
Filed Feb 13, 2025

Revenues to Recover Energy Procurement and Other Pass-Through Costs Electricity Procurement Costs California IOUs are responsible for procuring electrical capacity required to meet bundled customer demand, plus applicable reserve margins. The utilities are responsible for scheduling and bidding electric generation resources, including certain electricity procured from third parties, into the wholesale market to meet customer demand according to which resources are the least expensive (i.e., using the principles of "least-cost dispatch"). In addition, the utilities are required to obtain CPUC approval of their BPPs based on long-term demand forecasts. In October 2015, the CPUC approved the Utility's most recent comprehensive BPP. It has been revised since its initial approval, and the revised version will remain in effect, subject to any further revisions, until superseded by a subsequent CPUC-approved plan. 22 California law allows electric utilities to recover the costs incurred in compliance with their CPUC-approved BPPs without further after-the-fact reasonableness review by the CPUC. The CPUC may disallow costs associated with electricity purchases if the costs were not incurred in compliance with the CPUC-approved plan or if the CPUC determines that the utility failed to follow the principles of least-cost dispatch. Additionally, the CPUC may disallow the value of lost generation due to unplanned outages at utility-owned generation facilities. The Utility recovers its electric procurement costs annually primarily through balancing accounts. See Note 3 of the Notes to the Consolidated Financial Statements in Item 8. Each year, the CPUC reviews the Utility's forecasted procurement costs related to power purchase agreements, derivative instruments, GHG emissions costs, and generation fuel expense, and approves a forecasted revenue requirement. The CPUC may adjust the Utility's retail electric rates more frequently if the forecasted aggregate over-collections or under-collections in the Energy Resource Recovery Account, net of bundled service customer Portfolio Allocation Balancing Account balances, exceed five percent of its prior year electric procurement and Utility-owned generation revenues. The CPUC performs an annual compliance review of the procurement transactions recovered in various balancing accounts, including the Energy Resource Recovery Account and the Portfolio Allocation Balancing Account. The CPUC has approved various power purchase agreements into which the Utility has entered with third parties in accordance with the Utility's CPUC-approved BPP, to meet mandatory renewable energy targets, and to comply with RA requirements. For more information, see "Electric Utility Operations - Electricity Resources" below as well as Note 15 of the Notes to the Consolidated Financial Statements in Item 8. The Utility is also responsible, as the central procurement entity ("CPE") for its distribution service area, for seeking to procure the entire amount of required local RA on behalf of all CPUC-jurisdictional LSEs in its distribution service area. CPUC decisions grant the Utility, acting as CPE, discretion to defer procurement of local resources to the CAISO's backstop mechanisms if bid costs are deemed unreasonably high. The Utility, as the CPE, will not be assessed fines or penalties for failing to procure resources to meet the local RA requirements and deferring local procurement to the CAISO backstop mechanism, so long as the CPE exercised reasonable efforts to secure capacity and certain specified requirements are met. In addition, the Utility, as the CPE, has been ordered or authorized to seek to procure specific local capacity products pursuant to CPUC decisions. In connection with its CPE function, the Utility is responsible for making compliance demonstrations to the CPUC and the CAISO. The Utility recovers its administrative and procurement costs associated with its CPE function through a balancing account. The CPUC may disallow costs associated with the CPE function that were not incurred in compliance with the CPUC's decisions and guidance. The CPUC has also approved the Power Charge Indifference Adjustment ("PCIA"). The PCIA is a cost recovery mechanism to ensure that customers who switch from the Utility's bundled service to a non-Utility provider, such as a DA or CCA provider, pay their share of the above-market costs associated with long-term power purchase commitments and Utility-owned generation made on their behalf.

reworded People

FY 2023 10-K
Removed
Filed Feb 22, 2024

People The people element of the triple bottom line represents PG&E Corporation's and the Utility's commitment to their workforce, their customers, the residents of local communities in which the companies do business, and other stakeholders. PG&E Corporation's and the Utility's goal is to continually reduce risk to keep customers, the communities they serve, and their workforce (both employees and contractors) safe. Their focus is on continuously building an organization where every work activity is designed to facilitate safe performance, every worker knows and practices safe behaviors, and every individual is encouraged to speak up and stop work if they see unsafe or risky behavior, and has confidence that their concerns and ideas will be heard and pursued. PG&E Corporation and the Utility are committed to significantly improving their safety performance by understanding their risks, prioritizing their work, using controls to reduce risks, and continuously measuring and improving risk reduction. PG&E Corporation's and the Utility's human capital resource objectives are to build and retain an engaged, well trained, diverse, and equitably-paid workforce. PG&E Corporation and the Utility place a high priority on delivering customer value and providing a hometown customer experience. The Utility's customer-driven investment program is aimed at improving safety, increasing electric and gas reliability, and improving customer satisfaction.

FY 2024 10-K
Added
Filed Feb 13, 2025

People The people element of the triple bottom line represents PG&E Corporation's and the Utility's commitment to their workforce, their customers, the residents of local communities in which the companies do business, and other stakeholders. 12 PG&E Corporation's and the Utility's goal is to continually reduce risk to keep customers, the communities they serve, and their workforce (both employees and contractors) safe. Their focus is on continuously building an organization where every work activity is designed to facilitate safe performance, every worker knows and practices safe behaviors, and every individual is encouraged to speak up and stop work if they see unsafe or risky behavior, and has confidence that their concerns and ideas will be heard and pursued. PG&E Corporation and the Utility are committed to significantly improving their safety performance by understanding their risks, prioritizing their work, using controls to reduce risks, and continuously measuring and improving risk reduction. PG&E Corporation's and the Utility's human capital resource objectives are to build and retain an engaged, well trained, diverse, and equitably-paid workforce. Their focus is on making it enjoyable to work with and for PG&E Corporation and the Utility. PG&E Corporation and the Utility place a high priority on delivering customer value and providing a hometown customer experience. The Utility's customer-driven investment program is aimed at improving safety, increasing electric and gas service reliability, and improving customer satisfaction.

reworded Nuclear Decommissioning Costs

FY 2023 10-K
Removed
Filed Feb 22, 2024

Nuclear Decommissioning Costs The Utility's nuclear power facilities consist of two units at Diablo Canyon and the retired facility at Humboldt Bay. Nuclear decommissioning requires the safe removal of nuclear facilities from service and the reduction of residual radioactivity to a level that permits termination of the NRC license and release of the property for unrestricted use. Nuclear decommissioning costs are generally collected in advance through rates and are held in nuclear decommissioning trusts to be used for the eventual decommissioning of each nuclear unit. The Utility files an application with the CPUC every three years requesting approval of the Utility's updated estimated decommissioning costs and any rate change necessary to fully fund the nuclear decommissioning trusts to the levels needed to decommission the Utility's nuclear plants. If the nuclear decommissioning trusts are overfunded, the amount of such overfunding will be returned to customers. Pursuant to Public Utilities Code Section 8325, to the extent the monies available for decommissioning are insufficient to pay for all reasonable and prudent decommissioning costs, the CPUC must authorize the electric utility to collect these charges from its customers.

FY 2024 10-K
Added
Filed Feb 13, 2025

Nuclear Decommissioning Costs The Utility's nuclear power facilities consist of two units at DCPP and the Humboldt Bay independent spent fuel installation. Nuclear decommissioning requires the safe removal of nuclear facilities from service and the reduction of residual radioactivity to a level that permits termination of the NRC license and release of the property for unrestricted use. Nuclear decommissioning costs are generally collected in advance through rates and are held in nuclear decommissioning trusts to be used for the eventual decommissioning of each nuclear unit. The Utility files an application with the CPUC, generally every three years, requesting approval of the Utility's updated estimated decommissioning costs and any rate change necessary to fully fund the nuclear decommissioning trusts to the levels needed to decommission the Utility's nuclear facilities. If the nuclear decommissioning trusts are overfunded, the amount of such overfunding will be returned to customers. Pursuant to Public Utilities Code Section 8325, to the extent the monies available for decommissioning are insufficient to pay for all reasonable and prudent decommissioning costs, the CPUC must authorize the electric utility to collect these charges from its customers.

reworded Employees and Contractors

FY 2023 10-K
Removed
Filed Feb 22, 2024

Employees and Contractors As of December 31, 2023, PG&E Corporation had 10 employees and the Utility had approximately 28,000 regular employees. Of the Utility's regular employees, approximately 17,000 are covered by collective bargaining agreements with the local chapters of three labor unions: the International Brotherhood of Electrical Workers ("IBEW") Local 1245; the Engineers and Scientists of California ("ESC") IFPTE 20; and the Service Employees International Union Local 24/7 ("SEIU"). The collective bargaining agreements in effect for the IBEW Local 1245, ESC Local 20, and SEIU United Service Workers West, are set to expire on December 31, 2025. The agreements increase wages annually by 3.75% from 2022 through 2025 and maintain current contributions to specified benefits. The IBEW, ESC, and SEIU represent approximately 63% of the Utility's employee workforce and support several areas of the Utility's business, including gas and electric operations. The Utility enjoys stable and productive relationships with its unions and did not experience any work stoppages in 2023. PG&E Corporation's employees are primarily at the executive management level. The Utility generally has a stable workforce. The Utility's turnover rates for 2023 and 2022 were 4.0% and 7.1%, respectively. Approximately 42% of PG&E Corporation's and the Utility's employees have a tenure of more than 10 years, with an average tenure of 11 years. Approximately 18% of PG&E Corporation's and the Utility's employees are eligible to retire. (PG&E Corporation and the Utility define retirement age as 55 years and older.)

FY 2024 10-K
Added
Filed Feb 13, 2025

Employees and Contractors As of December 31, 2024, PG&E Corporation had 10 employees and the Utility had approximately 28,400 regular employees. Of the Utility's regular employees, approximately 17,600 are covered by collective bargaining agreements with the local chapters of three labor unions: the International Brotherhood of Electrical Workers ("IBEW") Local 1245; the Engineers and Scientists of California ("ESC") IFPTE 20; and the Service Employees International Union Local 24/7 ("SEIU"). The collective bargaining agreements in effect for the IBEW Local 1245, ESC Local 20, and SEIU United Service Workers West, are set to expire on December 31, 2025. The agreements increase wages annually by 3.75% from 2022 through 2025 and maintain current contributions to specified benefits. The IBEW, ESC, and SEIU represent approximately 62% of the Utility's employee workforce and support several areas of the Utility's business, including gas and electric operations. The Utility enjoys stable and productive relationships with its unions and did not experience any work stoppages in 2024. 24 PG&E Corporation's employees are primarily at the executive management level. The Utility generally has a stable workforce. The Utility's turnover rate for each of 2024 and 2023 was 4.0%. Approximately 44% of PG&E Corporation's and the Utility's employees have a tenure of more than 10 years, with an average tenure of 11 years. Approximately 18% of PG&E Corporation's and the Utility's employees are eligible to retire. (PG&E Corporation and the Utility define retirement age as 55 years and older.)

reworded Safety

FY 2023 10-K
Removed
Filed Feb 22, 2024

All PG&E Corporation and Utility officer compensation currently is funded by shareholders. Safety The Utility's strategy to deliver on safety outcomes focuses on workforce and public safety. In 2023, in addition to deploying a safety management system, the Utility targets mitigations to the highest risk work. The Utility's safety metrics include the number of actual serious incidents or fatalities ("SIF-A") incidents and the "SIF-P" rate, which measures events that could have resulted in a SIF-A per 200,000 hours worked. In 2023, the Utility had four SIF-A incidents, which resulted in two fatalities and two serious injuries, and a SIF-P rate of 0.1. Additionally, the Utility measures DART (days away, restricted or transferred duty per 200,000 hours worked). In 2023, the Utility's DART was 0.7. In particular, the Utility improved safety through the reduction of preventable motor vehicle incidents ("PMVI"). In 2023, the Utility's PMVI rate was the lowest rate in the last eight years.

FY 2024 10-K
Added
Filed Feb 13, 2025

All executive officer compensation is paid by PG&E Corporation. 25 Safety The Utility's strategy to deliver on safety outcomes focuses on employee, contractor, and public safety. Identifying, eliminating and mitigating high-energy hazards remains a priority. The Utility's safety metrics include the number of actual serious incidents or fatalities ("SIF-A") and high-energy events that could have resulted in a serious injury or fatality ("SIF-P") where SIF-P rate measures events that could have resulted in a SIF-A per 200,000 hours worked. In 2024, the Utility had seven SIF-A incidents, which resulted in zero fatalities and seven serious injuries, and a SIF-P rate of 0.05. Additionally, the Utility measures DART (days away, restricted or transferred duty per 200,000 hours worked). In 2024, the Utility's DART was 0.7. In particular, the Utility improved safety through the implementation of the Utility's safety excellence management system and a focus on essential controls for high energy hazards.

reworded Electricity Resources

FY 2023 10-K
Removed
Filed Feb 22, 2024

Electricity Resources The Utility is required to maintain adequate capacity to meet its customers' demand for electricity ("load"), including peak demand and planning and operating reserves, deliverable to the locations and at times as may be necessary to provide reliable electric service. The Utility is responsible for scheduling and bidding electric generation resources, including certain electricity procured from third parties into the wholesale market, to meet customer demand. The following table shows the percentage of the Utility's estimated total net deliveries of electricity to customers in 2023 represented by each major electric resource, and further discussed below. The Utility's deliveries were primarily from renewable energy resources that qualify under California's RPS and other GHG-free resources (i.e., nuclear, and large hydroelectric generation). California's RPS requirements and SB 100 goal is to serve 100% of retail electricity sales with GHG-free resources by 2045. For more information about California's RPS requirements and clean energy goals, see further below and in the Environmental Regulation section above.

FY 2024 10-K
Added
Filed Feb 13, 2025

Electricity Resources The Utility is required to maintain adequate capacity to meet its customers' demand for electricity ("load"), including peak demand and planning and operating reserves, deliverable to the locations and at times as may be necessary to provide reliable electric service. The Utility is responsible for scheduling and bidding electric generation resources, including certain electricity procured from third parties into the wholesale market, to meet customer demand. The following table shows the percentage of the Utility's estimated total net deliveries of electricity to retail customers in 2024 represented by each major electric resource, and further discussed below. The Utility's deliveries were primarily from renewable energy resources that qualify under California's RPS and other GHG-free resources (i.e., nuclear, and large hydroelectric generation). California's RPS requirements and SB 100 goal is to serve 100% of retail electricity sales with GHG-free resources by 2045. For more information about California's RPS requirements and clean energy goals, see further below and in the "Sustainability and Resiliency" section below. 26

reworded (6) Amount is comprised of renewable, nuclear, and large hydroelectric facility resources generated, procured, and sold.

FY 2023 10-K
Removed
Filed Feb 22, 2024

(4) Amounts consist primarily of natural gas facilities. (5) Amount is mainly comprised of net CAISO open market (sales)/purchases. (6) Amount is comprised of renewable, nuclear, and large hydroelectric facility resources generated, procured, and sold. 29

FY 2024 10-K
Added
Filed Feb 13, 2025

(4) Amounts consist primarily of natural gas facilities. (5) Amount is mainly comprised of net CAISO open market (sales)/purchases. (6) Amount is comprised of renewable, nuclear, and large hydroelectric facility resources generated, procured, and sold.

reworded Renewable Energy Resources

FY 2023 10-K
Removed
Filed Feb 22, 2024

Renewable Energy Resources California law established an RPS that requires LSEs, such as the Utility, to gradually increase the amount of renewable energy they deliver to their customers. See "Environmental Regulation - Air Quality and Climate Change" above. The Utility may in the future incur additional costs to procure renewable energy to meet the new renewable energy targets, which the Utility expects will continue to be recoverable through rates as "pass-through" costs. The Utility also may be subject to penalties for failure to meet the higher targets. Renewable generation resources, for purposes of the RPS requirements, include bioenergy such as biogas and biomass, certain hydroelectric facilities (30 MW or less), wind, solar, and geothermal energy. RPS requirements are based on procurement, which aligns with the methodology presented in the first column of the table above. Procurement from renewable energy sources was estimated to comprise 37% of total annual retail sales in 2023. Per the Power Content Label methodology based on current CEC guidelines presented in the table above, an estimated 34% of the Utility's energy deliveries were from renewable energy sources in 2023.

FY 2024 10-K
Added
Filed Feb 13, 2025

(7) Amount includes adjustments due to DCPP's extended operations, consistent with CPUC and CEC guidelines. Renewable Energy Resources California law established an RPS that requires LSEs, such as the Utility, to gradually increase the amount of renewable energy they deliver to their customers. See "Sustainability and Resiliency" below. The Utility may in the future incur additional costs to procure renewable energy to meet the new renewable energy targets. The Utility expects that these costs will continue to be recoverable through rates as "pass-through" costs. The Utility also may be subject to penalties for failure to meet the higher targets. Renewable generation resources, for purposes of the RPS requirements, include bioenergy such as biogas and biomass, certain hydroelectric facilities (30 MW or less), wind, solar, and geothermal energy. RPS requirements are based on procurement, which aligns with the methodology presented in the first column of the table above. Procurement from renewable energy sources was estimated to comprise 23% of total annual retail sales in 2024. Per the Power Content Label methodology based on current CEC guidelines presented in the table above, an estimated 23% of the Utility's energy deliveries were from renewable energy sources in 2024. 27

reworded TypePercent of Customer Retail Sales (estimated procurement)(1)

FY 2023 10-K
Removed
Filed Feb 22, 2024

The estimated total renewable deliveries as of December 31, 2023, shown above was 9,676 GWh and comprised of the following: TypePercent of Customer Retail Sales (estimated procurement)(1)

FY 2024 10-K
Added
Filed Feb 13, 2025

The estimated total renewable deliveries for the year ended December 31, 2024, shown above was 5,920 GWh and comprised of the following: TypePercent of Customer Retail Sales (estimated procurement)(1)

reworded Total23 %

FY 2023 10-K
Removed
Filed Feb 22, 2024

Biopower4 % Geothermal- % RPS-Eligible Small Hydroelectric3 % Solar24 % Wind6 % Total37 % (1) Estimated renewable procurement percentages above and renewable compliance percentages are expected to be consistent; however, final RPS compliance reporting is subject to a different methodology and may result in differences between the two percentages.

FY 2024 10-K
Added
Filed Feb 13, 2025

Biopower3 % Geothermal- % RPS-Eligible Small Hydroelectric2 % Solar15 % Wind3 % Total23 % (1) Estimated renewable procurement percentages above and renewable compliance percentages are expected to be consistent; however, final RPS compliance reporting is subject to a different methodology and may result in differences between the two percentages.

reworded At December 31, 2024, the Utility owned the following generation facilities, all located in California, listed by energy source and further described below:

FY 2023 10-K
Removed
Filed Feb 22, 2024

Owned Generation Facilities At December 31, 2023, the Utility owned the following generation facilities, all located in California, listed by energy source and further described below:

FY 2024 10-K
Added
Filed Feb 13, 2025

Owned Generation Facilities At December 31, 2024, the Utility owned the following generation facilities, all located in California, listed by energy source and further described below:

reworded Conventional16 counties in northern and central California91 2,628

FY 2023 10-K
Removed
Filed Feb 22, 2024

Generation TypeCounty LocationNumber of UnitsNet Operating Capacity (MW) Nuclear (1): Diablo CanyonSan Luis Obispo2 2,240 Hydroelectric (2): Conventional16 counties in northern and central California96 2,633

FY 2024 10-K
Added
Filed Feb 13, 2025

Generation TypeCounty LocationNumber of UnitsNet Operating Capacity (MW) Nuclear (1): Diablo CanyonSan Luis Obispo2 2,240 Hydroelectric (2): Conventional16 counties in northern and central California91 2,628

reworded Electricity Distribution

FY 2023 10-K
Removed
Filed Feb 22, 2024

Decisions about expansions and maintenance of the transmission system can be influenced by decisions of the Utility's regulators and the CAISO. 31 Electricity Distribution Distribution lines allow electricity to travel at lower voltages from substations directly to customers. The Utility's electric distribution network consists of approximately 108,000 circuit miles of distribution lines (of which, as of December 31, 2023, approximately 26% are underground and approximately 74% are overhead), 67 transmission switching substations, and 752 distribution substations with a capacity of approximately 36,000 MVA. The Utility's distribution network interconnects with its transmission system, primarily at switching and distribution substations, where equipment reduces the high-voltage transmission voltages to lower voltages, suitable for distribution to the Utility's customers. These distribution substations serve as the central hubs for the Utility's electric distribution network. Emanating from each substation are primary and secondary distribution lines connected to local transformers and switching equipment that link distribution lines and provide delivery to customers. In some cases, third parties, such as municipal and other utilities, who generate or procure their own power rely upon the Utility's distribution facilities to deliver their power to them, so that they are able to resell the electricity. The Utility operates electric distribution control center facilities in Concord, Rocklin, and Fresno, California; these control centers form a key part of the Utility's efforts to create a smarter, more resilient grid.

FY 2024 10-K
Added
Filed Feb 13, 2025

Decisions about expansions and maintenance of the transmission system can be influenced by decisions of the Utility's regulators and the CAISO. Electricity Distribution Distribution lines allow electricity to travel at lower voltages from substations directly to customers. The Utility's electric distribution network consists of approximately 108,000 circuit miles of distribution lines (of which, as of December 31, 2024, approximately 27% are underground and approximately 73% are overhead), 59 transmission and distribution substations, and 603 distribution substations with a capacity of approximately 33,000 MVA. The Utility's distribution network interconnects with its transmission system, primarily at switching and distribution substations, where equipment reduces the high-voltage transmission voltages to lower voltages, suitable for distribution to the Utility's customers. These distribution substations serve as the central hubs for the Utility's electric distribution network. Emanating from each substation are primary and secondary distribution lines connected to local transformers and switching equipment that link distribution lines and provide delivery to customers. In some cases, third parties, such as municipal and other utilities, who generate or procure their own power rely upon the Utility's distribution facilities to deliver their power to them, so that they are able to resell the electricity. The Utility operates electric distribution control center facilities in Concord, Rocklin, and Fresno, California; these control centers form a key part of the Utility's efforts to create a smarter, more resilient grid. 29

reworded Electricity Operating Statistics

FY 2023 10-K
Removed
Filed Feb 22, 2024

Electricity Operating Statistics The following table shows certain of the Utility's operating statistics from 2021 to 2023 for electricity sold or delivered, including the classification of revenues by type of service. No single customer of the Utility accounted for 10% or more of consolidated revenues for electricity sold in 2023, 2022 or 2021.

FY 2024 10-K
Added
Filed Feb 13, 2025

Electricity Operating Statistics The following table shows certain of the Utility's operating statistics from 2022 to 2024 for electricity sold or delivered, including the classification of revenues by type of service. No single customer of the Utility accounted for 10% or more of consolidated revenues for electricity sold in 2024, 2023, or 2022.

reworded (1) These amounts include electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers.

FY 2023 10-K
Removed
Filed Feb 22, 2024

Industrial0.1294 0.1177 0.1075 Agricultural0.2984 0.2435 0.2104 Net plant investment per customer$10,720 $9,967 $9,199 (1) These amounts include electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers.

FY 2024 10-K
Added
Filed Feb 13, 2025

Industrial0.1475 0.1294 0.1177 Agricultural0.3597 0.2984 0.2435 Net plant investment per customer$11,460 $10,720 $9,967 (1) These amounts include electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers.

reworded Natural Gas System Assets

FY 2023 10-K
Removed
Filed Feb 22, 2024

Natural Gas System Assets The Utility owns and operates an integrated natural gas transmission, storage, and distribution system that includes most of northern and central California. At December 31, 2023, the Utility's natural gas system consisted of approximately 44,200 miles of distribution pipelines, over 6,400 miles of backbone and local transmission pipelines, and various storage facilities. The Utility owns and operates eight natural gas compressor stations on its backbone transmission system and one compressor station on its local transmission system that are used to move gas through the Utility's pipelines. The Utility's backbone transmission system is used to transport gas from the Utility's interconnection with interstate pipelines, other local distribution companies, and California gas fields to the Utility's local transmission and distribution systems. The Utility has firm transportation agreements for the transportation of natural gas from various natural gas supply points and interconnection points to the Utility's natural gas transportation system. These agreements provide transportation service from western Canada to the United States-Canada border, from the United States-Canada border to an interconnection point with the Utility's natural gas transportation system at the Oregon-California border, from the U.S. Rocky Mountains to an interconnection point with the Utility's natural gas transportation system at the Oregon-California border, and from supply points in the southwestern United States to interconnection points with the Utility's natural gas transportation system in the area of California near Topock, Arizona. (For more information regarding the Utility's natural gas transportation agreements, see Note 15 of the Notes to the Consolidated Financial Statements in Item 8.) The Utility owns and operates three underground natural gas storage fields and has a 25% interest in a fourth storage field, all of which are connected to the Utility's gas transmission system. In 2019, the CPUC approved the discontinuation, through closure or sale, of operations at two of the Utility's owned and operated gas storage fields, Pleasant Creek and Los Medanos. The Utility expects to close on the sale of Pleasant Creek in 2024. The Utility plans to keep the Los Medanos storage field in operation as filed and approved in the 2023 GRC. The Utility owns and operates compressors and other facilities at these storage fields that are used to inject gas into the fields for storage and later for withdrawal. In addition, four independent storage operators are interconnected to the Utility's Northern California gas transmission system.

FY 2024 10-K
Added
Filed Feb 13, 2025

Natural Gas System Assets The Utility owns and operates an integrated natural gas transmission, storage, and distribution system that includes most of northern and central California. On December 31, 2024, the Utility's natural gas system consisted of approximately 45,200 miles of distribution pipelines, approximately 5,700 miles of backbone and local transmission pipelines, and various storage facilities. The Utility owns and operates eight natural gas compressor stations on its backbone transmission system and one compressor station on its local transmission system that are used to move gas through the Utility's pipelines. The Utility's backbone transmission system is used to transport gas from the Utility's interconnection with interstate pipelines, other local distribution companies, and California gas fields to the Utility's local transmission and distribution systems. The Utility has firm transportation agreements for the transportation of natural gas from various natural gas supply points and interconnection points to the Utility's natural gas transportation system. These agreements provide transportation service from western Canada to the United States-Canada border, from the United States-Canada border to an interconnection point with the Utility's natural gas transportation system at the Oregon-California border, from the U.S. Rocky Mountains to an interconnection point with the Utility's natural gas transportation system at the Oregon-California border, and from supply points in the southwestern United States to interconnection points with the Utility's natural gas transportation system in the area of California near Topock, Arizona. (For more information regarding the Utility's natural gas transportation agreements, see Note 15 of the Notes to the Consolidated Financial Statements in Item 8.) The Utility owns and operates three underground natural gas storage fields and has a 25% interest in a fourth storage field, all of which are connected to the Utility's gas transmission system. In 2019, the CPUC approved the discontinuation, through closure or sale, of operations at two of the Utility's owned and operated gas storage fields, Pleasant Creek and Los Medanos. The sale of Pleasant Creek is currently pending CPUC review and approval and the Utility anticipates to close on the sale in 2025. The Utility continues to operate and rely on the Los Medanos storage field as filed and approved in the 2023 GRC. The Utility owns and operates compressors and other facilities at these storage fields that are used to inject gas into the fields for storage and later for withdrawal. In addition, four independent storage operators are interconnected to the Utility's Northern California gas transmission system.

reworded Natural Gas Operating Statistics

FY 2023 10-K
Removed
Filed Feb 22, 2024

In 2023, the Utility continued upgrading transmission pipeline to allow for the use of in-line inspection tools. 33 Natural Gas Operating Statistics The following table shows the Utility's operating statistics from 2021 through 2023 (excluding subsidiaries) for natural gas, including the classification of revenues by type of service. No single customer of the Utility accounted for 10% or more of consolidated revenues for bundled gas sales in 2023, 2022 or 2021.

FY 2024 10-K
Added
Filed Feb 13, 2025

In 2024, the Utility continued upgrading transmission pipelines to allow for the use of in-line inspection tools. 31 Natural Gas Operating Statistics The following table shows the Utility's operating statistics from 2022 through 2024 (excluding subsidiaries) for natural gas, including the classification of revenues by type of service. No single customer of the Utility accounted for 10% or more of consolidated revenues for bundled gas sales in 2024, 2023 or 2022.

reworded See "Ratemaking Mechanisms" below and "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC and FERC proceedings.

FY 2023 10-K
Removed
Filed Feb 22, 2024

Under cost-of-service ratemaking, a utility's earnings depend on the outcomes of its ratemaking proceedings and its ability to manage costs. See "Ratemaking Mechanisms" below and "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC and FERC proceedings. 13 Generally, differences between forecast costs and actual costs can occur for numerous reasons, including the volume of work required and the impact of market forces on the cost of labor and materials. Differences in costs can also arise from changes in laws and regulations at both the state and federal level. PG&E Corporation and the Utility are committed to taking steps to improve their credit ratings and metrics over time, including by reducing PG&E Corporation's debt by at least $2 billion by the end of 2026. PG&E Corporation and the Utility expect that reducing the consolidated debt will help them achieve investment grade credit ratings for their unsecured securities, for the benefit of both customers and investors. For more information, see "Liquidity and Financial Resources" in Item 7. MD&A. In 2022, an affiliate of the Utility issued an aggregate of $7.5 billion of SB 901 securitization bonds. The net proceeds were used to reimburse the Utility for previously incurred recovery costs, including the retirement of $6.0 billion of Utility debt, as of December 31, 2023. In November 2023, the Board of Directors of PG&E Corporation reinstated the dividend on PG&E Corporation common stock, declaring a dividend of $21 million, or approximately 1 cent per share, which was paid by January 16, 2024. The Boards of Directors of PG&E Corporation and the Utility had suspended quarterly cash dividends in 2017 on both PG&E Corporation's and the Utility's common stock, as well as the Utility's preferred stock. For more information, see "Liquidity and Financial Resources - Dividends" in Item 7. MD&A. Total capital expenditures recorded in 2023 were $9.8 billion. The Utility's total capital expenditures (including accruals) are forecasted to be $10.4 billion for 2024, $12.7 billion for 2025, $11.5 billion for 2026, $13.6 billion for 2027, and $14.0 billion for 2028. The Utility has identified additional opportunities for investment in the coming years in addition to its forecast, including investments in transportation electrification capacity, FERC-jurisdictional assets, electric distribution capacity, hydroelectric facilities, energy storage, information technology, and automation. The Utility also plans to submit a cost recovery application for its 10-year distribution undergrounding program pursuant to SB 884. Some of these investments depend on the Utility's ability to generate or obtain the cash to support such investments over this period of time. The completion of projects, the timing of expenditures, and the associated cost recovery may be affected by permitting requirements and delays, construction schedules, availability of labor, equipment and materials, financing, legal and regulatory approvals and developments, community requests or protests, weather, and other unforeseen conditions. The Utility expects to make additional capital expenditures, the recovery of which will be subject to future regulatory approval. These expenditures include capital expenditures exceeding amounts authorized in the 2023 GRC final decision issued on November 17, 2023, and expenditures to be included in a later filing or separate applications. These expenditures are expected to be primarily for wildfire mitigation and electrification. Additionally, $3.21 billion of fire risk mitigation capital expenditures has been excluded from the Utility's equity base rate pursuant to AB 1054. PG&E Corporation and the Utility are committed to finding ways to lower the cost of providing gas and electric services for customers. The Utility's capital investment plan, increasing procurement of renewable power and energy storage, increasing environmental regulations, and the cumulative impact of other public policy requirements collectively place continuing upward pressure on customer rates. Certain CPUC proceedings could impact different types of customers differently. The Utility has set a goal to increase customer capital investments while also limiting customer bill impacts, including by achieving operating cost savings and by seeking efficient financing. The Utility plans to meet its cost reduction goal through increased efficiencies, including waste elimination through the Lean operating system. The Utility has a number of programs in place to assist low-income customers, such as the CARE program. Under the CARE program, income-qualified customers can receive a monthly discount of 20% or more on their gas and electric bill. PG&E Corporation's and the Utility's Corporate Sustainability Report, which is available to the public, describes the companies' progress toward world-class performance measured with the triple bottom line framework.

FY 2024 10-K
Added
Filed Feb 13, 2025

Under cost-of-service ratemaking, a utility's earnings depend on the outcomes of its ratemaking proceedings and its ability to manage costs. See "Ratemaking Mechanisms" below and "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC and FERC proceedings. Generally, differences between forecast costs and actual costs can occur for numerous reasons, including the volume of work required and the impact of market forces on the cost of labor and materials. Differences in costs can also arise from changes in laws and regulations at both the state and federal level. Costs can also decrease due to improved efficiencies or waste elimination. PG&E Corporation and the Utility are committed to taking steps to improve their credit ratings and metrics over time, including by reducing PG&E Corporation's debt by $2 billion by the end of 2026. All three credit ratings agencies have increased PG&E Corporation's and the Utility's issuer credit ratings since 2020. In December 2024, PG&E Corporation announced a new dividend policy entailing consistent dividend increases targeting a dividend payout ratio of approximately 20% of core earnings by 2028. For more information, see "Liquidity and Financial Resources - Dividends" in Item 7, MD&A and Note 6 of the Notes to the Consolidated Financial Statements. Total capital expenditures recorded in 2024 were $10.6 billion. The Utility's total capital expenditures (including accruals) are forecasted to be $12.9 billion for 2025, $12.0 billion for 2026, $13.6 billion for 2027, and $14.0 billion for 2028. The Utility has identified additional opportunities for investment in the coming years in addition to its forecast, including investments in transportation electrification capacity, FERC-jurisdictional assets, electric distribution capacity, hydroelectric facilities, energy storage, information technology, and automation. The Utility also plans to submit a cost recovery application for its 10-year distribution undergrounding program pursuant to SB 884. Some of these investments depend on the Utility's ability to generate or obtain the cash to support such investments over this period of time. The completion of projects, the timing of expenditures, and the associated cost recovery may be affected by permitting requirements and delays, construction schedules, availability of labor, equipment and materials, financing, legal and regulatory approvals and developments, community requests or protests, weather, and other unforeseen conditions. The Utility expects to make additional capital expenditures, the recovery of which will be subject to future regulatory approval. These expenditures include capital expenditures exceeding amounts authorized in the 2023 GRC final decision and expenditures to be included in a later filing or separate applications. These expenditures are expected to be primarily for wildfire mitigation and electrification. Additionally, $3.21 billion of fire risk mitigation capital expenditures has been excluded from the Utility's equity base rate pursuant to AB 1054. 14 PG&E Corporation and the Utility are committed to building a safe, reliable, sustainable, and climate-resilient energy system at the lowest possible cost for customers. The Utility's capital investment plan, increasing procurement of renewable power and energy storage, increasing environmental regulations, and the cumulative impact of other public policy requirements collectively place continuing upward pressure on customer rates. Certain CPUC proceedings could impact different types of customers differently. The Utility has set a goal to increase customer capital investments while also limiting customer bill impacts, including by achieving operating cost savings, seeking efficient financing, and benefiting from electric load growth. The Utility plans to meet its cost savings goal through increased efficiencies including waste elimination through the Lean operating system. The Utility expects electric vehicle adoption, data centers, and building electrification to drive load growth. However, the scale of this growth will depend on the Utility's ability to construct necessary infrastructure and the extent of customer demand. The Utility has a number of programs in place to assist low-income customers, such as the CARE program. Under the CARE program, income-qualified customers can receive a monthly discount of 20% or more on their natural gas and electric bill. PG&E Corporation's and the Utility's Corporate Sustainability Report, which is available to the public, describes the companies' progress toward world-class performance measured with the triple bottom line framework.

reworded Average annual residential usage (Mcf)37 37 37

FY 2023 10-K
Removed
Filed Feb 22, 2024

Subtotal6,196 6,055 4,958 Regulatory balancing accounts (2) 808 565 553 Total operating revenues$7,004 $6,620 $5,511 Selected Statistics: Average annual residential usage (Mcf)37 37 37

FY 2024 10-K
Added
Filed Feb 13, 2025

Subtotal6,047 6,196 6,055 Regulatory balancing accounts (2) 561 808 565 Total operating revenues$6,608 $7,004 $6,620 Selected Statistics: Average annual residential usage (Mcf)37 37 37

reworded Trends in Market Demand and Competitive Conditions in the Electricity Industry

FY 2023 10-K
Removed
Filed Feb 22, 2024

(2) These amounts represent revenues authorized to be billed. Competition Trends in Market Demand and Competitive Conditions in the Electricity Industry The Utility expects customer electric load to increase in coming years primarily as a result of electrification of buildings and transportation. The Utility is not able to predict how quickly this electrification will occur. The Utility expects customer demand for gas to decrease in the coming years, primarily in response to policies supporting California's climate goals. California law allows qualifying non-residential electric customers of IOUs to purchase electricity from energy service providers rather than from the utilities up to certain annual limits specified for each utility. This arrangement is known as DA. In addition, California law permits cities, counties, and certain other public agencies that have qualified to become a CCA to generate or purchase electricity for their local residents and businesses. By law, a CCA can procure electricity for all of its residents and businesses that do not affirmatively elect to continue to receive electricity generated or procured by a utility. The Utility continues to provide transmission, distribution, metering, and billing services to DA customers at the election of their energy service provider. The CCA customers continue to obtain transmission, distribution, metering, and billing services from the Utility. In addition to collecting charges for transmission, distribution, metering, and billing services that it provides, the Utility is able to collect charges intended to recover the generation-related costs that the Utility incurred on behalf of DA and CCA customers while they were the Utility's customers. The Utility remains the electricity provider of last resort for these customers. Section 387 of the Public Utilities Code allows for a request to transfer the responsibilities of the provider of last resort obligation from IOUs to other entities. 34 The Utility is also impacted by an increasing quantity of distributed generation and energy storage. The levels of self-generation of electricity by customers (primarily solar installations) and customer enrollment in NEM, which allows self-generating customers employing qualifying renewable resources to receive bill credits at the full retail rate, put upward rate pressure on non-NEM customers. The successor to the NEM tariffs, the NBT, will provide bill credits at a lower rate, which reduces the level of upward rate pressure on non-NEM or non-NBT customers, but does not eliminate such upward rate pressure. Like NEM customers, customers interconnecting on the NBT, are required to pay an interconnection fee, utilize time of use rates, and pay certain non-bypassable charges to help fund some of the costs of low income, energy efficiency, and other programs that other customers pay. Significantly higher bills for non-NEM or non-NBT customers may result in a decline of the number of such customers as they may seek alternative energy providers or adopt self-generation technologies. See "Concerns about high rates for the Utility's customers could negatively impact PG&E Corporation's and the Utility's financial condition, results of operations, liquidity, and cash flows" in Item 1A. Risk Factors and "Regulatory Matters - OIR to Revisit Net Energy Metering Tariffs" in Item 7. MD&A. Further, in some circumstances, governmental entities such as cities and irrigation districts may have authority under the state constitution or state statute to provide retail electric service directly to consumers, in some cases bypassing the Utility's electric infrastructure entirely. Those entities may also rely upon FERC open access tariffs and Utility infrastructure to deliver their energy for resale at retail to existing or potential new Utility customers. These entities may also seek to acquire the Utility's transmission or distribution facilities through eminent domain for use in serving electricity at retail to existing or potential new Utility customers. As a result, the Utility could lose customers (residential, commercial, and industrial) or experience limited growth in the municipality. See "Jurisdictions may attempt to acquire the Utility's assets through eminent domain, and third parties may attempt to acquire the Utility's customers by bypassing the Utility's electric infrastructure system" in Item 1A. Risk Factors. It is also expected that some publicly-owned utilities will build new or duplicate transmission or distribution facilities to serve existing or potential new Utility customers, bypassing the Utility's electric infrastructure. In some instances, microgrid formation is a key factor in a community's choice to engage governmental entities. Some private companies have also called for changes in law that could allow those companies to privately serve electricity to retail customers without being regulated by the CPUC as public utilities. To the extent such changes occur and result in large customers reducing the share of transmission, distribution, and non-bypassable charges they pay, PG&E Corporation's and the Utility's financial condition and results of operations could be materially impacted. The effect of such types of retail competition generally is to reduce the number of utility customers, leading to decreased growth or a reduction in the Utility's rate base. The Utility also competes for the opportunity to develop and construct certain types of electric transmission facilities within, or interconnected to, its service area through a competitive bidding process managed by the CAISO.

FY 2024 10-K
Added
Filed Feb 13, 2025

Competition Trends in Market Demand and Competitive Conditions in the Electricity Industry The Utility expects customer electric load to increase in coming years primarily as a result of electric vehicle adoption, data centers, and building electrification. The Utility is not able to predict how quickly this electrification will occur. The Utility expects customer demand for gas to decrease in the coming years, primarily in response to policies supporting California's climate goals. California law allows qualifying non-residential electric customers of IOUs to purchase electricity from energy service providers rather than from the utilities up to certain annual limits specified for each utility. This arrangement is known as DA. In addition, California law permits cities, counties, and certain other public agencies that have qualified to become a CCA to generate or purchase electricity for their local residents and businesses. By law, a CCA can procure electricity for all of its residents and businesses that do not affirmatively elect to continue to receive electricity generated or procured by a utility. The Utility continues to provide transmission, distribution, metering, and billing services to DA customers at the election of their energy service provider. The CCA customers continue to obtain transmission, distribution, metering, and billing services from the Utility. In addition to collecting charges for transmission, distribution, metering, and billing services that it provides, the Utility is able to collect charges intended to recover the generation-related costs that the Utility incurred on behalf of DA and CCA customers while they were the Utility's customers. The Utility remains the electricity provider of last resort for these customers. Section 387 of the Public Utilities Code allows for a request to transfer the responsibilities of the provider of last resort obligation from IOUs to other entities. The Utility is also impacted by an increasing quantity of distributed generation and energy storage. The levels of self-generation of electricity by customers (primarily solar installations) and customer enrollment in NEM, which allows self-generating customers employing qualifying renewable resources to receive bill credits at the full retail rate, put upward rate pressure on non-NEM customers. The successor to the NEM tariffs, the NBT provides bill credits at a lower rate, which reduces the level of upward rate pressure on non-NEM or non-NBT customers, but does not eliminate the upward rate pressure. NEM and NBT customers are required to pay an interconnection fee, utilize time of use rates, and pay certain non-bypassable charges to help fund some of the costs of low income, energy efficiency, and other programs that other customers pay. Significantly higher bills for non-NEM or non-NBT customers may result in a decline of the number of such customers as they may seek alternative energy providers or adopt self-generation technologies. See "Concerns about high rates for the Utility's customers could negatively impact PG&E Corporation's and the Utility's financial condition, results of operations, liquidity, and cash flows" in Item 1A. Risk Factors and "Regulatory Matters - Order Instituting Rulemaking ("OIR") to Revisit Net Energy Metering Tariffs" in Item 7. MD&A. Further, in some circumstances, governmental entities such as cities and irrigation districts may have authority under the state constitution or state statute to provide retail electric service directly to consumers, in some cases bypassing the Utility's electric infrastructure entirely. Those entities may also rely upon FERC open access tariffs and Utility infrastructure to deliver their energy for resale at retail to existing or potential new Utility customers. These entities may also seek to acquire the Utility's transmission or distribution facilities through eminent domain for use in serving electricity at retail to existing or potential new Utility customers. As a result, the Utility could lose customers (residential, commercial, and industrial) or experience limited growth in the municipality. See "Jurisdictions attempt to acquire the Utility's assets through eminent domain, and third parties attempt to acquire the Utility's customers by bypassing the Utility's electric infrastructure system" in Item 1A. Risk Factors. It is also expected that some publicly-owned utilities will build new or duplicate transmission or distribution facilities to serve existing or potential new Utility customers, bypassing the Utility's electric infrastructure. In some instances, microgrid formation is a key factor in a community's choice to engage governmental entities. Some private companies have also called for changes in law that could allow those companies to privately serve electricity to retail customers without being regulated by the CPUC as public utilities. To the extent such changes occur and result in large customers reducing the share of transmission, distribution, and non-bypassable charges they pay, PG&E Corporation's and the Utility's financial condition and results of operations could be materially impacted. The effect of such types of retail competition generally is to reduce the number of utility customers, leading to decreased growth or a reduction in the Utility's rate base. The Utility also competes for the opportunity to develop and construct certain types of electric transmission facilities within, or interconnected to, its service area through a competitive bidding process managed by the CAISO.

reworded •Renewable and zero-carbon resources supplying 90% of utilities' retail sales to customers by 2035, 95% by 2040, and 100% by 2045.

FY 2023 10-K
Removed
Filed Feb 22, 2024

•Economy-wide State carbon neutrality by 2045, with net negative emissions thereafter. •Renewable and zero-carbon resources supplying 90% of utilities' retail sales to customers by 2035, 95% by 2040, and 100% by 2045. For the percentage of the Utility's estimated total net deliveries of electricity to customers in 2023, including estimated GHG-free and renewable energy percentages, see "Electric Utility Operations - Electricity Resources" below. The CARB has also approved GHG emissions reporting and a state-wide, comprehensive cap-and-trade program that sets gradually declining limits (or "caps") on the amount of GHGs that may be emitted by major GHG emission sources within different sectors of the economy. The cap-and-trade program has been extended through 2030. The CARB plans to update the cap-and-trade regulation in 2024 and is considering reforms that would reduce overall allowance budgets to align with CARB's 2022 Climate Change Scoping Plan. 20 During each year of the program, the CARB issues emission allowances (i.e., the rights to emit GHGs) equal to the amount of GHG emissions allowed for that year. Entities with a compliance obligation can obtain allowances from the CARB at quarterly auctions or from third parties or exchanges. Complying entities may also satisfy a portion of their compliance obligation through the purchase of offset credits (e.g., credits for GHG reductions achieved by third parties, such as landowners, livestock owners, and farmers, that occur outside of the entities' facilities through CARB-qualified offset projects such as reforestation or biomass projects). The Utility expects all costs and revenues associated with the GHG cap-and-trade program to be passed through to customers. The cap-and-trade program applies to the electric generation, large industrial, natural gas, petroleum, and transportation sectors. The Utility's compliance obligation as a natural gas supplier applies to the GHG emissions attributable to the combustion of natural gas delivered to the Utility's customers other than large natural gas delivery customers that are separately regulated as covered entities and have their own compliance obligations.

FY 2024 10-K
Added
Filed Feb 13, 2025

•Renewable and zero-carbon resources supplying 90% of utilities' retail sales to customers by 2035, 95% by 2040, and 100% by 2045. The CARB has also approved GHG emissions reporting and a state-wide, comprehensive cap-and-trade program that sets gradually declining limits (or "caps") on the amount of GHGs that may be emitted by major GHG emission sources within different sectors of the economy. The cap-and-trade program has been extended through 2030. The CARB plans to update the cap-and-trade regulation in 2025 and is considering reforms that would reduce overall allowance budgets to align with CARB's 2022 Climate Change Scoping Plan. 34 During each year of the program, the CARB issues emission allowances (i.e., the rights to emit GHGs) equal to the amount of GHG emissions allowed for that year. Entities with a compliance obligation can obtain allowances from the CARB at quarterly auctions or from third parties or exchanges. Complying entities may also satisfy a portion of their compliance obligation through the purchase of offset credits (e.g., credits for GHG reductions achieved by third parties, such as landowners, livestock owners, and farmers, that occur outside of the entities' facilities through CARB-qualified offset projects such as reforestation or methane capture projects). The Utility expects all costs and revenues associated with the GHG cap-and-trade program to be passed through to customers. The cap-and-trade program applies to the electric generation, large industrial, natural gas, and transportation sectors. The Utility's compliance obligation as a natural gas supplier applies to the GHG emissions attributable to the combustion of natural gas delivered to the Utility's customers other than large natural gas delivery customers that are separately regulated as covered entities and have their own compliance obligations. The federal administration of President Trump has led to uncertainty with regard to what further actions may occur regarding climate change at the federal level.

reworded 39,446,426

FY 2023 10-K
Removed
Filed Feb 22, 2024

Scope 1 and 2 emissions (1) 3,372,509 Scope 3 emissions (2) 38,753,533 (1) Scope 1 emissions are direct emissions from the Utility's operations and Scope 2 emissions are indirect emissions from facility electricity use and electric line losses. (2) Scope 3 emissions are emissions resulting from downstream value chain activities not owned or controlled by the Utility but that which can be indirectly impacted by the Utility's actions. The majority of these emissions came from customer natural gas use. The Utility utilized the CEC's Power Source Disclosure program methodology to calculate the CO2 emissions rate associated with the electricity delivered to retail customers in 2022. This resulted in a third-party verified CO2 emissions rate of 56 pounds of CO2 per MWh.

FY 2024 10-K
Added
Filed Feb 13, 2025

Scope 1 and 2 emissions (1) 4,026,490 Scope 3 emissions (2) 39,446,426 (1) Scope 1 emissions are direct emissions from the Utility's operations and Scope 2 emissions are indirect emissions from facility electricity use and electric line losses. 36 (2) Scope 3 emissions are emissions resulting from downstream value chain activities not owned or controlled by the Utility but that which can be indirectly impacted by the Utility's actions. The majority of these emissions came from customer natural gas use. The Utility utilized the CEC's Power Source Disclosure program methodology to calculate the CO2 emissions rate associated with the electricity delivered to retail customers in 2023. This resulted in a third-party verified CO2 emissions rate of 12 pounds of CO2 per MWh.

reworded SO2 emissions rate (pounds/MWh)

FY 2023 10-K
Removed
Filed Feb 22, 2024

20222021 Total NOx emissions (tons)121 139 NOx emissions rate (pounds/MWh)0.01 0.01 Total SO2 emissions (tons) 11 14 SO2 emissions rate (pounds/MWh)

FY 2024 10-K
Added
Filed Feb 13, 2025

20232022 Total NOx emissions (tons)139 121 NOx emissions rate (pounds/MWh)0.01 0.01 Total SO2 emissions (tons) 13 11 SO2 emissions rate (pounds/MWh)

  FY2022 → FY2023 Text Diffs 

escalated Other Regulators A new regulatory section was added detailing that the Department of Transportation's Pipeline and Hazardous Materials Safety Administration has established regulations for natural gas facilities, which the CPUC administers oversight for. Furthermore, the OEIS expanded its responsibilities to include reviewing proposed undergrounding plans under SB 884.

FY 2022 10-K
Removed
Filed Feb 23, 2023

Other Regulators The CEC is California's primary energy policy and planning agency. The CEC is responsible for licensing all thermal power plants over 50 MW within California. The CEC also is responsible for forecasts of future energy needs used by the CPUC in determining the adequacy of the utilities' electricity procurement plans and for adopting building and appliance energy efficiency requirements. The CARB is the state agency responsible for setting and monitoring GHG and other emission limits. The CARB is also responsible for adopting and enforcing regulations to implement state law requirements to gradually reduce GHG emissions in California. See "Environmental Regulation - Air Quality and Climate Change" below. 18 The NTSB is an independent U.S. government investigative agency responsible for civil transportation accident investigations, including pipeline accidents. The NTSB also conducts special investigations and safety studies, and issues safety recommendations to prevent future accidents. The California Geologic Energy Management Division is the state agency responsible for establishing and enforcing regulations for the operation of the Utility's underground gas storage facilities. The OEIS is a state agency responsible for reviewing and approving the Utility's WMP and for evaluating the Utility's implementation of the WMP. The OEIS is also responsible for reviewing and issuing the Utility's annual safety certification, annually reviewing and approving the Utility's executive compensation plan, conducting assessments of the Utility's safety culture, and conducting field inspections of wildfire mitigation activities. In addition, the Utility obtains permits, authorizations, and licenses in connection with the construction and operation of the Utility's generation facilities, electricity transmission lines, natural gas transportation pipelines, and gas compressor station facilities. The Utility also periodically obtains permits, authorizations, and licenses in connection with distribution of electricity and natural gas that grant the Utility rights to occupy or use public property for the operation of the Utility's business and to conduct certain related operations. The Utility has franchise agreements with approximately 300 cities and counties that permit the Utility to install, operate, and maintain the Utility's electric and natural gas facilities in the public streets and highways. In exchange for the right to use public streets and highways, the Utility pays annual fees to the cities and counties. In most cases, the Utility's franchise agreements are for an indeterminate term, with no expiration date. For more information see Item 1A. Risk Factors.

FY 2023 10-K
Added
Filed Feb 22, 2024

Other Regulators The CEC is a California agency with responsibility for energy policy and planning. The CEC is responsible for licensing all thermal power plants over 50 MW within California. The CEC establishes forecasts of future energy needs used by the CPUC in determining the adequacy of utilities' and other load-serving entities' electricity procurement. The CEC also promotes energy management and conservation programs, including setting standards for building and appliance energy efficiency and load management programs. The CARB is the state agency responsible for setting and monitoring GHG and other emission limits. The CARB is also responsible for adopting and enforcing regulations to implement state law requirements to gradually reduce GHG emissions in California. See "Environmental Regulation - Air Quality and Climate Change" below. The NTSB is an independent U.S. government investigative agency responsible for civil transportation accident investigations, including pipeline accidents. The NTSB also conducts special investigations and safety studies, and issues safety recommendations to prevent future accidents. The California Geologic Energy Management Division is the state agency responsible for establishing and enforcing regulations for the operation of the Utility's underground gas storage facilities. The Department of Transportation's ("DOT") Pipeline and Hazardous Materials Safety Administration has established regulations regarding the design, construction, operation, maintenance, integrity, safety, and security of natural gas distribution, transmission, and underground storage facilities. The DOT has certified the CPUC to administer oversight and compliance with these regulations for the entities it regulates in California. 18 The OEIS is a state agency responsible for reviewing and approving the Utility's WMP and for evaluating the Utility's implementation of the WMP. The OEIS is also responsible for reviewing and issuing the Utility's annual safety certification, annually reviewing and approving the Utility's executive compensation plan, conducting assessments of the Utility's safety culture, conducting field inspections of wildfire mitigation activities, and reviewing proposed undergrounding plans under SB 884. In addition, the Utility obtains permits, authorizations, and licenses in connection with the construction and operation of the Utility's generation facilities, electricity transmission lines, natural gas transportation pipelines, and gas compressor station facilities. Delay in obtaining, or failure to obtain and maintain, any such permits, authorizations, or licenses could prevent construction of new facilities, limit or prevent continued operation of existing facilities, or result in significant additional costs or restrictions on operations. The Utility also periodically obtains permits, authorizations, and licenses in connection with distribution of electricity and natural gas that grant the Utility rights to occupy or use public property for the operation of the Utility's business and to conduct certain related operations. The Utility has franchise agreements with approximately 300 cities and counties that permit the Utility to install, operate, and maintain the Utility's electric or natural gas facilities in the public streets and highways. In exchange for the right to use public streets and highways, the Utility pays annual fees to the cities and counties. In most cases, the Utility's franchise agreements are for an indeterminate term, with no expiration date. For more information see Item 1A. Risk Factors.

escalated Cost of Capital Proceedings

FY 2022 10-K
Removed
Filed Feb 23, 2023

Cost of Capital Proceedings The CPUC periodically conducts a cost of capital proceeding to authorize the Utility's capital structure and rates of return for its electric generation, electric and natural gas distribution, and natural gas transmission and storage rate base. The CPUC's cost of capital proceedings generally take place in a consolidated proceeding with California's other large investor-owned electric and gas utilities. For more information about the cost of capital proceedings, see "Regulatory Matters - Cost of Capital Proceedings" in Item 7. MD&A.

FY 2023 10-K
Added
Filed Feb 22, 2024

Cost of Capital Proceedings The CPUC periodically conducts a cost of capital proceeding to authorize the Utility's capital structure and rates of return for its electric generation, electric and natural gas distribution, and natural gas transmission and storage rate base. The rate of return, or cost of capital, is the weighted average cost of debt, preferred equity, and common stock a utility has issued to finance its utility capital investments. The CPUC's cost of capital proceedings generally take place in a consolidated proceeding with California's other large investor-owned electric and gas utilities. For more information about the cost of capital proceedings, see "Regulatory Matters - Cost of Capital Proceedings" in Item 7. MD&A.

escalated •Helped customers avoid emissions and manage energy costs through robust energy efficiency programs. The Utility increased its GHG-free electricity delivery from over 95% to 100%, while also launching a first-of-its-kind vehicle-to-grid program and introducing an initiative to purchase renewable natural gas toward a target of serving 15% of bundled residential and small commercial demand by 2030. Additionally, the Utility expanded its battery energy storage management contracts from 3.3 GWs to over 3.5 GW and increased the total number of interconnected private solar customers to more than 800,000.

FY 2022 10-K
Removed
Filed Feb 23, 2023

•Delivered clean electricity to customers in 2022 that was more than 95% GHG free. •Helped customers avoid emissions and energy costs through robust energy efficiency programs. •Awarded contracts for more than 3.3 GWs of battery energy storage to be deployed over the next several years, strengthening California's grid efficiency and reliability. •Installed approximately 340 charging ports for electric vehicles at schools, parks, public charging locations, and in support of fleets - with nearly half in disadvantaged communities - and received regulatory approval for new innovative pilots on vehicle grid integration, submetering, and dynamic rates. •Brought the total number of interconnected private solar customers to more than 700,000 and supported more than 50,000 customers who have installed battery storage at their homes or businesses. •Continued to advance decarbonization initiatives for the Utility's natural gas delivery system, including meeting the CPUC-mandated methane emission reduction target ahead of schedule and accelerating initiatives to meet its voluntary 2030 reduction goal. 13 The CPUC coordinates the planning of supply resources through the Integrated Resource Planning ("IRP") proceeding and has determined that replacing the power generated by Diablo Canyon is the responsibility of all LSEs within the CAISO. Looking ahead, the Utility expects its GHG-free energy supply mix of renewable, large hydroelectric, and nuclear generation resources to decrease as, beginning in 2023, the Utility is required to offer for allocation or sale renewables portfolio standard-eligible ("RPS") attributes that the Utility procured on behalf of customers that subsequently switched to non-Utility providers in order to comply with regulatory mandates and to manage customer affordability. Towards the end of the decade and beyond, the Utility's GHG-free energy supply mix is expected to grow relative to 2025 levels as the Utility procures new GHG-free generation and storage to meet California's IRP GHG emissions reduction targets and California's clean energy goals. For more information, see "Electric Integrated Resource Planning and Related Procurement" below.

FY 2023 10-K
Added
Filed Feb 22, 2024

•Delivered electricity to customers in 2023 that was 100% GHG free (see "Electricity Resources" below for more information). •Helped customers avoid emissions and manage energy costs through robust energy efficiency programs. •Managed contracts for more than 3.5 GW of battery energy storage to be deployed over the next several years and operated 183 MW of Utility-owned battery storage, strengthening California's grid efficiency and reliability. •Helped enable the total number of electric vehicles operating in the Utility's service area to exceed 550,000; installed more than 475 charging ports for electric vehicles at schools, public charging locations, and in support of fleets; and launched a first of its kind vehicle-to-grid program enabling customers to leverage their electric vehicles to power their home. •Brought the total number of interconnected private solar customers to more than 800,000 and supported more than 70,000 customers who have installed battery storage at their homes or businesses. •Continued to advance decarbonization initiatives for the Utility's natural gas delivery system, including meeting the CPUC-mandated methane emission reduction target ahead of schedule and accelerated initiatives to meet its voluntary 2030 reduction goal. The Utility also launched an initiative to purchase California-produced renewable natural gas for its natural gas customers, toward a target to procure renewable natural gas to serve 15% of its bundled residential and small commercial demand by 2030. The CPUC coordinates the planning of supply resources through the Integrated Resource Planning ("IRP") proceeding and has determined that replacing the power generated by Diablo Canyon is the responsibility of all LSEs within the CAISO. Looking ahead, the Utility expects its GHG-free energy supply mix of renewable, large hydroelectric, and nuclear generation resources to decrease as, beginning in 2023, the Utility was required to offer, for allocation or sale, renewable sources eligible under California's RPS program that the Utility procured on behalf of customers that subsequently switched to non-Utility providers. These requirements were established to comply with regulatory mandates and to manage customer affordability. Towards the end of the decade and beyond, the Utility's GHG-free energy supply mix is expected to grow relative to 2025 levels as the Utility procures new GHG-free generation and storage to meet California's IRP GHG emissions reduction targets and California's clean energy goals. PG&E Corporation's and the Utility's voluntary goal continues to be to deliver 70% RPS clean electricity by 2030, compared to a state mandate of 60% (see "Air Quality and Climate Change" below for more information).

escalated Energy Storage

FY 2022 10-K
Removed
Filed Feb 23, 2023

Energy Storage Energy storage improves system reliability and supports California's decarbonization goals by integrating increased levels of renewable energy. The CPUC has established a multi-year energy storage procurement framework, under which the Utility was required to procure 580 MW of qualifying storage capacity by the end of 2020, with all energy storage projects required to be operational by the end of 2024. As of December 31, 2022, the Utility was on track to meet its storage goals by the end of 2024. Additionally, the Utility has been actively procuring energy storage to meet critical reliability needs. The CPUC previously approved more than 1,100 MW of storage to come online in 2022 and 2023. In January 2022, the Utility also requested CPUC approval for another 1,600 MW of storage to be completed by the summer of 2024, which would bring the Utility's total energy storage system capacity to more than 3,330 MW. Finally, the Utility is soliciting 200 MW of long-duration storage, which is storage with at least eight hours of discharge capacity, to have these resources online between 2026 and 2028.

FY 2023 10-K
Added
Filed Feb 22, 2024

Energy Storage Energy storage improves system reliability and supports California's decarbonization goals by integrating increased levels of renewable energy. The CPUC has established a multi-year energy storage procurement framework, under which the Utility was required to procure 580 MW of qualifying storage capacity by the end of 2020, with all energy storage projects required to be operational by the end of 2024. As of December 31, 2023, the Utility was on track to meet its storage goals by the end of 2024. Additionally, the Utility has been actively procuring energy storage to meet critical reliability needs. The CPUC previously approved more than 1,100 MW of storage to come online in 2022 and 2023. In January 2022, the Utility also requested CPUC approval for another 1,600 MW of storage to be completed by the summer of 2024, which would bring the Utility's total energy storage system capacity to more than 3,330 MW. Finally, the Utility is soliciting 200 MW of long-duration storage, which is storage with at least eight hours of discharge capacity, to have these resources online between 2026 and 2028. In order to address both its bundled portfolio need and to help to meet State planning and policy objectives to increase long-duration storage capacity after 2028, the Utility is pursuing regulatory approval to increase the nameplate generating capacity of its Helms Pumped Storage Facility. 30

escalated Electricity Transmission

FY 2022 10-K
Removed
Filed Feb 23, 2023

Electricity Transmission As of December 31, 2022, the Utility owned approximately 18,000 circuit miles of interconnected transmission lines operating at voltages ranging from 60 kV to 500 kV. The Utility also operated 33 electric transmission substations with a capacity of approximately 65,000 MVA. The Utility's electric transmission system is interconnected with electric power systems in the Western Electricity Coordinating Council, which includes many western states, the Canadian provinces of Alberta and British Columbia, and parts of Mexico.

FY 2023 10-K
Added
Filed Feb 22, 2024

Electricity Transmission Transmission lines deliver electricity at high voltages and over long distances from power sources to transmission substations closer to customers. A strong transmission system supports reliable and affordable service, ability to meet state energy policy goals, and support for a diverse generation mix, including renewable energy. As of December 31, 2023, the Utility owned approximately 18,000 circuit miles of interconnected transmission lines operating at voltages ranging from 60 kV to 500 kV. The Utility also operated 33 electric transmission substations with a capacity of approximately 66,000 MVA. The Utility's electric transmission system is interconnected with electric power systems in the Western Electricity Coordinating Council, which includes many western states, the Canadian provinces of Alberta and British Columbia, and parts of Mexico.

escalated Natural Gas Operating Statistics

FY 2022 10-K
Removed
Filed Feb 23, 2023

Natural Gas Operating Statistics The following table shows the Utility's operating statistics from 2020 through 2022 (excluding subsidiaries) for natural gas, including the classification of revenues by type of service. No single customer of the Utility accounted for 10% or more of consolidated revenues for bundled gas sales in 2022, 2021 or 2020.

FY 2023 10-K
Added
Filed Feb 22, 2024

In 2023, the Utility continued upgrading transmission pipeline to allow for the use of in-line inspection tools. 33 Natural Gas Operating Statistics The following table shows the Utility's operating statistics from 2021 through 2023 (excluding subsidiaries) for natural gas, including the classification of revenues by type of service. No single customer of the Utility accounted for 10% or more of consolidated revenues for bundled gas sales in 2023, 2022 or 2021.

escalated Trends in Market Demand and Competitive Conditions in the Electricity Industry The competitive risk section was expanded to include the threat of unregulated private companies serving customers without CPUC oversight and clarified that governmental entities may now provide retail service while bypassing the Utility's electric infrastructure entirely. Furthermore, the analysis on distributed generation was updated to detail how the successor NEM tariff (NBT) reduces but does not eliminate upward rate pressure on non-NEM or non-NBT customers.

FY 2022 10-K
Removed
Filed Feb 23, 2023

(2) These amounts represent revenues authorized to be billed. Competition Trends in Market Demand and Competitive Conditions in the Electricity Industry The Utility expects customer electric load to increase in coming years primarily as a result of electrification of buildings and transportation. The Utility is not able to predict how quickly this electrification will occur. The Utility expects customer demand for gas to decrease in the coming years, primarily in response to policies supporting California's climate goals. California law allows qualifying non-residential electric customers of IOUs to purchase electricity from energy service providers rather than from the utilities up to certain annual limits specified for each utility. This arrangement is known as DA. In addition, California law permits cities, counties, and certain other public agencies that have qualified to become a CCA to generate or purchase electricity for their local residents and businesses. By law, a CCA can procure electricity for all of its residents and businesses that do not affirmatively elect to continue to receive electricity generated or procured by a utility. The Utility continues to provide transmission, distribution, metering, and billing services to DA customers at the election of their energy service provider. The CCA customers continue to obtain transmission, distribution, metering, and billing services from the Utility. In addition to collecting charges for transmission, distribution, metering, and billing services that it provides, the Utility is able to collect charges intended to recover the generation-related costs that the Utility incurred on behalf of DA and CCA customers while they were the Utility's customers. The Utility remains the electricity provider of last resort for these customers. Section 387 of the Public Utilities Code allows for a request to transfer the responsibilities of the provider of last resort obligation from IOUs to other entities. 34 The Utility is also impacted by the increasing viability of distributed generation and energy storage. The levels of self-generation of electricity by customers (primarily solar installations) and customer enrollment in NEM, which allows self-generating customers employing qualifying renewable resources to receive bill credits at the full retail rate, are increasing, putting upward rate pressure on remaining customers. New NEM customers, as well as customers interconnecting on the successor to the NEM tariffs, are required to pay an interconnection fee, utilize time of use rates, and are required to pay certain non-bypassable charges to help fund some of the costs of low income, energy efficiency, and other programs that other customers pay. Significantly higher bills for remaining customers may result in a decline of the number of such customers as they may seek alternative energy providers or adopt self-generation technologies. See "Rising rates for the Utility's customers could result in circumstances in which the Utility is unable to fully recover costs or earn its authorized ROE" in Item 1A. Risk Factors and "Regulatory Matters - OIR to Revisit Net Energy Metering Tariffs" in Item 7. MD&A. Further, in some circumstances, governmental entities such as cities and irrigation districts may have authority under the state constitution or state statute to provide retail electric service directly to consumers. Those entities may rely upon FERC open access tariffs and Utility infrastructure to deliver energy to them at wholesale rates for resale at retail to existing or potential new Utility customers. These entities may also seek to acquire the Utility's transmission or distribution facilities through eminent domain for use in serving electricity at retail to existing or potential new Utility customers. As a result, the Utility could lose customers (residential, commercial, and industrial) in the municipality. See "Jurisdictions may attempt to acquire the Utility's assets through eminent domain" in Item 1A. Risk Factors. It is also expected that some publicly-owned utilities will build new or duplicate transmission or distribution facilities to serve existing or potential new Utility customers. In some instances, microgrid formation is a key factor in a community's choice to engage governmental entities. The effect of such types of retail competition generally is to reduce the number of utility customers, leading to a reduction in the Utility's rate base. The Utility also competes for the opportunity to develop and construct certain types of electric transmission facilities within, or interconnected to, its service area through a competitive bidding process managed by the CAISO.

FY 2023 10-K
Added
Filed Feb 22, 2024

(2) These amounts represent revenues authorized to be billed. Competition Trends in Market Demand and Competitive Conditions in the Electricity Industry The Utility expects customer electric load to increase in coming years primarily as a result of electrification of buildings and transportation. The Utility is not able to predict how quickly this electrification will occur. The Utility expects customer demand for gas to decrease in the coming years, primarily in response to policies supporting California's climate goals. California law allows qualifying non-residential electric customers of IOUs to purchase electricity from energy service providers rather than from the utilities up to certain annual limits specified for each utility. This arrangement is known as DA. In addition, California law permits cities, counties, and certain other public agencies that have qualified to become a CCA to generate or purchase electricity for their local residents and businesses. By law, a CCA can procure electricity for all of its residents and businesses that do not affirmatively elect to continue to receive electricity generated or procured by a utility. The Utility continues to provide transmission, distribution, metering, and billing services to DA customers at the election of their energy service provider. The CCA customers continue to obtain transmission, distribution, metering, and billing services from the Utility. In addition to collecting charges for transmission, distribution, metering, and billing services that it provides, the Utility is able to collect charges intended to recover the generation-related costs that the Utility incurred on behalf of DA and CCA customers while they were the Utility's customers. The Utility remains the electricity provider of last resort for these customers. Section 387 of the Public Utilities Code allows for a request to transfer the responsibilities of the provider of last resort obligation from IOUs to other entities. 34 The Utility is also impacted by an increasing quantity of distributed generation and energy storage. The levels of self-generation of electricity by customers (primarily solar installations) and customer enrollment in NEM, which allows self-generating customers employing qualifying renewable resources to receive bill credits at the full retail rate, put upward rate pressure on non-NEM customers. The successor to the NEM tariffs, the NBT, will provide bill credits at a lower rate, which reduces the level of upward rate pressure on non-NEM or non-NBT customers, but does not eliminate such upward rate pressure. Like NEM customers, customers interconnecting on the NBT, are required to pay an interconnection fee, utilize time of use rates, and pay certain non-bypassable charges to help fund some of the costs of low income, energy efficiency, and other programs that other customers pay. Significantly higher bills for non-NEM or non-NBT customers may result in a decline of the number of such customers as they may seek alternative energy providers or adopt self-generation technologies. See "Concerns about high rates for the Utility's customers could negatively impact PG&E Corporation's and the Utility's financial condition, results of operations, liquidity, and cash flows" in Item 1A. Risk Factors and "Regulatory Matters - OIR to Revisit Net Energy Metering Tariffs" in Item 7. MD&A. Further, in some circumstances, governmental entities such as cities and irrigation districts may have authority under the state constitution or state statute to provide retail electric service directly to consumers, in some cases bypassing the Utility's electric infrastructure entirely. Those entities may also rely upon FERC open access tariffs and Utility infrastructure to deliver their energy for resale at retail to existing or potential new Utility customers. These entities may also seek to acquire the Utility's transmission or distribution facilities through eminent domain for use in serving electricity at retail to existing or potential new Utility customers. As a result, the Utility could lose customers (residential, commercial, and industrial) or experience limited growth in the municipality. See "Jurisdictions may attempt to acquire the Utility's assets through eminent domain, and third parties may attempt to acquire the Utility's customers by bypassing the Utility's electric infrastructure system" in Item 1A. Risk Factors. It is also expected that some publicly-owned utilities will build new or duplicate transmission or distribution facilities to serve existing or potential new Utility customers, bypassing the Utility's electric infrastructure. In some instances, microgrid formation is a key factor in a community's choice to engage governmental entities. Some private companies have also called for changes in law that could allow those companies to privately serve electricity to retail customers without being regulated by the CPUC as public utilities. To the extent such changes occur and result in large customers reducing the share of transmission, distribution, and non-bypassable charges they pay, PG&E Corporation's and the Utility's financial condition and results of operations could be materially impacted. The effect of such types of retail competition generally is to reduce the number of utility customers, leading to decreased growth or a reduction in the Utility's rate base. The Utility also competes for the opportunity to develop and construct certain types of electric transmission facilities within, or interconnected to, its service area through a competitive bidding process managed by the CAISO.

de-emphasised PG&E Corporation's and the Utility's operating revenues, income, and total assets can be found below in Item 8. Financial Statements and Supplementary Data.

FY 2022 10-K
Removed
Filed Feb 23, 2023

PG&E Corporation's and the Utility's operating revenues, income, and total assets can be found below in Item 8. Financial Statements and Supplementary Data. The principal executive offices of PG&E Corporation and the Utility are located at 300 Lakeside Drive, Oakland, California 94612. PG&E Corporation's telephone number is (415) 973-1000 and the Utility's telephone number is (415) 973-7000. This is a combined Annual Report on Form 10-K for PG&E Corporation and the Utility. Each of PG&E Corporation and the Utility is a separate entity, with distinct creditors and claimants, and is subject to separate laws, rules, and regulations. 11 Over the past several years, Northern California has experienced major wildfires. For more information about material wildfires, see Item 7. MD&A, and Note 15 of the Notes to the Consolidated Financial Statements in Item 8. This 2022 Form 10-K contains forward-looking statements that are necessarily subject to various risks and uncertainties. For a discussion of the significant risks that could affect the outcome of these forward-looking statements and PG&E Corporation's and the Utility's future financial condition, results of operations, liquidity, and cash flows, see Item 1A. Risk Factors and "Forward-Looking Statements" above.

FY 2023 10-K
Added
Filed Feb 22, 2024

PG&E Corporation's and the Utility's operating revenues, income, and total assets can be found below in Item 8. Financial Statements and Supplementary Data. The principal executive offices of PG&E Corporation and the Utility are located at 300 Lakeside Drive, Oakland, California 94612. PG&E Corporation's telephone number is (415) 973-1000 and the Utility's telephone number is (415) 973-7000. This is a combined Annual Report on Form 10-K for PG&E Corporation and the Utility. Each of PG&E Corporation and the Utility is a separate entity. This 2023 Form 10-K contains forward-looking statements that are necessarily subject to various risks and uncertainties. For a discussion of the significant risks that could affect the outcome of these forward-looking statements and PG&E Corporation's and the Utility's future financial condition, results of operations, liquidity, and cash flows, see Item 1A. Risk Factors and "Forward-Looking Statements" above.

de-emphasised Emissions Data

FY 2022 10-K
Removed
Filed Feb 23, 2023

Emissions Data PG&E Corporation and the Utility track and report their annual environmental performance results across a broad spectrum of areas. The Utility reports its GHG emissions to the CARB and the EPA on a mandatory basis. On a voluntary basis, the Utility reports a more comprehensive emissions inventory to The Climate Registry, a non-profit organization. The Utility's third-party verified voluntary GHG inventory reported to The Climate Registry for 2021, which is the most recent data available, totaled Scope 1 and 2 emissions of approximately 4.6 million metric tons of CO2 equivalent (MMT CO2e) and Scope 3 emissions of approximately 42 MMT CO2e, the majority of which came from customer natural gas use. The following table shows the 2021 GHG emissions data the Utility reported to the CARB, which is the most recent data available. PG&E Corporation and the Utility also publish additional GHG emissions data in their annual Corporate Sustainability Report.

FY 2023 10-K
Added
Filed Feb 22, 2024

Emissions Data PG&E Corporation and the Utility track and report their annual environmental performance results across a broad spectrum of areas. The Utility reports its GHG emissions to the CARB and the EPA on a mandatory basis. On a voluntary basis, the Utility reports a more comprehensive emissions inventory to The Climate Registry, a non-profit organization. The following table shows the Utility's third-party verified voluntary GHG inventory reported to The Climate Registry for 2022, which is the most recent data available.

de-emphasised Nuclear Fuel Disposal

FY 2022 10-K
Removed
Filed Feb 23, 2023

0.001 0.001 22 Nuclear Fuel Disposal Nuclear power plant operations produce gaseous, liquid, and solid radioactive wastes, which are covered by federal regulation. High-level radioactive wastes primarily include used nuclear fuel. Low-level waste consists primarily of demineralizer resins, paper, protective clothing, rags, tools, and equipment contaminated through use. Under the Nuclear Waste Policy Act of 1982, the DOE and electric utilities with commercial nuclear power plants were authorized to enter into contracts under which the DOE would be required to dispose of the utilities' spent nuclear fuel and high-level radioactive waste by January 1998, in exchange for fees paid by the utilities' customers. The DOE has been unable to meet its contractual obligation with the Utility to dispose of nuclear waste from the Utility's two nuclear generating units at Diablo Canyon and the retired nuclear facility at Humboldt Bay. As a result, the Utility constructed interim dry cask storage facilities to store its spent fuel onsite at Diablo Canyon and at Humboldt Bay until the DOE fulfills its contractual obligation to take possession of the spent fuel. The Utility and other nuclear power plant owners sued the DOE to recover the costs that they incurred to construct interim storage facilities for spent nuclear fuel. In September 2012, the DOJ and the Utility executed a settlement agreement that provided a claims process by which the Utility submits annual requests for reimbursement of its ongoing spent fuel storage costs. The claim for the period June 1, 2021 through May 31, 2022, totaled approximately $10.5 million and is under review by the DOE. Amounts reimbursed by DOE are refunded to customers through rates. Considerable uncertainty continues to exist regarding when and whether the DOE will meet its contractual obligation to the Utility and other nuclear power plant owners to dispose of spent fuel.

FY 2023 10-K
Added
Filed Feb 22, 2024

0.001 0.001 22 Nuclear Fuel Disposal Nuclear power plant operations produce gaseous, liquid, and solid radioactive wastes, which are covered by federal regulation. High-level radioactive wastes primarily include used nuclear fuel. Low-level waste consists primarily of demineralizer resins, paper, protective clothing, rags, tools, and equipment contaminated through use. Under the Nuclear Waste Policy Act of 1982, the DOE and electric utilities with commercial nuclear power plants were authorized to enter into contracts under which the DOE would be required to dispose of the utilities' spent nuclear fuel and high-level radioactive waste by January 1998, in exchange for fees paid by the utilities' customers. The DOE has been unable to meet its contractual obligation with the Utility to dispose of nuclear waste from the Utility's two nuclear generating units at Diablo Canyon and the retired nuclear facility at Humboldt Bay. As a result, the Utility constructed interim dry cask storage facilities to store its spent fuel onsite at Diablo Canyon and at Humboldt Bay until the DOE fulfills its contractual obligation to take possession of the spent fuel. The Utility and other nuclear power plant owners sued the DOE to recover the costs that they incurred to construct interim storage facilities for spent nuclear fuel.

de-emphasised Ratemaking Mechanisms The disclosure was significantly reduced, removing all subsequent details regarding cost of equity approval, pass-through costs, FERC formula rates, the use of regulatory balancing accounts to decouple base revenues from sales volume, seasonal demand impacts, and incentive ratemaking mechanisms.

FY 2022 10-K
Removed
Filed Feb 23, 2023

Ratemaking Mechanisms The Utility operates under a "cost-of-service" ratemaking model, which means that rates for electric and natural gas utility services are generally set at levels that are intended to allow the Utility to recover its costs of providing service and to earn a return on invested capital ("cost-of-service ratemaking"). In order to set rates, the CPUC and the FERC conduct proceedings to determine the amount that the Utility will be authorized to collect from its customers ("revenue requirements"). In the GRC proceedings, the CPUC also generally approves the level of capital spending on a forecasted basis. Revenue authorized by the CPUC through GRC proceedings is intended to provide the Utility a reasonable opportunity to recover its costs and earn a return on its investments in generation and distribution assets and general plant (also referred to as "rate base"). The Utility's revenue requirements consist primarily of a base amount set to enable the Utility to recover its reasonable operating expenses (e.g., maintenance, administration and general expenses) and capital costs (e.g., depreciation, and financing expenses). The Utility's costs of equity and long-term debt are generally approved in the CPUC's cost of capital proceedings. In addition, the CPUC authorizes the Utility to collect revenues to recover costs that the Utility is allowed to "pass through" to customers (referred to as "Utility Revenues and Costs that did not Impact Earnings" in Item 7. MD&A), including its costs to procure electricity and natural gas for customers and to administer public purpose and customer programs. FERC revenue requirements are set through a FERC-approved formula rate. The Utility's rate of return on electric transmission assets is determined in the FERC TO proceedings. Other than certain gas transmission and storage revenues, the Utility's base revenues are "decoupled" from its sales volume through certain regulatory balancing accounts, or revenue adjustment mechanisms, that are designed to allow the Utility to collect its authorized base revenue requirements regardless of sales volume. As a result, the Utility's base revenues are not impacted by fluctuations in sales resulting from, for example, weather or economic conditions. The Utility's earnings primarily depend on its ability to manage its base operating and capital costs (referred to as "Utility Revenues and Costs that Impacted Earnings" in Item 7. MD&A) within its authorized base revenue requirements. Due to the seasonal nature of the Utility's business and rate design, customer electric bills are generally higher during summer months (May to October) because of higher demand, driven by air conditioning loads. Customer bills related to gas service are generally higher during winter months (November to March) because of higher demand due to heating. From time to time, the CPUC may use incentive ratemaking mechanisms that provide the Utility an opportunity to earn additional revenues. For example, the Utility has earned incentives for the successful implementation of energy efficiency programs.

FY 2023 10-K
Added
Filed Feb 22, 2024

Ratemaking Mechanisms The Utility operates under a "cost-of-service" ratemaking model, which means that rates for electric and natural gas utility services are generally set at levels that are intended to allow the Utility to recover its costs of providing service and to earn a return on invested capital ("cost-of-service ratemaking"). To set rates, the CPUC and the FERC conduct proceedings to determine the amount that the Utility will be authorized to collect from its customers ("revenue requirements"). In the GRC proceedings, the CPUC also generally approves the level of spending on a forecasted basis. Revenue authorized by the CPUC through GRC proceedings is intended to provide the Utility a reasonable opportunity to recover its costs and earn a return on its investments in generation and distribution assets and general plant (also referred to as "rate base"). The Utility's revenue requirements consist primarily of a base amount set to enable the Utility to recover its reasonable operating expenses (e.g., maintenance, administration, and general expenses) and capital costs (e.g., depreciation, and financing expenses).

de-emphasised Safety

FY 2022 10-K
Removed
Filed Feb 23, 2023

All PG&E Corporation and Utility officer compensation currently is funded by shareholders. Safety The Utility's strategy to deliver on safety outcomes focuses on workforce, and public safety. In 2023, in addition to deploying the safety management system, the Utility targets mitigations to the highest risk work. The Utility's safety metrics include the number of SIF-A incidents and the SIF-P rate, which measures events that could have resulted in a SIF-A per 200,000 hours worked. In 2022, the Utility had seven SIF-A incidents, which resulted in three fatalities and four serious injuries, and a SIF-P rate of 0.11. Additionally, the Utility measures DART. In 2022, the Utility's DART was 0.67, which was 34% lower than in 2021 and its lowest rate in the past five years. Throughout the COVID-19 pandemic, PG&E Corporation and the Utility have continued to monitor activities at the Centers for Disease Control and Prevention and the World Health Organization. PG&E Corporation and the Utility have updated their protocols and actions in accordance with guidance from these organizations, following state and local health and safety regulations, and in consultation with the Utility's medical director. PG&E Corporation and the Utility have also remained focused on protecting the health and safety of their employees, contractors and the Utility's customers, while continuing to perform critical utility work, and have continued to monitor and track the impact of the pandemic, modifying or adopting new policies in support of their employees' health and safety as pandemic conditions and governmental response have changed.

FY 2023 10-K
Added
Filed Feb 22, 2024

All PG&E Corporation and Utility officer compensation currently is funded by shareholders. Safety The Utility's strategy to deliver on safety outcomes focuses on workforce and public safety. In 2023, in addition to deploying a safety management system, the Utility targets mitigations to the highest risk work. The Utility's safety metrics include the number of actual serious incidents or fatalities ("SIF-A") incidents and the "SIF-P" rate, which measures events that could have resulted in a SIF-A per 200,000 hours worked. In 2023, the Utility had four SIF-A incidents, which resulted in two fatalities and two serious injuries, and a SIF-P rate of 0.1. Additionally, the Utility measures DART (days away, restricted or transferred duty per 200,000 hours worked). In 2023, the Utility's DART was 0.7. In particular, the Utility improved safety through the reduction of preventable motor vehicle incidents ("PMVI"). In 2023, the Utility's PMVI rate was the lowest rate in the last eight years.

de-emphasised Renewable Energy Resources

FY 2022 10-K
Removed
Filed Feb 23, 2023

Renewable Energy Resources California law established an RPS that requires LSEs, such as the Utility, to gradually increase the amount of renewable energy they deliver to their customers. SB 350 increased the amount of renewable energy that must be delivered by most LSEs, including the Utility, to their customers from 33% of their total annual retail sales by the end of the 2017-2020 compliance period, to 50% of their total annual retail sales by the end of the 2028-2030 compliance period, and in each three-year compliance period thereafter, unless changed by legislative action. SB 350 provides compliance flexibility and waiver mechanisms, including increased flexibility to apply excess renewable energy procurement in one compliance period to future compliance periods. In September 2018, the California Governor signed SB 100 into law, increasing from 50% to 60% of California's electricity portfolio that must come from renewables by 2030; and established state policy that 100% of all retail electricity sales must come from RPS-eligible or carbon-free resources by 2045. The Utility may in the future incur additional costs to procure renewable energy to meet the new renewable energy targets, which the Utility expects will continue to be recoverable through rates as "pass-through" costs. The Utility also may be subject to penalties for failure to meet the higher targets. 29 Renewable generation resources, for purposes of the RPS requirements, include bioenergy such as biogas and biomass, certain hydroelectric facilities (30 MW or less), wind, solar, and geothermal energy. RPS requirements are based on procurement, which aligns with the methodology presented in the first column of the table above. Procurement from renewable energy sources was estimated to comprise 40% of total annual retail sales in 2022.

FY 2023 10-K
Added
Filed Feb 22, 2024

Renewable Energy Resources California law established an RPS that requires LSEs, such as the Utility, to gradually increase the amount of renewable energy they deliver to their customers. See "Environmental Regulation - Air Quality and Climate Change" above. The Utility may in the future incur additional costs to procure renewable energy to meet the new renewable energy targets, which the Utility expects will continue to be recoverable through rates as "pass-through" costs. The Utility also may be subject to penalties for failure to meet the higher targets. Renewable generation resources, for purposes of the RPS requirements, include bioenergy such as biogas and biomass, certain hydroelectric facilities (30 MW or less), wind, solar, and geothermal energy. RPS requirements are based on procurement, which aligns with the methodology presented in the first column of the table above. Procurement from renewable energy sources was estimated to comprise 37% of total annual retail sales in 2023. Per the Power Content Label methodology based on current CEC guidelines presented in the table above, an estimated 34% of the Utility's energy deliveries were from renewable energy sources in 2023.

de-emphasised Total37 %

FY 2022 10-K
Removed
Filed Feb 23, 2023

Biopower5 % Geothermal- % RPS-Eligible Small Hydroelectric2 % Solar24 % Wind9 % Total40 % (1) Estimated renewable procurement amounts are expected to be consistent with Power Content Label reporting and adjustments, based on current CEC guidelines. (2) Estimated renewable procurement percentages above and renewable compliance percentages are expected to be consistent; however, final RPS compliance reporting is subject to a different methodology and may result in some differences between the two percentages.

FY 2023 10-K
Added
Filed Feb 22, 2024

Biopower4 % Geothermal- % RPS-Eligible Small Hydroelectric3 % Solar24 % Wind6 % Total37 % (1) Estimated renewable procurement percentages above and renewable compliance percentages are expected to be consistent; however, final RPS compliance reporting is subject to a different methodology and may result in differences between the two percentages.

de-emphasised See "Ratemaking Mechanisms" below and "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC and FERC proceedings. The amount of Utility debt retired using SB 901 securitization bonds increased from $5.0 billion to $6.0 billion, and while the focus for additional capital expenditures narrowed by removing the Lakeside Building project, the utility expanded its forecast timeline through 2028 and added new investment opportunities including FERC-jurisdictional assets and hydroelectric facilities.

FY 2022 10-K
Removed
Filed Feb 23, 2023

Under cost-of-service ratemaking, a utility's earnings depend on the outcomes of its ratemaking proceedings and its ability to manage costs. See "Ratemaking Mechanisms" below and "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC and FERC proceedings. Generally, differences between forecast costs and actual costs (discussed in "Utility Revenues and Costs that Impacted Earnings" in Results of Operations in Item 7. MD&A) can occur for numerous reasons, including the volume of work required and the impact of market forces on the cost of labor and materials. Differences in costs can also arise from changes in laws and regulations at both the state and federal level. PG&E Corporation and the Utility are committed to taking steps to improve their credit ratings and metrics over time, including by reducing their debt. PG&E Corporation and the Utility have set goals to reduce their debt over time, including reducing PG&E Corporation's debt by at least $2 billion by the end of 2026. PG&E Corporation and the Utility expect that reducing the consolidated debt will help them achieve investment grade credit ratings for their unsecured securities, for the benefit of both customers and investors. For more information, see Note 5 of the Notes to the Consolidated Financial Statements in Item 8. Pursuant to SB 901, the Utility filed an application with the CPUC seeking authorization for a post-emergence transaction to recover $7.5 billion of 2017 wildfire claims costs, which was approved by the CPUC on February 28, 2022. PG&E Wildfire Recovery Funding LLC, a bankruptcy remote, limited liability company wholly owned by the Utility, issued $3.6 billion aggregate principal amount of Series 2022-A Recovery Bonds on May 10, 2022 and $3.9 billion aggregate principal amount of Series 2022-B Recovery Bonds on July 20, 2022. The net proceeds from both transactions were used to reimburse the Utility for previously incurred recovery costs, including the retirement of $5.0 billion of Utility debt and the repayment of a portion of the loans outstanding under the Utility's revolving credit facility pursuant to the Utility Revolving Credit Agreement. The Utility intends to use a portion of the remaining proceeds to fund the redemption of $1.0 billion of Utility debt. For more information, see "Application for Post-Emergence Securitization Transaction" in Item 7. MD&A. On December 20, 2017, the Boards of Directors of PG&E Corporation and the Utility suspended quarterly cash dividends on both PG&E Corporation's and the Utility's common stock, as well as the Utility's preferred stock. PG&E Corporation's and the Utility's ability to issue dividends is subject to restrictions. On February 8, 2022, the Board of Directors of the Utility authorized the payment of all cumulative and unpaid dividends on the Utility's preferred stock. On June 15, 2022, the Board of Directors of the Utility also reinstated the dividend on the Utility's common stock. For more information, see "Dividends" in Item 7. MD&A. Total capital expenditures (including accruals) recorded in 2022 were $9.6 billion. The Utility's total capital expenditures (including accruals) are forecasted to be between $7.9 billion and $11.2 billion for 2023, between $7.9 billion and $12.2 billion for 2024, between $8.0 billion and $12.7 billion for 2025, between $8.1 billion and $13.3 billion for 2026, and between $8.1 billion and $13.8 billion for 2027. The completion of projects, the timing of expenditures, and the associated cost recovery may be affected by permitting requirements and delays, construction schedules, availability of labor, equipment and materials, financing, legal and regulatory approvals and developments, community requests or protests, weather, and other unforeseen conditions. 14 The Utility expects to make additional capital expenditures, the recovery of which will be subject to future regulatory approval, including the 2023 GRC. These expenditures include capital expenditures exceeding amounts authorized in the 2020 GRC and 2019 GT&S, and expenditures to be included in a later stage of the 2023 GRC or separate applications. These expenditures are expected to primarily be for wildfire mitigation, transportation electrification, and the Lakeside Building. Additionally, $3.21 billion of fire risk mitigation capital expenditures will be excluded from the Utility's equity rate base pursuant to AB 1054. PG&E Corporation and the Utility are committed to keeping gas and electric services affordable for all customers. The Utility's capital investment plan, increasing procurement of renewable power and energy storage, increasing environmental regulations, and the cumulative impact of other public policy requirements collectively place continuing upward pressure on customer rates. Certain CPUC proceedings could impact different types of customers differently. Similarly, although the Utility generally recovers its electricity and natural gas procurement costs through rates as "pass-through" costs, commodity prices rose substantially in 2022, relative to 2021. The Utility has set a goal to increase customer capital investments while also limiting customer impacts, including by reducing non-fuel Operating and maintenance costs by two percent per year and by seeking efficient financing. The Utility plans to meet its two percent non-fuel Operating and maintenance cost reduction goal through increased efficiency, including waste elimination through the Lean operating system. The Utility has a number of programs in place to assist low-income customers, such as the CARE program. Under the CARE program, income-qualified customers can receive a monthly discount of 20% or more on their gas and electric bill. PG&E Corporation's and the Utility's Corporate Sustainability Report, which is available to the public, describes the companies' progress toward world-class performance measured with the triple bottom line framework.

FY 2023 10-K
Added
Filed Feb 22, 2024

Under cost-of-service ratemaking, a utility's earnings depend on the outcomes of its ratemaking proceedings and its ability to manage costs. See "Ratemaking Mechanisms" below and "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC and FERC proceedings. 13 Generally, differences between forecast costs and actual costs can occur for numerous reasons, including the volume of work required and the impact of market forces on the cost of labor and materials. Differences in costs can also arise from changes in laws and regulations at both the state and federal level. PG&E Corporation and the Utility are committed to taking steps to improve their credit ratings and metrics over time, including by reducing PG&E Corporation's debt by at least $2 billion by the end of 2026. PG&E Corporation and the Utility expect that reducing the consolidated debt will help them achieve investment grade credit ratings for their unsecured securities, for the benefit of both customers and investors. For more information, see "Liquidity and Financial Resources" in Item 7. MD&A. In 2022, an affiliate of the Utility issued an aggregate of $7.5 billion of SB 901 securitization bonds. The net proceeds were used to reimburse the Utility for previously incurred recovery costs, including the retirement of $6.0 billion of Utility debt, as of December 31, 2023. In November 2023, the Board of Directors of PG&E Corporation reinstated the dividend on PG&E Corporation common stock, declaring a dividend of $21 million, or approximately 1 cent per share, which was paid by January 16, 2024. The Boards of Directors of PG&E Corporation and the Utility had suspended quarterly cash dividends in 2017 on both PG&E Corporation's and the Utility's common stock, as well as the Utility's preferred stock. For more information, see "Liquidity and Financial Resources - Dividends" in Item 7. MD&A. Total capital expenditures recorded in 2023 were $9.8 billion. The Utility's total capital expenditures (including accruals) are forecasted to be $10.4 billion for 2024, $12.7 billion for 2025, $11.5 billion for 2026, $13.6 billion for 2027, and $14.0 billion for 2028. The Utility has identified additional opportunities for investment in the coming years in addition to its forecast, including investments in transportation electrification capacity, FERC-jurisdictional assets, electric distribution capacity, hydroelectric facilities, energy storage, information technology, and automation. The Utility also plans to submit a cost recovery application for its 10-year distribution undergrounding program pursuant to SB 884. Some of these investments depend on the Utility's ability to generate or obtain the cash to support such investments over this period of time. The completion of projects, the timing of expenditures, and the associated cost recovery may be affected by permitting requirements and delays, construction schedules, availability of labor, equipment and materials, financing, legal and regulatory approvals and developments, community requests or protests, weather, and other unforeseen conditions. The Utility expects to make additional capital expenditures, the recovery of which will be subject to future regulatory approval. These expenditures include capital expenditures exceeding amounts authorized in the 2023 GRC final decision issued on November 17, 2023, and expenditures to be included in a later filing or separate applications. These expenditures are expected to be primarily for wildfire mitigation and electrification. Additionally, $3.21 billion of fire risk mitigation capital expenditures has been excluded from the Utility's equity base rate pursuant to AB 1054. PG&E Corporation and the Utility are committed to finding ways to lower the cost of providing gas and electric services for customers. The Utility's capital investment plan, increasing procurement of renewable power and energy storage, increasing environmental regulations, and the cumulative impact of other public policy requirements collectively place continuing upward pressure on customer rates. Certain CPUC proceedings could impact different types of customers differently. The Utility has set a goal to increase customer capital investments while also limiting customer bill impacts, including by achieving operating cost savings and by seeking efficient financing. The Utility plans to meet its cost reduction goal through increased efficiencies, including waste elimination through the Lean operating system. The Utility has a number of programs in place to assist low-income customers, such as the CARE program. Under the CARE program, income-qualified customers can receive a monthly discount of 20% or more on their gas and electric bill. PG&E Corporation's and the Utility's Corporate Sustainability Report, which is available to the public, describes the companies' progress toward world-class performance measured with the triple bottom line framework.

de-emphasised Performance: Underpinning the Triple Bottom Line The Utility introduced PG&E's Safety Excellence Management System in 2023 and expanded its Lean operating system to include five basic plays, including waste elimination. Regarding wildfire risk mitigation, PSPS reporting shifted from zero events in the prior period to two events impacting a total of 5,099 customers in the current period.

FY 2022 10-K
Removed
Filed Feb 23, 2023

In 2021, the Utility spent $4.01 billion with certified diverse suppliers, representing 38.7% of its total spend. Performance: Underpinning the Triple Bottom Line PG&E Corporation and the Utility use the Lean operating system, which includes four basic "plays:" visual management; operating reviews; problem solving; and standard work. Visual management allows teams to see how they are performing against their most important metrics using real-time data. PG&E Corporation and the Utility hold daily, weekly, and monthly operating reviews designed to align the performance of workers closest to the work with the goals and objectives of senior leadership. These brief meetings help the Utility identify gaps and quickly develop plans to support the teams performing the work and give the Utility more visibility, control and predictability in its operations. Problem solving involves a structured approach to identifying, containing, analyzing, and solving problems in order to capitalize on opportunities. Standard work reduces costs and increases productivity by ensuring a consistent company-wide method for completing a task. For instance, the Lean operating system helped the Utility identify patterns in the conditions of ignitions and led to the implementation of EPSS and drove significant benefit and understanding in how PG&E Corporation and the Utility manage customer satisfaction. PG&E Corporation's and the Utility's performance is also driven by an increased focus on alignment on shared outcomes among its leadership and within the organization. In 2023, PG&E Corporation's and the Utility's Lean deployment will focus on a fifth play, waste elimination, which enables the companies to identify and eliminate inefficiencies in both process and workflow in a sustainable manner, as well as the continued adoption of a performance playbook and improvements to financial visibility and controls. PG&E Corporation and the Utility have implemented a regional service model to bring the Utility closer to the hometowns it serves. Through the regional service model, the Utility has restructured its service area into five regions, with leaders in each region to deliver improved public and employee safety, customer service, and operational reliability outcomes. PG&E Corporation and the Utility are committed to designing an electric system that is resilient to climate change, decarbonized, and optimized to local and system needs. California has experienced unprecedented weather conditions in recent years and the Utility's service area remains susceptible to additional wildfire activity. In response, the Utility has implemented operational changes and investments that reduce wildfire risk, including: •Enhanced Powerline Safety Settings: EPSS adjusts the sensitivity of circuit protection devices on selected power lines to de-energize them more rapidly in the event of a disturbance to help prevent potential ignitions. After EPSS was initiated, both the size and number of CPUC-reportable ignitions were reduced substantially on EPSS-enabled circuits, compared to the prior three-year average. 15 •Public Safety Power Shutoffs: The PSPS program proactively de-energizes power lines in response to forecasted weather conditions. Since its inception in late 2017, the PSPS program has become more targeted because the Utility has developed more granular risk models, including adding consideration of vegetation management and maintenance tag statuses for scoping PSPS events. The Utility has also installed sectionalizers for more targeted de-energizations of circuits and transmission lines. In 2022, the Utility did not have any PSPS events. •Vegetation management: The Utility inspects its overhead electric distribution and transmission facilities on an annual basis to identify and clear vegetation that might grow or fall into utility equipment. The Utility is also increasing oversight and engagement with the contractors supporting vegetation management work. •Asset inspections: Since 2018, the Utility has reoriented its asset inspections programs toward asset condition and consequence risk, particularly wildfire risk, and these programs have become more thorough, standardized, digitized, and verifiable. The Utility uses risk-informed inspection cycles. In 2022, the Utility continued to refine its risk modeling, including further incorporating data from asset inspections. As a result of the improved inspection program, the Utility's inspections in recent years have begun to more thoroughly identify equipment conditions. •System hardening: System hardening entails repairing, replacing, or eliminating existing power lines in HFTDs and installing stronger and more resilient equipment. As the Utility's asset inspections have identified more equipment conditions, the Utility has hardened its system by correcting significantly more equipment conditions than in prior years. Hardening methods include replacing bare overhead conductor with covered conductor and installing stronger poles, removing lines, and serving customers through remote grids, or converting lines from overhead to underground. In 2021, the Utility announced a program to underground 10,000 miles of electric distribution lines in high wildfire risk areas. In 2022, the Utility undergrounded 180 miles of lines, which exceeded its plan to underground 175 miles of lines. Undergrounding can substantially reduce ignition risk and improve reliability during storms or periods of high wildfire risk. The Utility also brought online two additional "remote grids" in 2022, which allow distribution lines in HFTDs to be removed and replaced with locally sited resources. Remote grids can reduce costs and fire risks, while maintaining service to participating customers. As a result of these measures, the Utility significantly reduced both the size and number of CPUC-reportable ignitions and number of acres burned in 2022, compared to prior years.

FY 2023 10-K
Added
Filed Feb 22, 2024

In 2022, the Utility spent $4.79 billion with certified diverse suppliers, representing 39.3% of its total spend. 14 Performance: Underpinning the Triple Bottom Line PG&E Corporation and the Utility use the Lean operating system, which includes five basic "plays": visual management; operating reviews; problem solving; standard work; and waste elimination. Visual management allows teams to see how they are performing against their most important metrics using real-time data. Teams throughout PG&E Corporation and the Utility hold daily, weekly, and monthly operating reviews designed to align the performance of workers closest to the work with the goals and objectives of senior leadership. These brief meetings help the Utility identify gaps and quickly develop plans to support the teams performing the work and give the Utility more visibility, control and predictability in its operations. Problem solving involves a structured approach to identifying, containing, analyzing, and solving problems in order to capitalize on opportunities. Standard work reduces costs and increases productivity by establishing a consistent company-wide method for completing a task. For instance, the Lean operating system helped the Utility identify patterns in the conditions of ignitions and led to the implementation of EPSS, which drove a significant reduction in facility ignitions. PG&E Corporation's and the Utility's performance is also driven by an increased focus on alignment of shared outcomes among its leadership and within the organization. Waste elimination, the fifth Lean play, was deployed in 2023 and enables the companies to identify and eliminate inefficiencies in both process and workflow in a sustainable manner and drive the continued adoption of consistent processes and improvements to financial visibility and controls. In 2023, the Utility implemented PG&E's Safety Excellence Management System, which is a more systematic approach to assess risk and evaluate or implement controls for safe operation based on industry standards. PG&E Corporation and the Utility have implemented a regional service model to bring the Utility closer to the hometowns it serves. Through the regional service model, the Utility has restructured its service area into five regions, with leaders assigned for each region to deliver improved public and employee safety, customer service, and operational reliability outcomes. PG&E Corporation and the Utility are committed to designing an electric system that is resilient to climate change, decarbonized, and optimized to local and system needs. California has experienced unprecedented weather conditions in recent years and the Utility's service area remains susceptible to additional wildfire activity. In response, the Utility has implemented operational changes and investments that reduce wildfire risk, including: •Enhanced Powerline Safety Settings: EPSS adjusts the sensitivity of circuit protection devices on selected power lines to de-energize them in less than one-tenth of a second in the event of a disturbance to help prevent potential ignitions. After EPSS was initiated, both the size and number of CPUC-reportable ignitions were reduced substantially on EPSS-enabled circuits, compared to the prior three-year average. •Public Safety Power Shutoffs: The PSPS program proactively de-energizes power lines in response to forecasted weather conditions. Since its inception in late 2017, the PSPS program has become more targeted through the use of more granular risk models, including incorporating more detailed data inputs. The Utility has also installed sectionalizers for more targeted de-energizations of circuits and transmission lines. These more targeted scoping criteria are engineered to reduce the number of customers impacted by any particular PSPS event. In 2023, the Utility had two PSPS events impacting a total of 5,099 customers. •Vegetation management: The Utility inspects its overhead electric distribution and transmission facilities on an annual basis to identify and clear vegetation that might grow or fall into utility equipment. The Utility is also increasing oversight and engagement with the contractors supporting vegetation management work. •Asset inspections: Since 2018, the Utility has reoriented its asset inspections programs toward asset condition and consequence risk, particularly wildfire risk, and these programs have become more thorough, standardized, digitized, and verifiable. The Utility uses risk-informed inspection cycles. In 2023, the Utility continued to refine its risk modeling, including further incorporating data from asset inspections. As a result of the improved inspection program, the Utility's inspections in recent years have begun to more thoroughly identify equipment conditions. 15

reworded Nuclear Regulatory Commission

FY 2022 10-K
Removed
Filed Feb 23, 2023

Nuclear Regulatory Commission The NRC oversees the licensing, construction, operation and decommissioning of nuclear facilities, including the Utility's two nuclear generating units at Diablo Canyon and the Utility's retired nuclear generating unit at Humboldt Bay. See "Electricity Resources" below. NRC regulations require extensive monitoring and review of the safety, radiological, seismic, environmental, and security aspects of these facilities. In the event of non-compliance, the NRC has the authority to impose fines or to force a shutdown of a nuclear plant, or both. NRC safety and security requirements have, in the past, necessitated substantial capital expenditures at Diablo Canyon, and substantial capital expenditures could be required in the future. For more information about Diablo Canyon, see Item 1A. Risk Factors and Note 16 of the Notes to the Consolidated Financial Statements in Item 8.

FY 2023 10-K
Added
Filed Feb 22, 2024

Nuclear Regulatory Commission The NRC oversees the licensing, construction, operation, and decommissioning of nuclear facilities, including the Utility's two nuclear generating units at Diablo Canyon and the Utility's independent spent fuel storage installation at Humboldt Bay. See "Electricity Resources" below. NRC regulations require extensive monitoring and review of the safety, radiological, seismic, environmental, and security aspects of these facilities. In the event of non-compliance, the NRC has the authority to impose fines or to force a shutdown of a nuclear plant, or both. NRC safety and security requirements have, in the past, necessitated that the Utility incur substantial costs at Diablo Canyon, and substantial costs could be required in the future. For more information about Diablo Canyon, see Item 1A. Risk Factors and Note 15 of the Notes to the Consolidated Financial Statements in Item 8.

reworded Material Effects of Compliance with Governmental Regulations

FY 2022 10-K
Removed
Filed Feb 23, 2023

Material Effects of Compliance with Governmental Regulations As indicated above, the Utility's business is subject to the regulatory jurisdiction of various agencies at the federal, state, and local levels. Compliance with such extensive government regulations requires substantial expenditures and has had in the past and may continue to have in the future a material effect on PG&E Corporation's and the Utility's financial condition, results of operations, liquidity, cash flows and competitive position. For more information about costs incurred to comply with government regulations and related material effects on PG&E Corporation and the Utility, see Item 1A. Risk Factors, "Regulatory Matters" in Item 7. MD&A, and Notes 15 and 16 of the Notes to the Consolidated Financial Statements in Item 8.

FY 2023 10-K
Added
Filed Feb 22, 2024

Material Effects of Compliance with Governmental Regulations As indicated above, the Utility's business is subject to the regulatory jurisdiction of various agencies at the federal, state, and local levels. Compliance with such extensive government regulations requires substantial expenditures and has had in the past and may continue to have in the future a material effect on PG&E Corporation's and the Utility's financial condition, results of operations, liquidity, cash flows and competitive position. For more information about costs incurred to comply with government regulations and related material effects on PG&E Corporation and the Utility, see Item 1A. Risk Factors, "Liquidity and Financial Resources" and "Regulatory Matters" in Item 7. MD&A, and Notes 14 and 15 of the Notes to the Consolidated Financial Statements in Item 8.

reworded Adapting to the Physical Impacts of Climate Change

FY 2022 10-K
Removed
Filed Feb 23, 2023

Adapting to the Physical Impacts of Climate Change Effectively managing physical climate risk will become increasingly critical as the physical impacts of climate change become increasingly frequent and severe over the coming years in California. The Utility's climate resilience efforts continue to focus on characterizing and mitigating the physical impacts of climate change to the Utility's infrastructure, assets, and operations. The Utility is making substantial investments to build a more resilient system that can better withstand extreme weather and related emergencies. For more information on such investments, see "Performance: Underpinning the Triple Bottom Line" above. The Utility's preparations for the physical risks of climate change include an updated, more detailed, system‑wide CVA of the Utility's assets, operations, and services, which will be completed in 2024 and filed with the CPUC. The updated CVA will improve the Utility's understanding of its exposure to climate hazards in the near- and long-term and the sensitivity of assets and operations to these hazards. It will also inform the Utility's understanding of the ease or difficulty of various options for adapting to changing conditions. In the past few years, the Utility's electric distribution system has experienced multiple major outage-causing events associated with extreme heat events and peak loads. Peak loads are expected to increase with increasing temperatures due to direct impacts of ambient temperatures on equipment and direct impacts on electricity demand driven by rising air conditioning installation and usage. The Utility's assets on the coast and in or near watersheds face potential increased exposures to coastal, riverine (fluvial), and precipitation related (pluvial) flooding because of climate‑driven changes in precipitation and sea level rise. The risk of damage to or interruptions of operations at facilities such as substations is predicted to increase over time due to sea level rise. Electric and gas equipment and safe access for operations must be prepared for these changing conditions. Changing precipitation dynamics may impact the Utility's hydroelectric generation. Diminishing future water availability and altered runoff timing during extreme drought poses risks to hydropower generation, operations, and revenue. Also, extreme rain events suggest enhanced risk of hydropower asset damage or failure associated with flooding, which in the worst cases (e.g., uncontrolled water release) may have catastrophic impacts. Climate change will also continue to intensify the potential for wildfires throughout California. Models incorporating future temperature and precipitation projections suggest that landscape susceptibility to wildfire within the Utility's service area will continue to increase over time, with an expansion of areas that may become HFTD and an intensification of risk within HFTDs. Climate change may also result in increased potential of lines to cause ignitions or to require PSPS events, as well as the potential for the Utility's equipment to sustain damage from wildfires of any origin. The Utility's updated CVA will be used to inform changes to design and construction standards for equipment and facilities to increase infrastructure resilience to current and future extreme weather conditions. Results from the updated CVA will be incorporated into the Utility's key risk and planning functions, as well as asset management strategy, to identify priority adaptive actions. 21 The Utility is also engaging with CPUC-designated disadvantaged and vulnerable communities throughout the CVA process to ensure that customer perspectives regarding energy system resilience are part of updating the CVA. The Utility is conducting regional community engagement campaigns throughout its service area to understand how some of the most vulnerable communities the Utility serves think about climate hazards and adaptation. This information will help the Utility plan adaptive climate action aligned with customer and community perspectives. In addition to updating the CVA, the Utility regularly reviews relevant scientific literature regarding climate change to incorporate appropriate information into its operations. For example, based on a recent report about potential major atmospheric river events, the Utility updated and modified its flooding emergency response plan. The Utility's commitment to increasing resilience to climate change includes aligning its resources and business strategy with California's clean energy goals, the Utility's climate strategy, and advocating for policies and programs that enable safe and reliable energy for the Utility's customers in light of climate change. For example, the Utility believes its strategies to reduce GHG emissions through energy efficiency and demand response programs, infrastructure improvements, and the use of renewable energy and energy storage will help it adapt to the expected increases in demand for electricity.

FY 2023 10-K
Added
Filed Feb 22, 2024

Adapting to the Physical Impacts of Climate Change Effectively managing physical climate risk will become increasingly critical as the physical impacts of climate change become increasingly frequent and severe over the coming years in California. The Utility's climate resilience efforts continue to focus on characterizing and mitigating the physical impacts of climate change to the Utility's infrastructure, assets, and operations. The Utility is making substantial investments to build a more resilient system that can better withstand extreme weather and related emergencies. For more information on such investments, see "Performance: Underpinning the Triple Bottom Line" above. The Utility's preparations for the physical risks of climate change include an updated, more detailed, system‑wide CVA of the Utility's assets, operations, and services, which will be completed and filed with the CPUC in mid-2024. The updated CVA will improve the Utility's understanding of its exposure to climate hazards in the near- and long-term and the sensitivity of assets and operations to these hazards. It will also inform the Utility's understanding of the ease or difficulty of various options for adapting to changing conditions. In the past few years, the Utility's electric distribution system has experienced multiple major outage-causing events associated with extreme heat events and peak loads. Peak loads are expected to increase with increasing temperatures due to direct impacts of ambient temperatures on equipment, increased electricity demand driven by rising air conditioning installation and usage, and continued electrification of transportation and buildings. The Utility's assets on the coast and in or near watersheds face potential increased exposures to coastal, riverine (fluvial), and precipitation related (pluvial) flooding because of climate‑driven changes in precipitation and sea level rise. The risk of damage to or interruptions of operations at facilities such as substations is predicted to increase over time due to sea level rise. Electric and gas equipment and safe access for operations must be prepared for these changing conditions. Changing precipitation dynamics may impact the Utility's hydroelectric generation. Diminishing future water availability and altered runoff timing during extreme drought poses risks to hydropower generation, operations, and revenue. Also, extreme rain events suggest enhanced risk of hydropower asset damage or failure associated with flooding, which in the worst cases (e.g., uncontrolled water release) may have catastrophic impacts. Climate change will also continue to intensify the potential for wildfires throughout California. Models incorporating future temperature and precipitation projections suggest that landscape susceptibility to wildfire within the Utility's service area will continue to increase over time, with an expansion of areas that may become HFTD and an intensification of risk within HFTDs. Climate change may also result in increased potential of lines to cause ignitions or to require PSPS events, as well as the potential for the Utility's equipment to sustain damage from wildfires of any origin. 21 The Utility's updated CVA will be used to inform changes to design and construction standards for equipment and facilities to increase infrastructure resilience to current and future extreme weather conditions. Results from the updated CVA will be incorporated into the Utility's key risk and planning functions, as well as asset management strategy, to identify priority adaptive actions. The Utility has also engaged with CPUC-designated disadvantaged and vulnerable communities throughout the CVA process to better understand customer perspectives regarding energy system resilience. The Utility has conducted regional community engagement campaigns throughout its service area to understand how some of the most vulnerable communities the Utility serves think about climate hazards and adaptation. This information will help the Utility plan adaptive climate action aligned with customer and community perspectives. In addition to updating the CVA, the Utility regularly reviews relevant scientific literature regarding climate change to incorporate appropriate information into its operations. For example, based on a report about potential major atmospheric river events, the Utility updated and modified its flooding emergency response plan. The Utility's commitment to increasing resilience to climate change includes aligning its resources and business strategy with California's clean energy goals, the Utility's climate strategy, and advocating for policies and programs that enable safe and reliable energy for the Utility's customers in light of climate change. For example, the Utility believes its strategies to reduce GHG emissions through energy efficiency and demand response programs, infrastructure improvements, and the use of renewable energy and energy storage will help it adapt to the expected increases in demand for electricity.

reworded SO2 emissions rate (pounds/MWh)

FY 2022 10-K
Removed
Filed Feb 23, 2023

20212020 Total NOx emissions (tons)139 141 NOx emissions rate (pounds/MWh)0.010.01 Total SO2 emissions (tons) 14 15 SO2 emissions rate (pounds/MWh)

FY 2023 10-K
Added
Filed Feb 22, 2024

20222021 Total NOx emissions (tons)121 139 NOx emissions rate (pounds/MWh)0.01 0.01 Total SO2 emissions (tons) 11 14 SO2 emissions rate (pounds/MWh)

reworded Electricity Transmission Owner Rate Cases

FY 2022 10-K
Removed
Filed Feb 23, 2023

Electricity Transmission Owner Rate Cases The FERC determines the amount of authorized revenue requirements, including the rate of return on electric transmission assets, that the Utility may collect in rates in the TO rate case. In its TO rate cases, the Utility uses a formula rate methodology, which includes an authorized revenue requirement and rate base for a given year but also provides for an annual update of the previous year's revenue requirement and rates in accordance with the terms of the FERC-approved formula. Under the formula rate mechanism, transmission revenue requirements are updated to the actual cost of service annually as part of the true-up process. Differences between amounts collected and determined under the formula rate are either collected from or refunded to customers. The FERC-approved formula rate will be effective through December 31, 2023. These FERC-approved rates are included by the CPUC in the Utility's retail electric rates and by the CAISO in its transmission access charges to wholesale customers. For more information, see "Regulatory Matters - Transmission Owner Rate Cases" in Item 7. MD&A. The Utility also recovers a portion of its revenue requirements for its wholesale electric transmission costs through charges collected under specific contracts with wholesale transmission customers that the Utility entered into before the CAISO began its operations. These wholesale customers are charged individualized rates based on the terms of their contracts.

FY 2023 10-K
Added
Filed Feb 22, 2024

Electricity Transmission Owner Rate Cases The FERC determines the amount of authorized revenue requirements, including the rate of return on electric transmission assets, that the Utility may collect through rates in the TO rate case. In its TO rate cases, the Utility uses a formula rate methodology, which includes an authorized revenue requirement and rate base for a given year but also provides for an annual update of the previous year's revenue requirement and rates in accordance with the terms of the FERC-approved formula. Under the formula rate mechanism, transmission revenue requirements are updated to the actual cost of service annually as part of the true-up process. Differences between amounts collected and determined under the formula rate are either collected from or refunded to customers. These FERC-approved rates are included by the CPUC in the Utility's retail electric rates and by the CAISO in its transmission access charges to wholesale customers. For more information, see "Regulatory Matters - Transmission Owner Rate Cases" in Item 7. MD&A. The Utility also recovers a portion of its revenue requirements for its wholesale electric transmission costs through charges collected under specific contracts with wholesale transmission customers that the Utility entered into before the CAISO began its operations. These wholesale customers are charged individualized rates based on the terms of their contracts. 24

reworded Program-Specific Memorandum Account and Balancing Account Costs

FY 2022 10-K
Removed
Filed Feb 23, 2023

Program-Specific Memorandum Account and Balancing Account Costs Periodically, costs arise outside of the CPUC GRC proceedings or that have been deliberately excluded therefrom. These costs may result from catastrophic events, changes in regulation, new programs, or extraordinary changes in operating practices. The Utility may seek authority to track incremental costs in a memorandum account, and the CPUC may authorize recovery of costs tracked in memorandum accounts if the costs are deemed reasonable. For instance, these accounts allow the Utility to track the costs associated with work related to disaster and wildfire response, and other wildfire prevention-related costs. Recovery of the costs tracked in these memorandum accounts in rates requires CPUC authorization in separate proceedings for which the Utility may be unable to predict the outcome. Alternatively, the Utility may seek authority to track incremental costs related to these non-GRC programs in balancing accounts. The CPUC may authorize recovery of costs tracked in the balancing accounts on either a "one-way" basis, which typically only allows actual costs to be recovered up to a pre-established cap, or a "two-way" basis, which typically allows actual costs to be recovered, and in some cases subject to further CPUC review. For more information, see "Regulatory Matters - Cost Recovery Proceedings" in Item 7. MD&A and Note 4 of the Notes to the Consolidated Financial Statements in Item 8. 24

FY 2023 10-K
Added
Filed Feb 22, 2024

Program-Specific Memorandum Account and Balancing Account Costs Periodically, costs arise outside of the CPUC's GRC proceedings or that have been deliberately excluded therefrom. These costs may result from catastrophic events, changes in regulation, new programs, or extraordinary changes in operating practices. The Utility may seek authority to track incremental costs in a memorandum account, and the CPUC may authorize recovery of costs tracked in memorandum accounts if the costs are deemed reasonable. For instance, these accounts allow the Utility to track the costs associated with work related to disaster and wildfire response, and other wildfire prevention-related costs. Recovery of the costs tracked in these memorandum accounts through rates requires CPUC authorization in separate proceedings, the outcome of which the Utility may be unable to predict. Alternatively, the Utility may seek authority to track incremental costs related to these non-GRC programs in balancing accounts. The CPUC may authorize recovery of costs tracked in the balancing accounts on either a "one-way" basis, which typically only allows actual costs to be recovered up to a pre-established cap, or a "two-way" basis, which typically allows actual costs to be recovered, and in some cases subject to further CPUC review. For more information, see "Regulatory Matters - Cost Recovery Proceedings" in Item 7. MD&A and Note 3 of the Notes to the Consolidated Financial Statements in Item 8.

reworded The Utility recovers the cost of gas used in generation facilities as a cost of electricity that is recovered annually through retail electric rates.

FY 2022 10-K
Removed
Filed Feb 23, 2023

Natural Gas Procurement, Storage, and Transportation Costs The Utility recovers the cost of gas used in generation facilities as a cost of electricity that is recovered annually through retail electric rates. 25 The Utility sets the natural gas procurement rate for small commercial and residential customers (referred to as "core" customers) monthly, based on the forecasted costs of natural gas, core pipeline capacity and storage costs. The Utility recovers the cost of gas purchased on behalf of core customers as well as the cost of derivative instruments for its core gas portfolio, through its retail gas rates, subject to limits as set forth in its CPIM described below. The Utility reflects the difference between actual natural gas purchase costs and forecasted natural gas purchase costs in several natural gas balancing accounts, with under-collections and over-collections taken into account in subsequent monthly rate changes. The CPIM protects the Utility against after-the-fact reasonableness reviews of its gas procurement costs for its core gas portfolio. Under the CPIM, the Utility's natural gas purchase costs for a fixed 12-month period are compared to an aggregate market-based benchmark based on a weighted average of published monthly and daily natural gas price indices at the points where the Utility typically purchases natural gas. Costs that fall within a tolerance band, which is 99% to 102% of the commodity benchmark, are considered reasonable and are fully recovered through rates. One-half of the costs above 102% of the benchmark are recoverable through rates, and the Utility's customers receive in their rates 80% of any savings resulting from the Utility's cost of natural gas that is less than 99% of the benchmark. The Utility retains the remaining amount of these savings as incentive revenues, subject to a cap equal to 1.5% of total natural gas commodity costs. While this mechanism remains in place, changes in the price of natural gas, consistent with the market-based benchmark, are not expected to materially impact net income. The Utility incurs transportation costs under various agreements with interstate and Canadian third-party transportation service providers. These providers transport natural gas from the points at which the Utility takes delivery of natural gas (typically in Canada, the U.S. Rocky Mountains, and the southwestern United States) to the points at which the Utility's natural gas transportation system begins. These agreements are governed by the FERC-approved tariffs that detail rates, rules, and terms of service for the provision of natural gas transportation services to the Utility on interstate and Canadian pipelines. The FERC approves the United States tariffs that shippers, including the Utility, pay for pipeline service, and the applicable Canadian tariffs are approved by the National Energy Board, a Canadian regulatory agency. The transportation costs the Utility incurs under these agreements are recovered through CPUC-approved rates as core natural gas procurement costs or as a cost of electricity.

FY 2023 10-K
Added
Filed Feb 22, 2024

Natural Gas Procurement, Storage, and Transportation Costs The Utility recovers the cost of gas used in generation facilities as a cost of electricity that is recovered annually through retail electric rates. The Utility sets the natural gas procurement rate for small commercial and residential customers (referred to as "core" customers) monthly, based on the forecasted costs of natural gas, core pipeline capacity and storage costs. The Utility recovers the cost of gas purchased on behalf of core customers as well as the cost of derivative instruments for its core gas portfolio, through its retail gas rates, subject to limits as set forth in its CPIM described below. The Utility reflects the difference between actual natural gas purchase costs and forecasted natural gas purchase costs in several natural gas balancing accounts, with adjustments for under-collections and over-collections made in subsequent monthly rate changes. The CPIM protects the Utility against after-the-fact reasonableness reviews of its gas procurement costs for its core gas portfolio. Under the CPIM, the Utility's natural gas purchase costs for a fixed 12-month period are compared to an aggregate market-based benchmark based on a weighted average of published monthly and daily natural gas price indices at the points where the Utility typically purchases natural gas. Costs that fall within a tolerance band, which is 99% to 102% of the commodity benchmark, are considered reasonable and are fully recovered through rates. One-half of the costs above 102% of the benchmark are recoverable through rates, and the Utility's customers receive in their rates 80% of any savings resulting from the Utility's cost of natural gas that is less than 99% of the benchmark. The Utility retains the remaining amount of these savings as incentive revenues, subject to a cap equal to 1.5% of total natural gas commodity costs. While this mechanism remains in place, changes in the price of natural gas, consistent with the market-based benchmark, are not expected to materially impact net income. The Utility incurs transportation costs under various agreements with interstate and Canadian third-party transportation service providers. These providers transport natural gas from the points at which the Utility takes delivery of natural gas (typically in Canada, the U.S. Rocky Mountains, and the southwestern United States) to the points at which the Utility's natural gas transportation system begins. These agreements are governed by FERC-approved tariffs that detail rates, rules, and terms of service for the provision of natural gas transportation services to the Utility on interstate and Canadian pipelines. The FERC approves the United States tariffs governing payments by shippers (including the Utility) for pipeline service, and the Canada Energy Regulator, the Canadian regulatory agency, approves the applicable Canadian tariffs. The transportation costs the Utility incurs under these agreements are recovered through CPUC-approved rates as core natural gas procurement costs or as a cost of electricity. 26

reworded Planet

FY 2022 10-K
Removed
Filed Feb 23, 2023

For more information, see "Human Capital" below. Planet The planet element of the triple bottom line represents PG&E Corporation's and the Utility's commitment to protect and serve the environment. This commitment extends beyond compliance with various state and federal environmental, health, and safety laws and regulations. PG&E Corporation and the Utility believe that integrating and managing climate change and other environmental considerations in the companies' business strategies creates long-term value for PG&E Corporation and the Utility, and for their customers, communities, coworkers, and other stakeholders. Mitigating and adapting to the impacts of climate change presents opportunities for growth for the Utility's business and economic opportunity for the communities it serves. 12 The Utility strives to be prepared to continue to deliver safe, clean, affordable, and reliable energy in the face of increasingly severe and extreme climate-driven natural hazards. To build resilience to these hazards, the Utility is working to systematically integrate the consideration of forward-looking climate data and tools in its decision-making. PG&E Corporation and the Utility also work with policymakers and regulators to advance effective climate adaptation policy in California, and work directly with local governments and communities on adaptation solutions. PG&E Corporation and the Utility have committed to helping heal the planet. PG&E Corporation's and the Utility's Climate Strategy Report, which is available to the public, describes the companies' climate goals and plans to meet those goals. To meet their longer-term climate goals, PG&E Corporation and the Utility intend to scale their efforts to decarbonize the electric system to accommodate a shift to vehicle electrification, integrate a proliferation of distributed energy resources, and achieve increased penetration of renewable energy combined with investments in the grid and energy storage. PG&E Corporation and the Utility also plan to transition the gas system to cleaner fuels, increasingly target natural gas delivery for hard-to-electrify customer sectors, and support efforts to accelerate building electrification. The objective is to do so in an orderly manner to achieve a positive customer and community experience, while reducing natural gas system investments in targeted electrified communities. The impacts of climate change on the Utility's infrastructure are already a reality. Record-breaking extreme heat and heat waves are increasingly a regular occurrence throughout California. Peak electric loads are expected to increase with increasing temperatures due to direct impacts of ambient temperatures on equipment and direct impacts on electricity demand driven by rising air conditioning installation and usage, and increasingly driven in the future from widespread progress in adoption of beneficial electrification technologies. The Utility's assets on the coast and in or near watersheds face potential increased exposures to coastal, riverine, and precipitation-related flooding because of climate-driven changes in precipitation and sea-level rise. Climate change will also continue to intensify the potential for wildfires throughout California. The worsening conditions across California increase the likelihood and severity of wildfires, including those where the Utility's equipment may be alleged to be associated with the fire's ignition. Reducing risk will be even more important as climate change continues to exacerbate the risks facing the Utility. A key element of preparing the Utility for the physical risks of climate change is an updated and more detailed system-wide CVA of the Utility's assets, operations, and services, which the Utility expects to file with the CPUC in 2024. The CVA is expected to improve the Utility's understanding of its exposure to climate hazards and the sensitivity of assets and operations to these hazards. PG&E Corporation and the Utility continue to pursue policies and programs that enable safe, reliable, and affordable clean and resilient energy for their customers. As a result of actions already taken by PG&E Corporation and the Utility, the companies have:

FY 2023 10-K
Added
Filed Feb 22, 2024

For more information, see "Human Capital" below. Planet The planet element of the triple bottom line represents PG&E Corporation's and the Utility's commitment to protect and serve the environment. This commitment extends beyond compliance with various state and federal environmental, health, and safety laws and regulations. PG&E Corporation and the Utility believe that integrating and managing climate change and other environmental considerations in the companies' business strategies creates long-term value for PG&E Corporation and the Utility, and for their customers, communities, coworkers, and other stakeholders. Mitigating and adapting to the impacts of climate change presents opportunities for growth for the Utility's business and economic opportunity for the communities it serves. The Utility is committed to delivering safe, clean, affordable, and reliable energy in the face of increasingly severe and extreme climate-driven natural hazards. To build resilience to these hazards, the Utility is working to systematically integrate forward-looking climate data and tools into its decision-making. PG&E Corporation and the Utility also work with policymakers and regulators to advance effective climate change policy in California, and work directly with local governments and communities on adaptation solutions. PG&E Corporation and the Utility are also committed to helping heal the planet. PG&E Corporation's and the Utility's Climate Strategy Report, which is available to the public, describes the companies' climate goals and plans to meet those goals. To meet their longer-term climate goals, PG&E Corporation and the Utility intend to scale their efforts to decarbonize the energy system to accommodate a shift to vehicle electrification, integrate a proliferation of distributed energy resources, and achieve increased penetration of renewable energy combined with investments in the grid and energy storage. PG&E Corporation and the Utility are also making progress on transitioning the gas system to cleaner fuels and supporting efforts to accelerate building electrification. The objective is to do so in an orderly manner to achieve a positive customer and community experience, while reducing natural gas system investments in targeted electrified communities. The impacts of climate change on the Utility's infrastructure are already a reality. Record-breaking extreme heat and heat waves are increasingly a regular occurrence throughout California. Peak electric loads are expected to increase with increasing temperatures due to direct impacts of ambient temperatures on equipment and direct impacts on electricity demand driven by rising air conditioning installation and usage, and increasingly driven in the future from widespread progress in adoption of strategic electrification technologies. The Utility's assets on the coast and in or near watersheds face potential increased exposures to coastal, riverine, and precipitation-related flooding because of climate-driven changes in precipitation and sea-level rise. 12 Climate change will also continue to intensify the potential for wildfires throughout California. The worsening conditions across California increase the likelihood and severity of wildfires, including those where the Utility's equipment may be alleged to be associated with the fire's ignition. Reducing risk will be even more important as climate change continues to exacerbate the risks facing the Utility. A key element of preparing the Utility for the physical risks of climate change is an updated and more detailed system-wide CVA of the Utility's assets, operations, and services, which the Utility expects to file with the CPUC in mid-2024. The CVA is expected to improve the Utility's understanding of its exposure to climate hazards and the sensitivity of assets and operations to these hazards. PG&E Corporation and the Utility continue to pursue policies and programs that enable safe, reliable, and affordable clean and resilient energy for their customers. As a result of actions already taken by PG&E Corporation and the Utility, the companies have:

reworded Human Capital

FY 2022 10-K
Removed
Filed Feb 23, 2023

For costs related to AROs see "Asset Retirement Obligations" in Note 3 of the Notes to the Consolidated Financial Statements in Item 8. 26 Human Capital

FY 2023 10-K
Added
Filed Feb 22, 2024

For costs related to AROs, see "Asset Retirement Obligations" in Note 2 of the Notes to the Consolidated Financial Statements in Item 8. Human Capital

reworded Employees and Contractors

FY 2022 10-K
Removed
Filed Feb 23, 2023

Employees and Contractors As of December 31, 2022, PG&E Corporation had 10 employees and the Utility had approximately 26,000 regular employees. Of the Utility's regular employees, approximately 16,000 are covered by collective bargaining agreements with the local chapters of three labor unions: the International Brotherhood of Electrical Workers ("IBEW") Local 1245; the Engineers and Scientists of California ("ESC") IFPTE 20; and the Service Employees International Union Local 24/7 ("SEIU"). The collective bargaining agreements in effect for the IBEW Local 1245; ESC Local 20; and SEIU, United Service Workers West will expire on December 31, 2025. The agreements increase wages annually by 3.75% from 2022 through 2025 and maintain current contributions to specified benefits. The IBEW, ESC, and SEIU represent approximately 62% of the Utility's employee workforce and support several areas of the Utility's business, including gas and electric operations. The Utility enjoys stable and productive relationships with its unions and did not experience any work stoppages in 2022. PG&E Corporation's employees are primarily at the executive management level, which experienced significant employee turnover throughout the course of its Chapter 11 Cases in 2019 and 2020. The Utility generally has a stable workforce, which translated into low voluntary turnover during that period. The Utility's turnover rates for 2022 and 2021 were 7.1% and 5.8%, respectively. Approximately 42% of PG&E Corporation's and the Utility's employees have a tenure of more than 10 years, with an average tenure of 11 years. Approximately 19% of PG&E Corporation's and the Utility's employees are eligible to retire. (PG&E Corporation and the Utility define retirement age as 55 years and older.)

FY 2023 10-K
Added
Filed Feb 22, 2024

Employees and Contractors As of December 31, 2023, PG&E Corporation had 10 employees and the Utility had approximately 28,000 regular employees. Of the Utility's regular employees, approximately 17,000 are covered by collective bargaining agreements with the local chapters of three labor unions: the International Brotherhood of Electrical Workers ("IBEW") Local 1245; the Engineers and Scientists of California ("ESC") IFPTE 20; and the Service Employees International Union Local 24/7 ("SEIU"). The collective bargaining agreements in effect for the IBEW Local 1245, ESC Local 20, and SEIU United Service Workers West, are set to expire on December 31, 2025. The agreements increase wages annually by 3.75% from 2022 through 2025 and maintain current contributions to specified benefits. The IBEW, ESC, and SEIU represent approximately 63% of the Utility's employee workforce and support several areas of the Utility's business, including gas and electric operations. The Utility enjoys stable and productive relationships with its unions and did not experience any work stoppages in 2023. PG&E Corporation's employees are primarily at the executive management level. The Utility generally has a stable workforce. The Utility's turnover rates for 2023 and 2022 were 4.0% and 7.1%, respectively. Approximately 42% of PG&E Corporation's and the Utility's employees have a tenure of more than 10 years, with an average tenure of 11 years. Approximately 18% of PG&E Corporation's and the Utility's employees are eligible to retire. (PG&E Corporation and the Utility define retirement age as 55 years and older.)

reworded Human Capital Management

FY 2022 10-K
Removed
Filed Feb 23, 2023

The Utility's contractors and subcontractors include approximately 42,000 individuals from approximately 1,200 contractor companies. Human Capital Management PG&E Corporation's and the Utility's human capital resource objectives are to build and retain an engaged, well trained, diverse, and equitable workforce. PG&E Corporation's and the Utility's Boards of Directors are responsible for overseeing management's development and execution of PG&E Corporation's and the Utility's human capital strategy. To build employee engagement, the Utility has a variety of both executive-level and employee-led initiatives and programs. PG&E Corporation's and the Utility's executive teams meet regularly to discuss and evaluate the state of employee talent, determine which programs are driving engagement and performance, and clarify the specific skills, behaviors, and values that should be cultivated. Each year, the Utility honors employees whose work embodies safety, diversity, equity, inclusion, belonging, environmental leadership, and community service. The Utility conducts an annual employee engagement survey to measure and improve employee engagement progress. Every year, PG&E Corporation and the Utility offer or require technical, leadership, and employee training, which includes a range of technical training for employees on the knowledge and skills required to perform their jobs safely using approved tools and work procedures. In addition, employees are required to complete an annual compliance and ethics training and a Code of Conduct training, both of which are intended to promote a culture in which employees are encouraged to speak up with any concerns or ideas for continuous improvement. In addition, the Utility offers a variety of other trainings and education opportunities. Among other programs, the Utility provides career opportunities through its PowerPathway™ workforce development program. Launched in 2008, PowerPathway is a workforce development model to enlarge the talent pool of local, qualified, diverse candidates for skilled craft and utility industry jobs through training program partnerships with educational, community-based and government organizations. PowerPathway helps people throughout the Utility's service area, including women and military veterans, prepare and compete for high demand jobs in the utility and energy industry. Students receive approximately eight weeks of industry-informed curriculum to ensure the academic, job specific, employability skills and physical training necessary to effectively compete for entry-level employment. Programs may also include hands-on training and on-the-job training. PG&E Corporation and the Utility also provide integrated solutions and programs that cover employee health and wellness and that encompass physical, emotional, and financial health, including an on-site health clinic, an annual health screening, and health management tools and resources, in addition to more traditional programs. 27 PG&E Corporation's and the Utility's financial incentives offered to employees include a Short-Term Incentive Plan ("STIP"), an at-risk part of employee compensation designed to reward eligible employees for achieving specific performance goals. The 2022 STIP was focused on company objectives of safety, customer impact, and financial health.

FY 2023 10-K
Added
Filed Feb 22, 2024

The Utility's contractors and subcontractors include approximately 30,000 individuals from approximately 1,000 contractor companies. Human Capital Management PG&E Corporation's and the Utility's human capital resource objectives are to build and retain an engaged, well trained, diverse, and equitable workforce. PG&E Corporation's and the Utility's Boards of Directors are responsible for overseeing management's development and execution of PG&E Corporation's and the Utility's human capital strategy. To build employee engagement, the Utility has a variety of both executive-level and employee-led initiatives and programs. PG&E Corporation's and the Utility's executive teams meet regularly to discuss and evaluate the state of employee talent, determine which programs are driving engagement and performance, and clarify the specific skills, behaviors, and virtues that should be cultivated. Each year, the Utility honors employees whose work embodies safety, diversity, equity, inclusion, belonging, environmental leadership, innovation, and community service. The Utility conducts an annual employee survey to measure and improve employee engagement. 27 Every year, PG&E Corporation and the Utility offer or require technical, leadership, and employee training, which includes a range of technical training for employees on the knowledge and skills required to perform their jobs safely using approved tools and work procedures. In addition, employees are required to complete annual compliance and ethics training and a Code of Conduct training, both of which are intended to promote a culture in which employees are encouraged to speak up with any concerns or ideas for continuous improvement. In addition, the Utility offers a variety of other trainings and education opportunities. In 2023, the Utility significantly expanded its training for supervisors. Among other programs, the Utility provides career opportunities through its PowerPathway™ workforce development program. Launched in 2008, PowerPathway is a workforce development model to enlarge the talent pool of local, qualified, diverse candidates for skilled craft and utility industry jobs through training program partnerships with educational, community-based and government organizations. PowerPathway helps people throughout the Utility's service area, including women and military veterans, prepare and compete for high demand jobs in the utility and energy industry. Students receive approximately eight weeks of industry-informed curriculum to ensure the academic, job specific, employability skills and physical training necessary to effectively compete for entry-level employment. Programs may also include hands-on training and on-the-job training. PG&E Corporation and the Utility also provide integrated solutions and programs for employee health and wellness that encompass physical, mental, and financial health. These resources include several on-site or near-site health clinics, annual health screenings, health management tools, ergonomic support, and injury management programs, in addition to more traditional programs. PG&E Corporation's and the Utility's financial incentives offered to employees include a Short-Term Incentive Plan ("STIP"), an at-risk part of employee compensation designed to reward eligible employees for achieving specific performance goals. The 2023 STIP was focused on company objectives of safety, customer impact, and financial health.

reworded Diversity, Equity, Inclusion, and Belonging

FY 2022 10-K
Removed
Filed Feb 23, 2023

Diversity, Equity, Inclusion, and Belonging PG&E Corporation's and the Utility's goal is to foster a diverse, equitable, and inclusive environment that enables all of their coworkers to bring their best selves to work so that they can provide exceptional customer service. These efforts are led by PG&E Corporation's and the Utility's Executive Vice President, People, Shared Services and Supply Chain, with support from the executive team. The People and Compensation Committee of PG&E Corporation's Board of Directors reviews the companies' diversity, equity, inclusion, and belonging practices and performance. Key elements of PG&E Corporation's and the Utility's approach include active programming to heighten cultural competency, encourage understanding and appreciation of diversity, and integrate thoughtful content into training and performance support materials. Additionally, the Utility's 11 Employee Resource Groups and three Engineering Network Groups execute enterprise-wide available programming, certain coworkers lead efforts within their departments, and other specialized teams facilitate dialogue across the companies. These efforts foster employee belonging and support an environment of inclusion that values and respects diversity in the workforce. In 2022, women, minorities, and military veterans accounted for approximately 26%, 49% and 7%, respectively, of total PG&E Corporation and Utility employees. Approximately 8% of the Utility's employees are younger than 30, 62% are between the ages of 30 and 49, and 30% are 50 or older.

FY 2023 10-K
Added
Filed Feb 22, 2024

Diversity, Equity, Inclusion, and Belonging PG&E Corporation's and the Utility's goal is to foster a diverse, equitable, and inclusive workforce culture where all employees find it enjoyable to work with and for PG&E Corporation and the Utility and feel they belong. These efforts are led by PG&E Corporation's and the Utility's Executive Vice President, Chief People Officer, in partnership with the executive team. The People and Compensation Committee of PG&E Corporation's Board of Directors reviews the companies' diversity, equity, inclusion, and belonging strategy, practices, and performance. Key elements of PG&E Corporation's and the Utility's approach include active programming to heighten cultural awareness, encourage understanding and appreciation of diversity, and integrate thoughtful content into training, development, and performance support resources. Additionally, the Utility's 12 Employee Resource Groups and three Engineering Network Groups execute enterprise-wide employee programming, nominated employees lead efforts within their departments, and other specialized teams facilitate dialogue across the companies. In 2023, women, minorities, and military veterans accounted for approximately 26%, 50%, and 7%, respectively, of total PG&E Corporation and Utility employees. Approximately 9% of the Utility's employees are younger than 30, 62% are between the ages of 30 and 49, and 29% are 50 or older. 28

reworded Electric Utility Operations

FY 2022 10-K
Removed
Filed Feb 23, 2023

Electric Utility Operations The Utility generates electricity and provides electric transmission and distribution services throughout its service area in northern and central California to residential, commercial, industrial, and agricultural customers. The Utility provides electricity, transmission and distribution services in its service area. Customers also can obtain electricity from alternative providers such as municipalities or CCAs, as well as from self-generation resources, such as rooftop solar installations. For more information, see "Regulatory Matters" in Item 7. MD&A.

FY 2023 10-K
Added
Filed Feb 22, 2024

Electric Utility Operations The Utility generates electricity and provides electric transmission and distribution services throughout its service area in northern and central California to residential, commercial, industrial, and agricultural customers. The Utility provides electricity, transmission, and distribution services in its service area. Customers also can obtain electricity from alternative providers such as municipalities or CCAs, as well as from self-generation resources, such as rooftop solar installations. For more information, see "Competition" below.

reworded Electricity Resources

FY 2022 10-K
Removed
Filed Feb 23, 2023

Electricity Resources The Utility is required to maintain adequate capacity to meet its customers' demand for electricity ("load"), including peak demand and planning and operating reserves, deliverable to the locations and at times as may be necessary to provide reliable electric service. The Utility is responsible for scheduling and bidding electric generation resources, including certain electricity procured from third parties into the wholesale market, to meet customer demand. 28 The following table shows the percentage of the Utility's estimated total net deliveries of electricity to customers in 2022 represented by each major electric resource, and further discussed below. The Utility's deliveries were primarily from renewable energy resources that qualify under California's RPS and other GHG-free resources (i.e., nuclear, and large hydroelectric generation). California's RPS requirements and SB 100 goal to serve 100% of retail electricity sales with GHG-free resources by 2045 are discussed further below and in the Environmental Regulation section above.

FY 2023 10-K
Added
Filed Feb 22, 2024

Electricity Resources The Utility is required to maintain adequate capacity to meet its customers' demand for electricity ("load"), including peak demand and planning and operating reserves, deliverable to the locations and at times as may be necessary to provide reliable electric service. The Utility is responsible for scheduling and bidding electric generation resources, including certain electricity procured from third parties into the wholesale market, to meet customer demand. The following table shows the percentage of the Utility's estimated total net deliveries of electricity to customers in 2023 represented by each major electric resource, and further discussed below. The Utility's deliveries were primarily from renewable energy resources that qualify under California's RPS and other GHG-free resources (i.e., nuclear, and large hydroelectric generation). California's RPS requirements and SB 100 goal is to serve 100% of retail electricity sales with GHG-free resources by 2045. For more information about California's RPS requirements and clean energy goals, see further below and in the Environmental Regulation section above.

reworded Percent of customer retail sales (estimated procurement)CEC reporting methodology adjustment(2)

FY 2022 10-K
Removed
Filed Feb 23, 2023

The total estimated electricity generated, procured, and sold (net), as of December 31, 2022 was 30,307 GWh (1) and comprised of the following: Percent of customer retail sales (estimated procurement)CEC reporting methodology adjustment(2)

FY 2023 10-K
Added
Filed Feb 22, 2024

The total estimated electricity generated, procured, and sold (net), as of December 31, 2023 was 26,018 GWh (1) and comprised of the following: Percent of customer retail sales (estimated procurement)CEC reporting methodology adjustment(2)

reworded Large hydroelectric15 %(2)%13 %

FY 2022 10-K
Removed
Filed Feb 23, 2023

Percent of customer retail sales (estimated Power Content Label) (2) Owned generation facilities Renewable (3) 2 %- %2 % Nuclear49 %- %49 % Large hydroelectric7 %- %7 %

FY 2023 10-K
Added
Filed Feb 22, 2024

Percent of customer retail sales (estimated Power Content Label) (2) Owned generation facilities Renewable (3) 2 %- %2 % Nuclear58 %(5)%53 % Large hydroelectric15 %(2)%13 %

reworded 14 %(14)%- %

FY 2022 10-K
Removed
Filed Feb 23, 2023

Fossil fuel-fired (4) 18 %(16)%2 % Total76 %(16)%60 % Third-party purchase agreements Renewable (3) 38 %- %38 % Large hydroelectric- %- %- % Fossil fuel-fired (4)

FY 2023 10-K
Added
Filed Feb 22, 2024

Fossil fuel-fired (4) 25 %(25)%- % Total100 %(32)%68 % Third-party purchase agreements Renewable (3) 35 %(3)%32 % Fossil fuel-fired (4) 14 %(14)%- %

reworded 110 %(10)%100 %

FY 2022 10-K
Removed
Filed Feb 23, 2023

16 %(14)%2 % Total54 %(14)%40 % Others, net (2)(5) (30)%30 %- % TOTAL100 %- %100 % Total renewable energy resources (3) 40 %- %40 % GHG-free resources (6)

FY 2023 10-K
Added
Filed Feb 22, 2024

Total49 %(17)%32 % Others, net (2)(5) (49)%49 %- % TOTAL100 %- %100 % Total renewable energy resources (3) 37 %(3)%34 % GHG-free resources (6) 110 %(10)%100 %

reworded (1) This amount excludes electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers.

FY 2022 10-K
Removed
Filed Feb 23, 2023

96 %- %96 % (1) This amount excludes electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers. (2) The allocation of "Others, net" in the "CEC Reporting Methodology Reduction" and "Power Content Label" columns is consistent with CEC guidelines, applied to specified electric generation and procurement volumes (i.e., fossil fuel-fired, nuclear, large hydroelectric, and renewable). Total reported generation and procurement volumes equate to actual electric retail sales. (3) Amounts include biopower (e.g., biogas, biomass), solar, wind, certain hydroelectric (i.e., 30MW or less), and geothermal facilities. The eligible renewable percentages above do not reflect RPS compliance, which is determined using a different methodology.

FY 2023 10-K
Added
Filed Feb 22, 2024

(1) This amount excludes electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers. (2) The allocation of "Others, net" in the "CEC Reporting Methodology Adjustment" and "Power Content Label" columns is consistent with current CEC guidelines as an adjustment mechanism to apply, as specified. Total reported generation and procurement volumes equate to actual electric retail sales. (3) Amounts include biopower (e.g., biogas, biomass), solar, wind, certain hydroelectric (i.e., 30MW or less), and geothermal facilities. The eligible renewable percentages above do not reflect RPS compliance, which is determined using a different methodology.

reworded (6) Amount is comprised of renewable, nuclear, and large hydroelectric facility resources generated, procured, and sold.

FY 2022 10-K
Removed
Filed Feb 23, 2023

(4) Amounts consist primarily of natural gas facilities. (5) Amount is mainly comprised of net CAISO open market (sales)/purchases. (6) Amount is comprised of renewable, nuclear, and large hydroelectric facility resources generated, procured, and sold.

FY 2023 10-K
Added
Filed Feb 22, 2024

(4) Amounts consist primarily of natural gas facilities. (5) Amount is mainly comprised of net CAISO open market (sales)/purchases. (6) Amount is comprised of renewable, nuclear, and large hydroelectric facility resources generated, procured, and sold. 29

reworded TypePercent of Customer Retail Sales (estimated procurement)(1)

FY 2022 10-K
Removed
Filed Feb 23, 2023

The estimated total renewable deliveries as of December 31, 2022, shown above was 12,163 GWh and comprised of the following: TypePercent of Customer Retail Sales (estimated procurement)(1) (2)

FY 2023 10-K
Added
Filed Feb 22, 2024

The estimated total renewable deliveries as of December 31, 2023, shown above was 9,676 GWh and comprised of the following: TypePercent of Customer Retail Sales (estimated procurement)(1)

reworded At December 31, 2023, the Utility owned the following generation facilities, all located in California, listed by energy source and further described below:

FY 2022 10-K
Removed
Filed Feb 23, 2023

Owned Generation Facilities At December 31, 2022, the Utility owned the following generation facilities, all located in California, listed by energy source and further described below:

FY 2023 10-K
Added
Filed Feb 22, 2024

Owned Generation Facilities At December 31, 2023, the Utility owned the following generation facilities, all located in California, listed by energy source and further described below:

reworded Conventional16 counties in northern and central California96 2,633

FY 2022 10-K
Removed
Filed Feb 23, 2023

Generation TypeCounty LocationNumber of UnitsNet Operating Capacity (MW) Nuclear (1): Diablo CanyonSan Luis Obispo2 2,240 Hydroelectric (2): Conventional16 counties in northern and central California99 2,645

FY 2023 10-K
Added
Filed Feb 22, 2024

Generation TypeCounty LocationNumber of UnitsNet Operating Capacity (MW) Nuclear (1): Diablo CanyonSan Luis Obispo2 2,240 Hydroelectric (2): Conventional16 counties in northern and central California96 2,633

reworded Electricity Distribution

FY 2022 10-K
Removed
Filed Feb 23, 2023

Decisions about expansions and maintenance of the transmission system can be influenced by decisions of the Utility's regulators and the CAISO. Electricity Distribution The Utility's electric distribution network consists of approximately 108,000 circuit miles of distribution lines (of which, as of December 31, 2022, approximately 25% are underground and approximately 75% are overhead), 67 transmission switching substations, and 752 distribution substations with a capacity of approximately 36,000 MVA. The Utility's distribution network interconnects with its transmission system, primarily at switching and distribution substations, where equipment reduces the high-voltage transmission voltages to lower voltages, ranging from 44 kV to 2.4 kV, suitable for distribution to the Utility's customers. These distribution substations serve as the central hubs for the Utility's electric distribution network. Emanating from each substation are primary and secondary distribution lines connected to local transformers and switching equipment that link distribution lines and provide delivery to end-users. In some cases, the Utility sells electricity from its distribution facilities to entities, such as municipal and other utilities, that resell the electricity. The Utility operates electric distribution control center facilities in Concord, Rocklin, and Fresno, California; these control centers form a key part of the Utility's efforts to create a smarter, more resilient grid. 31

FY 2023 10-K
Added
Filed Feb 22, 2024

Decisions about expansions and maintenance of the transmission system can be influenced by decisions of the Utility's regulators and the CAISO. 31 Electricity Distribution Distribution lines allow electricity to travel at lower voltages from substations directly to customers. The Utility's electric distribution network consists of approximately 108,000 circuit miles of distribution lines (of which, as of December 31, 2023, approximately 26% are underground and approximately 74% are overhead), 67 transmission switching substations, and 752 distribution substations with a capacity of approximately 36,000 MVA. The Utility's distribution network interconnects with its transmission system, primarily at switching and distribution substations, where equipment reduces the high-voltage transmission voltages to lower voltages, suitable for distribution to the Utility's customers. These distribution substations serve as the central hubs for the Utility's electric distribution network. Emanating from each substation are primary and secondary distribution lines connected to local transformers and switching equipment that link distribution lines and provide delivery to customers. In some cases, third parties, such as municipal and other utilities, who generate or procure their own power rely upon the Utility's distribution facilities to deliver their power to them, so that they are able to resell the electricity. The Utility operates electric distribution control center facilities in Concord, Rocklin, and Fresno, California; these control centers form a key part of the Utility's efforts to create a smarter, more resilient grid.

reworded Electricity Operating Statistics

FY 2022 10-K
Removed
Filed Feb 23, 2023

Electricity Operating Statistics The following table shows certain of the Utility's operating statistics from 2020 to 2022 for electricity sold or delivered, including the classification of revenues by type of service. No single customer of the Utility accounted for 10% or more of consolidated revenues for electricity sold in 2022, 2021 or 2020.

FY 2023 10-K
Added
Filed Feb 22, 2024

Electricity Operating Statistics The following table shows certain of the Utility's operating statistics from 2021 to 2023 for electricity sold or delivered, including the classification of revenues by type of service. No single customer of the Utility accounted for 10% or more of consolidated revenues for electricity sold in 2023, 2022 or 2021.

reworded (1) These amounts include electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers.

FY 2022 10-K
Removed
Filed Feb 23, 2023

Industrial0.1177 0.1075 0.1085 Agricultural0.2435 0.2104 0.2210 Net plant investment per customer$9,967 $9,199 $8,889 (1) These amounts include electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers.

FY 2023 10-K
Added
Filed Feb 22, 2024

Industrial0.1294 0.1177 0.1075 Agricultural0.2984 0.2435 0.2104 Net plant investment per customer$10,720 $9,967 $9,199 (1) These amounts include electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers.

reworded Natural Gas System Assets

FY 2022 10-K
Removed
Filed Feb 23, 2023

Natural Gas System Assets The Utility owns and operates an integrated natural gas transmission, storage, and distribution system that includes most of northern and central California. At December 31, 2022, the Utility's natural gas system consisted of approximately 44,000 miles of distribution pipelines, over 6,300 miles of backbone and local transmission pipelines, and various storage facilities. The Utility owns and operates eight natural gas compressor stations on its backbone transmission system and one compressor station on its local transmission system that are used to move gas through the Utility's pipelines. The Utility's backbone transmission system is used to transport gas from the Utility's interconnection with interstate pipelines, other local distribution companies, and California gas fields to the Utility's local transmission and distribution systems. The Utility has firm transportation agreements for the transportation of natural gas from various natural gas supply points and interconnection points to the Utility's natural gas transportation system. These agreements provide transportation service from western Canada to the United States-Canada border, from the United States-Canada border to an interconnection point with the Utility's natural gas transportation system at the Oregon-California border, from the U.S. Rocky Mountains to an interconnection point with the Utility's natural gas transportation system at the Oregon-California border, and from supply points in the southwestern United States to interconnection points with the Utility's natural gas transportation system in the area of California near Topock, Arizona. (For more information regarding the Utility's natural gas transportation agreements, see Note 16 of the Notes to the Consolidated Financial Statements in Item 8.) The Utility owns and operates three underground natural gas storage fields and has a 25% interest in a fourth storage field, all of which are connected to the Utility's gas transmission system. In 2019, the CPUC approved the discontinuation, through closure or sale, of operations at two of the Utility's owned and operated gas storage fields, Pleasant Creek and Los Medanos. The Utility expects to sell Pleasant Creek in 2023 in accordance with the CPUC's final decision in the 2019 GT&S rate case. The Utility intends to retain the Los Medanos field to further support system supply reliability as proposed in the 2023 GRC. The Utility owns and operates compressors and other facilities at these storage fields that are used to inject gas into the fields for storage and later for withdrawal. In addition, four independent storage operators are interconnected to the Utility's Northern California gas transmission system. In 2022, the Utility continued upgrading transmission pipeline to allow for the use of in-line inspection tools and substantially completed its work on the final recommendation from the NTSB's 2010-11 San Bruno investigation to confirm testing or perform a hydrostatic test for all Class 3 and Class 4 pipelines and all high consequence pipeline mileage. 33

FY 2023 10-K
Added
Filed Feb 22, 2024

Natural Gas System Assets The Utility owns and operates an integrated natural gas transmission, storage, and distribution system that includes most of northern and central California. At December 31, 2023, the Utility's natural gas system consisted of approximately 44,200 miles of distribution pipelines, over 6,400 miles of backbone and local transmission pipelines, and various storage facilities. The Utility owns and operates eight natural gas compressor stations on its backbone transmission system and one compressor station on its local transmission system that are used to move gas through the Utility's pipelines. The Utility's backbone transmission system is used to transport gas from the Utility's interconnection with interstate pipelines, other local distribution companies, and California gas fields to the Utility's local transmission and distribution systems. The Utility has firm transportation agreements for the transportation of natural gas from various natural gas supply points and interconnection points to the Utility's natural gas transportation system. These agreements provide transportation service from western Canada to the United States-Canada border, from the United States-Canada border to an interconnection point with the Utility's natural gas transportation system at the Oregon-California border, from the U.S. Rocky Mountains to an interconnection point with the Utility's natural gas transportation system at the Oregon-California border, and from supply points in the southwestern United States to interconnection points with the Utility's natural gas transportation system in the area of California near Topock, Arizona. (For more information regarding the Utility's natural gas transportation agreements, see Note 15 of the Notes to the Consolidated Financial Statements in Item 8.) The Utility owns and operates three underground natural gas storage fields and has a 25% interest in a fourth storage field, all of which are connected to the Utility's gas transmission system. In 2019, the CPUC approved the discontinuation, through closure or sale, of operations at two of the Utility's owned and operated gas storage fields, Pleasant Creek and Los Medanos. The Utility expects to close on the sale of Pleasant Creek in 2024. The Utility plans to keep the Los Medanos storage field in operation as filed and approved in the 2023 GRC. The Utility owns and operates compressors and other facilities at these storage fields that are used to inject gas into the fields for storage and later for withdrawal. In addition, four independent storage operators are interconnected to the Utility's Northern California gas transmission system.

reworded Average annual residential usage (Mcf)37 37 37

FY 2022 10-K
Removed
Filed Feb 23, 2023

Subtotal6,055 4,958 4,386 Regulatory balancing accounts (2) 565 553 225 Total operating revenues$6,620 $5,511 $4,611 Selected Statistics: Average annual residential usage (Mcf)37 37 37

FY 2023 10-K
Added
Filed Feb 22, 2024

Subtotal6,196 6,055 4,958 Regulatory balancing accounts (2) 808 565 553 Total operating revenues$7,004 $6,620 $5,511 Selected Statistics: Average annual residential usage (Mcf)37 37 37

reworded Regulatory Environment

FY 2022 10-K
Removed
Filed Feb 23, 2023

Regulatory Environment The Utility's business is subject to the regulatory jurisdiction of various agencies at the federal, state, and local levels. At the state level, the Utility is regulated primarily by the CPUC. At the federal level, the Utility is regulated primarily by the FERC and the NRC. The Utility is also subject to the requirements of other federal, state and local regulatory agencies, including with respect to safety, the environment, and health, such as the NTSB and OEIS. This section and the "Environmental Regulation" and the "Ratemaking Mechanisms" sections below summarize some of the more significant laws, regulations, and regulatory proceedings affecting the Utility. For more information, see Item 1A. Risk Factors and "Regulatory Matters" in Item 7. MD&A. PG&E Corporation is a "public utility holding company" as defined under the Public Utility Holding Company Act of 2005 and is subject to regulatory oversight by the FERC. PG&E Corporation and its subsidiaries are exempt from all requirements of the Public Utility Holding Company Act of 2005 other than the obligation to provide access to their books and records to the FERC and the CPUC for ratemaking purposes.

FY 2023 10-K
Added
Filed Feb 22, 2024

Regulatory Environment The Utility's business is subject to the regulatory jurisdiction of various agencies at the federal, state, and local levels. At the state level, the Utility is regulated primarily by the CPUC. At the federal level, the Utility is regulated primarily by the FERC and the NRC. The Utility is also subject to the requirements of other federal, state and local regulatory agencies, including with respect to safety, the environment, and health, such as the NTSB and the OEIS. This section and the "Environmental Regulation" and the "Ratemaking Mechanisms" sections below summarize some of the more significant laws, regulations, and regulatory proceedings affecting the Utility. For more information, see Item 1A. Risk Factors and "Regulatory Matters" in Item 7. MD&A. 16 PG&E Corporation is subject to the Public Utility Holding Company Act as a public utility holding company. The Public Utility Holding Company Act primarily obligates PG&E Corporation and its utility subsidiaries to provide access to their books and records to the FERC and the CPUC for ratemaking purposes.

  FY2021 → FY2022 Text Diffs 

escalated Other Regulators The filing added the OEIS as a new regulator responsible for reviewing safety certifications and wildfire mitigation, and it included extensive detail regarding the Utility's need to obtain permits, authorizations, and franchise agreements from cities and counties. Additionally, the description of the California Geologic Energy Management Division was updated from regulating "underground gas storage wells" to "underground gas storage facilities."

FY 2021 10-K
Removed
Filed Feb 10, 2022

Other Regulators The California Energy Commission is California's primary energy policy and planning agency. The CEC is responsible for licensing all thermal power plants over 50 MW within California. The CEC also is responsible for forecasts of future energy needs used by the CPUC in determining the adequacy of the utilities' electricity procurement plans and for adopting building and appliance energy efficiency requirements. The CARB is the state agency responsible for setting and monitoring GHG and other emission limits. The CARB is also responsible for adopting and enforcing regulations to implement state law requirements to gradually reduce GHG emissions in California. See "Environmental Regulation - Air Quality and Climate Change" below. The NTSB is an independent U.S. government investigative agency responsible for civil transportation accident investigations, including pipeline accidents. The NTSB also conducts special investigations and safety studies, and issues safety recommendations to prevent future accidents. The California Geologic Energy Management Division is the state agency responsible for establishing and enforcing regulations for the operation of the Utility's underground gas storage wells.

FY 2022 10-K
Added
Filed Feb 23, 2023

Other Regulators The CEC is California's primary energy policy and planning agency. The CEC is responsible for licensing all thermal power plants over 50 MW within California. The CEC also is responsible for forecasts of future energy needs used by the CPUC in determining the adequacy of the utilities' electricity procurement plans and for adopting building and appliance energy efficiency requirements. The CARB is the state agency responsible for setting and monitoring GHG and other emission limits. The CARB is also responsible for adopting and enforcing regulations to implement state law requirements to gradually reduce GHG emissions in California. See "Environmental Regulation - Air Quality and Climate Change" below. 18 The NTSB is an independent U.S. government investigative agency responsible for civil transportation accident investigations, including pipeline accidents. The NTSB also conducts special investigations and safety studies, and issues safety recommendations to prevent future accidents. The California Geologic Energy Management Division is the state agency responsible for establishing and enforcing regulations for the operation of the Utility's underground gas storage facilities. The OEIS is a state agency responsible for reviewing and approving the Utility's WMP and for evaluating the Utility's implementation of the WMP. The OEIS is also responsible for reviewing and issuing the Utility's annual safety certification, annually reviewing and approving the Utility's executive compensation plan, conducting assessments of the Utility's safety culture, and conducting field inspections of wildfire mitigation activities. In addition, the Utility obtains permits, authorizations, and licenses in connection with the construction and operation of the Utility's generation facilities, electricity transmission lines, natural gas transportation pipelines, and gas compressor station facilities. The Utility also periodically obtains permits, authorizations, and licenses in connection with distribution of electricity and natural gas that grant the Utility rights to occupy or use public property for the operation of the Utility's business and to conduct certain related operations. The Utility has franchise agreements with approximately 300 cities and counties that permit the Utility to install, operate, and maintain the Utility's electric and natural gas facilities in the public streets and highways. In exchange for the right to use public streets and highways, the Utility pays annual fees to the cities and counties. In most cases, the Utility's franchise agreements are for an indeterminate term, with no expiration date. For more information see Item 1A. Risk Factors.

escalated Nuclear Fuel Disposal

FY 2021 10-K
Removed
Filed Feb 10, 2022

0.001 0.001 Nuclear Fuel Disposal Under the Nuclear Waste Policy Act of 1982, the DOE and electric utilities with commercial nuclear power plants were authorized to enter into contracts under which the DOE would be required to dispose of the utilities' spent nuclear fuel and high-level radioactive waste by January 1998, in exchange for fees paid by the utilities' customers. The DOE has been unable to meet its contractual obligation with the Utility to dispose of nuclear waste from the Utility's two nuclear generating units at Diablo Canyon and the retired nuclear facility at Humboldt Bay. As a result, the Utility constructed interim dry cask storage facilities to store its spent fuel onsite at Diablo Canyon and at Humboldt Bay until the DOE fulfills its contractual obligation to take possession of the spent fuel. The Utility and other nuclear power plant owners sued the DOE to recover the costs that they incurred to construct interim storage facilities for spent nuclear fuel. In September 2012, the U.S. Department of Justice and the Utility executed a settlement agreement that provided a claims process by which the Utility submits annual requests for reimbursement of its ongoing spent fuel storage costs. The claim for the period June 1, 2020 through May 31, 2021, totaled approximately $11.6 million and is currently under review by the DOE. Amounts reimbursed by DOE are refunded to customers through rates. Considerable uncertainty continues to exist regarding when and whether the DOE will meet its contractual obligation to the Utility and other nuclear power plant owners to dispose of spent fuel.

FY 2022 10-K
Added
Filed Feb 23, 2023

0.001 0.001 22 Nuclear Fuel Disposal Nuclear power plant operations produce gaseous, liquid, and solid radioactive wastes, which are covered by federal regulation. High-level radioactive wastes primarily include used nuclear fuel. Low-level waste consists primarily of demineralizer resins, paper, protective clothing, rags, tools, and equipment contaminated through use. Under the Nuclear Waste Policy Act of 1982, the DOE and electric utilities with commercial nuclear power plants were authorized to enter into contracts under which the DOE would be required to dispose of the utilities' spent nuclear fuel and high-level radioactive waste by January 1998, in exchange for fees paid by the utilities' customers. The DOE has been unable to meet its contractual obligation with the Utility to dispose of nuclear waste from the Utility's two nuclear generating units at Diablo Canyon and the retired nuclear facility at Humboldt Bay. As a result, the Utility constructed interim dry cask storage facilities to store its spent fuel onsite at Diablo Canyon and at Humboldt Bay until the DOE fulfills its contractual obligation to take possession of the spent fuel. The Utility and other nuclear power plant owners sued the DOE to recover the costs that they incurred to construct interim storage facilities for spent nuclear fuel. In September 2012, the DOJ and the Utility executed a settlement agreement that provided a claims process by which the Utility submits annual requests for reimbursement of its ongoing spent fuel storage costs. The claim for the period June 1, 2021 through May 31, 2022, totaled approximately $10.5 million and is under review by the DOE. Amounts reimbursed by DOE are refunded to customers through rates. Considerable uncertainty continues to exist regarding when and whether the DOE will meet its contractual obligation to the Utility and other nuclear power plant owners to dispose of spent fuel.

escalated Ratemaking Mechanisms

FY 2021 10-K
Removed
Filed Feb 10, 2022

Ratemaking Mechanisms The Utility's rates for electric and natural gas utility services are generally set at levels that are intended to allow the Utility to recover its costs of providing service and a return on invested capital ("cost-of-service ratemaking"). In order to set rates, the CPUC and the FERC conduct proceedings to determine the amount that the Utility will be authorized to collect from its customers ("revenue requirements"). The Utility's revenue requirements consist primarily of a base amount set to enable the Utility to recover its reasonable operating expenses (e.g., maintenance, administration and general expenses) and capital costs (e.g., depreciation, and financing expenses). In addition, the CPUC authorizes the Utility to collect revenues to recover costs that the Utility is allowed to "pass-through" to customers (referred to as "Utility Revenues and Costs that did not Impact Earnings" in Item 7. MD&A), including its costs to procure electricity and natural gas for customers and to administer public purpose and customer programs. The Utility's rate of return on electric transmission assets is determined in the FERC TO proceedings. The rate of return on all other Utility assets is set in the CPUC's cost of capital proceeding. Other than certain gas transmission and storage revenues, the Utility's base revenues are "decoupled" from its sales volume through certain regulatory balancing accounts, or revenue adjustment mechanisms, that are designed to allow the Utility to collect its authorized base revenue requirements regardless of sales volume. As a result, the Utility's base revenues are not impacted by fluctuations in sales resulting from, for example, weather or economic conditions. The Utility's earnings primarily depend on its ability to manage its base operating and capital costs (referred to as "Utility Revenues and Costs that Impacted Earnings" in Item 7. MD&A) within its authorized base revenue requirements. Due to the seasonal nature of the Utility's business and rate design, customer electric bills are generally higher during summer months (May to October) because of higher demand, driven by air conditioning loads. Customer bills related to gas service are generally higher during winter months (November to March) because of higher demand due to heating. From time to time, the CPUC may use incentive ratemaking mechanisms that provide the Utility an opportunity to earn some additional revenues. For example, the Utility has earned incentives for the successful implementation of energy efficiency programs. 26

FY 2022 10-K
Added
Filed Feb 23, 2023

Ratemaking Mechanisms The Utility operates under a "cost-of-service" ratemaking model, which means that rates for electric and natural gas utility services are generally set at levels that are intended to allow the Utility to recover its costs of providing service and to earn a return on invested capital ("cost-of-service ratemaking"). In order to set rates, the CPUC and the FERC conduct proceedings to determine the amount that the Utility will be authorized to collect from its customers ("revenue requirements"). In the GRC proceedings, the CPUC also generally approves the level of capital spending on a forecasted basis. Revenue authorized by the CPUC through GRC proceedings is intended to provide the Utility a reasonable opportunity to recover its costs and earn a return on its investments in generation and distribution assets and general plant (also referred to as "rate base"). The Utility's revenue requirements consist primarily of a base amount set to enable the Utility to recover its reasonable operating expenses (e.g., maintenance, administration and general expenses) and capital costs (e.g., depreciation, and financing expenses). The Utility's costs of equity and long-term debt are generally approved in the CPUC's cost of capital proceedings. In addition, the CPUC authorizes the Utility to collect revenues to recover costs that the Utility is allowed to "pass through" to customers (referred to as "Utility Revenues and Costs that did not Impact Earnings" in Item 7. MD&A), including its costs to procure electricity and natural gas for customers and to administer public purpose and customer programs. FERC revenue requirements are set through a FERC-approved formula rate. The Utility's rate of return on electric transmission assets is determined in the FERC TO proceedings. Other than certain gas transmission and storage revenues, the Utility's base revenues are "decoupled" from its sales volume through certain regulatory balancing accounts, or revenue adjustment mechanisms, that are designed to allow the Utility to collect its authorized base revenue requirements regardless of sales volume. As a result, the Utility's base revenues are not impacted by fluctuations in sales resulting from, for example, weather or economic conditions. The Utility's earnings primarily depend on its ability to manage its base operating and capital costs (referred to as "Utility Revenues and Costs that Impacted Earnings" in Item 7. MD&A) within its authorized base revenue requirements. Due to the seasonal nature of the Utility's business and rate design, customer electric bills are generally higher during summer months (May to October) because of higher demand, driven by air conditioning loads. Customer bills related to gas service are generally higher during winter months (November to March) because of higher demand due to heating. From time to time, the CPUC may use incentive ratemaking mechanisms that provide the Utility an opportunity to earn additional revenues. For example, the Utility has earned incentives for the successful implementation of energy efficiency programs.

escalated (1) This amount excludes electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers.

FY 2021 10-K
Removed
Filed Feb 10, 2022

93 %- %93 % (1) This amount excludes electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers. (2) The allocation of "Others, Net" in the "CEC Reporting Methodology Reduction" and "Power Content Label" columns is consistent with CEC guidelines, applied to specified electric generation and procurement volumes (i.e., fossil fuel-fired, nuclear, large hydroelectric, and renewable). Total reported generation and procurement volumes equate to actual electric retail sales.

FY 2022 10-K
Added
Filed Feb 23, 2023

96 %- %96 % (1) This amount excludes electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers. (2) The allocation of "Others, net" in the "CEC Reporting Methodology Reduction" and "Power Content Label" columns is consistent with CEC guidelines, applied to specified electric generation and procurement volumes (i.e., fossil fuel-fired, nuclear, large hydroelectric, and renewable). Total reported generation and procurement volumes equate to actual electric retail sales. (3) Amounts include biopower (e.g., biogas, biomass), solar, wind, certain hydroelectric (i.e., 30MW or less), and geothermal facilities. The eligible renewable percentages above do not reflect RPS compliance, which is determined using a different methodology.

escalated (6) Amount is comprised of renewable, nuclear, and large hydroelectric facility resources generated, procured, and sold.

FY 2021 10-K
Removed
Filed Feb 10, 2022

(5) Amount is mainly comprised of net CAISO open market (sales)/purchases. (6) Amount is comprised of renewable, nuclear, and large hydroelectric facility resources generated, procured, and sold. 32

FY 2022 10-K
Added
Filed Feb 23, 2023

(4) Amounts consist primarily of natural gas facilities. (5) Amount is mainly comprised of net CAISO open market (sales)/purchases. (6) Amount is comprised of renewable, nuclear, and large hydroelectric facility resources generated, procured, and sold.

escalated (1) These amounts include electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers.

FY 2021 10-K
Removed
Filed Feb 10, 2022

Net plant investment per customer$9,199 $8,889 $8,375 (1) These amounts include electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers.

FY 2022 10-K
Added
Filed Feb 23, 2023

Industrial0.1177 0.1075 0.1085 Agricultural0.2435 0.2104 0.2210 Net plant investment per customer$9,967 $9,199 $8,889 (1) These amounts include electricity provided by DA providers and CCAs that procure their own supplies of electricity for their respective customers.

escalated See "Ratemaking Mechanisms" below and "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC and FERC proceedings. The status of the wildfire claims recovery shifted from filing an application to achieving CPUC approval, which allowed for bond issuances that retired $5.0 billion in Utility debt; additionally, the Utility reinstated its common stock dividend on June 15, 2022, and set a goal to reduce non-fuel Operating and maintenance costs by two percent per year.

FY 2021 10-K
Removed
Filed Feb 10, 2022

See "Ratemaking Mechanisms" below and "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC and FERC proceedings. Generally, differences between forecast costs and actual costs (referred to as "Utility Revenues and Costs that Impacted Earnings" in Results of Operations in Item 7. MD&A) can occur for numerous reasons, including the volume of work required and the impact of market forces on the cost of labor and materials. Differences in costs can also arise from changes in laws and regulations at both the state and federal level. The Utility has initiated a program to reduce its spending on operations and maintenance. PG&E Corporation and the Utility are committed to taking steps to improve their credit ratings and metrics over time, including by reducing their debt. PG&E Corporation and the Utility have set goals to reduce their debt over time, including reducing PG&E Corporation's debt by $2 billion by the end of 2023. PG&E Corporation and the Utility expect that reducing the consolidated debt will help them achieve investment grade credit ratings for their unsecured securities, for the benefit of both customers and investors. For more information, see Note 5 of the Notes to the Consolidated Financial Statements in Item 8. Additionally, the Utility filed an application with the CPUC seeking authorization for a post-emergence transaction to recover $7.5 billion of 2017 wildfire claims costs. Among other uses, as a result of the proposed transaction, the Utility would retire $6.0 billion of Utility debt. For more information, see "Application for Post-Emergence Securitization Transaction" in Item 7. MD&A. On December 20, 2017, the Boards of Directors of PG&E Corporation and the Utility suspended quarterly cash dividends on both PG&E Corporation's and the Utility's common stock, as well as the Utility's preferred stock. PG&E Corporation's and the Utility's ability to issue dividends is subject to restrictions. On February 8, 2022, the Board of Directors of the Utility authorized the payment of all cumulative and unpaid dividends on the Utility's preferred stock. For more information, see "Dividends" in Item 7. MD&A. Total capital expenditures (including accruals) recorded in 2021 were $8.6 billion. The Utility's total capital expenditures (including accruals) are forecasted to be between $7.8 billion and $8.9 billion for 2022, between $7.9 billion and $10.4 billion for 2023, between $7.9 billion and $10.7 billion for 2024, between $8.0 billion and $11.3 billion for 2025, and between $8.1 billion and $12.0 billion for 2026. The completion of projects, the timing of expenditures, and the associated cost recovery may be affected by permitting requirements and delays, construction schedules, availability of labor, equipment and materials, financing, legal and regulatory approvals and developments, community requests or protests, weather and other unforeseen conditions. The Utility expects to make additional CPUC capital expenditures, the recovery of which will be subject to future regulatory approval, including the 2023 GRC. These expenditures include capital expenditures exceeding amounts authorized in the 2020 GRC, and expenditures to be included in a later stage of the 2023 GRC. The 2023 through 2026 currently above authorized capital spending levels are primarily for additional wildfire mitigation, transportation electrification and the Lakeside Building. Additionally, $3.21 billion of fire risk mitigation capital expenditures will be excluded from the Utility's equity rate base pursuant to AB 1054. 17 PG&E Corporation and the Utility are committed to keeping gas and electric services affordable for all customers. The Utility's capital investment plan, increasing procurement of renewable power and energy storage, increasing environmental regulations, and the cumulative impact of other public policy requirements collectively place continuing upward pressure on customer rates. Certain CPUC proceedings, such as the OIR to Revisit Net Energy Metering Tariffs, could impact different types of customers differently. Similarly, although the Utility generally recovers its electricity and natural gas procurement costs through rates as "pass-through" costs, commodity prices rose substantially in 2021, relative to 2020. The Utility is addressing this customer rate pressure with cost reductions through increased efficiency, including efficiency driven by implementing the Lean operating system, improving its work management, identifying additional opportunities to convert expenses to capital expenditures, and an improved organizational design. The Utility has a number of programs in place to assist low-income customers, such as the CARE program. Under the CARE program, income-qualified customers can receive a monthly discount of 20% or more on their gas and electric bill. PG&E Corporation's and the Utility's Corporate Sustainability Report, which is available to the public, describes the companies' progress toward world-class performance measured with the triple bottom line framework.

FY 2022 10-K
Added
Filed Feb 23, 2023

Under cost-of-service ratemaking, a utility's earnings depend on the outcomes of its ratemaking proceedings and its ability to manage costs. See "Ratemaking Mechanisms" below and "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC and FERC proceedings. Generally, differences between forecast costs and actual costs (discussed in "Utility Revenues and Costs that Impacted Earnings" in Results of Operations in Item 7. MD&A) can occur for numerous reasons, including the volume of work required and the impact of market forces on the cost of labor and materials. Differences in costs can also arise from changes in laws and regulations at both the state and federal level. PG&E Corporation and the Utility are committed to taking steps to improve their credit ratings and metrics over time, including by reducing their debt. PG&E Corporation and the Utility have set goals to reduce their debt over time, including reducing PG&E Corporation's debt by at least $2 billion by the end of 2026. PG&E Corporation and the Utility expect that reducing the consolidated debt will help them achieve investment grade credit ratings for their unsecured securities, for the benefit of both customers and investors. For more information, see Note 5 of the Notes to the Consolidated Financial Statements in Item 8. Pursuant to SB 901, the Utility filed an application with the CPUC seeking authorization for a post-emergence transaction to recover $7.5 billion of 2017 wildfire claims costs, which was approved by the CPUC on February 28, 2022. PG&E Wildfire Recovery Funding LLC, a bankruptcy remote, limited liability company wholly owned by the Utility, issued $3.6 billion aggregate principal amount of Series 2022-A Recovery Bonds on May 10, 2022 and $3.9 billion aggregate principal amount of Series 2022-B Recovery Bonds on July 20, 2022. The net proceeds from both transactions were used to reimburse the Utility for previously incurred recovery costs, including the retirement of $5.0 billion of Utility debt and the repayment of a portion of the loans outstanding under the Utility's revolving credit facility pursuant to the Utility Revolving Credit Agreement. The Utility intends to use a portion of the remaining proceeds to fund the redemption of $1.0 billion of Utility debt. For more information, see "Application for Post-Emergence Securitization Transaction" in Item 7. MD&A. On December 20, 2017, the Boards of Directors of PG&E Corporation and the Utility suspended quarterly cash dividends on both PG&E Corporation's and the Utility's common stock, as well as the Utility's preferred stock. PG&E Corporation's and the Utility's ability to issue dividends is subject to restrictions. On February 8, 2022, the Board of Directors of the Utility authorized the payment of all cumulative and unpaid dividends on the Utility's preferred stock. On June 15, 2022, the Board of Directors of the Utility also reinstated the dividend on the Utility's common stock. For more information, see "Dividends" in Item 7. MD&A. Total capital expenditures (including accruals) recorded in 2022 were $9.6 billion. The Utility's total capital expenditures (including accruals) are forecasted to be between $7.9 billion and $11.2 billion for 2023, between $7.9 billion and $12.2 billion for 2024, between $8.0 billion and $12.7 billion for 2025, between $8.1 billion and $13.3 billion for 2026, and between $8.1 billion and $13.8 billion for 2027. The completion of projects, the timing of expenditures, and the associated cost recovery may be affected by permitting requirements and delays, construction schedules, availability of labor, equipment and materials, financing, legal and regulatory approvals and developments, community requests or protests, weather, and other unforeseen conditions. 14 The Utility expects to make additional capital expenditures, the recovery of which will be subject to future regulatory approval, including the 2023 GRC. These expenditures include capital expenditures exceeding amounts authorized in the 2020 GRC and 2019 GT&S, and expenditures to be included in a later stage of the 2023 GRC or separate applications. These expenditures are expected to primarily be for wildfire mitigation, transportation electrification, and the Lakeside Building. Additionally, $3.21 billion of fire risk mitigation capital expenditures will be excluded from the Utility's equity rate base pursuant to AB 1054. PG&E Corporation and the Utility are committed to keeping gas and electric services affordable for all customers. The Utility's capital investment plan, increasing procurement of renewable power and energy storage, increasing environmental regulations, and the cumulative impact of other public policy requirements collectively place continuing upward pressure on customer rates. Certain CPUC proceedings could impact different types of customers differently. Similarly, although the Utility generally recovers its electricity and natural gas procurement costs through rates as "pass-through" costs, commodity prices rose substantially in 2022, relative to 2021. The Utility has set a goal to increase customer capital investments while also limiting customer impacts, including by reducing non-fuel Operating and maintenance costs by two percent per year and by seeking efficient financing. The Utility plans to meet its two percent non-fuel Operating and maintenance cost reduction goal through increased efficiency, including waste elimination through the Lean operating system. The Utility has a number of programs in place to assist low-income customers, such as the CARE program. Under the CARE program, income-qualified customers can receive a monthly discount of 20% or more on their gas and electric bill. PG&E Corporation's and the Utility's Corporate Sustainability Report, which is available to the public, describes the companies' progress toward world-class performance measured with the triple bottom line framework.

escalated Performance: Underpinning the Triple Bottom Line Gas operations safety worsened in 2022, reporting two workforce serious injuries and fatalities ("SIF-A") compared to zero in the prior period; concurrently, the Utility expanded its EPSS program to all high fire risk areas and introduced microgrids and daily weather modeling to mitigate wildfire risk. Furthermore, the company achieved ISO 55001 certification for both electric and gas operations asset management systems.

FY 2021 10-K
Removed
Filed Feb 10, 2022

In 2021, the Utility also worked to reduce the impact of EPSS by adjusting the sensitivity of devices to reduce the likelihood of an outage, improving coordination between its devices to reduce the size of outages, and improving internal coordination of patrol crews for faster restoration times. In 2022, the Utility plans to expand the scope of the EPSS program to all HFTD areas. The Utility has focused on continuously improving its gas operations safety record. Since the San Bruno natural gas pipeline explosion in 2010, the Utility's asset safety efforts have included replacing distribution mains and transmission pipelines, as well as strength testing transmission pipelines. The Utility uses in-line inspections to assess the integrity of transmission pipelines. The Utility also uses safety and control systems to monitor, gather, and process real-time data on its gas system. In 2021, the Utility's gas operations achieved zero workforce serious injuries and fatalities ("SIF-A") incidents and reductions in the number of injuries that result in days away, restricted or transferred duty per 200,000 hours worked ("DART"). As of the date of this filing, the Utility's gas system has not had a public safety-related incident that resulted in a fatality or injury since 2015 or 2018, respectively. The Utility has engaged in educating employees, contractors, and the public regarding safe digging programs and practices for their awareness during construction and when digging near the Utility's underground gas and electric assets. The Utility also installed safety devices that automatically detect increasing pressure on systems and stop the flow of gas to avoid outages and overpressure events. Additionally, the Utility continues to streamline its efforts to respond to outages timely. The Utility's outage response is designed to keep the public safe while limiting customer outages and returning service safely and as quickly as possible. The Utility's generation operations have focused on safety and reliability. In 2021, the Utility's generation operations achieved zero SIF-A incidents and reductions in DART. Challenged by a drought year, the Utility scheduled dispatch and rescheduled outages to maximize availability during the summer months when demand for electricity is highest. The Utility is working to implement a comprehensive generation asset management strategy and further mature its outage and project management capabilities.

FY 2022 10-K
Added
Filed Feb 23, 2023

Even as the Utility works to mitigate wildfire risk, it also works to reduce the impact of those mitigations on its customers, including making the PSPS program less disruptive through sectionalizing devices for both distribution and transmission lines, temporary generation applications, and implementation of microgrids which enable portions of the grid to safely isolate areas from the broader grid and energize them during outages. For example, in 2022, the Utility prepared 12 distribution microgrids to operate with temporary generation if needed. In 2022, the Utility expanded the EPSS program to all high fire risk areas. In addition, the Utility uses multiple weather models on a daily basis that indicate which circuits to enable with safety settings and which to put in normal protection settings, optimizing for maximum wildfire ignition risk reduction when needed and enhancing reliability benefits when wildfire risk is low. In 2022, the Utility also began reviewing and adjusting settings to improve coordination among devices on a circuit to reduce the number of customers impacted by an outage. In 2023, the Utility will expand its deployment of advanced technology to detect low-current faults, which is expected to further decrease wildfire ignition risk. PG&E Corporation and the Utility are continuing to invest in a safe and reliable gas system and are working toward targeted electrification, greening the gas supply, and shaping California energy policy. The Utility has focused on continuously improving its gas operations safety record. Since the San Bruno natural gas pipeline explosion in 2010, the Utility's asset safety efforts have included replacing distribution mains and transmission pipelines, as well as strength testing transmission pipelines. The Utility uses in-line inspections to assess the integrity of transmission pipelines. The Utility also uses safety and control systems to monitor, gather, and process real-time data on its gas system. In 2022, the Utility's gas operations had two workforce serious injuries and fatalities ("SIF-A") incidents and reductions in the number of injuries that result in days away, restricted or transferred duty per 200,000 hours worked ("DART"). The Utility's gas system has not had a safety-related incident that affected the public and resulted in a fatality or injury since 2015 or 2018, respectively. 16 The Utility has engaged in educating employees, contractors, and the public regarding safe digging programs and practices for their awareness during construction and when digging near the Utility's underground gas and electric assets. The Utility also installed safety devices that automatically detect increasing pressure on systems and stop the flow of gas to avoid outages and overpressure events. Additionally, the Utility continues to streamline its efforts to respond to outages on a timely basis. The Utility's outage response is designed to keep the public safe while limiting customer outages and returning service safely and as quickly as possible. The Utility's generation operations have focused on safety and reliability. In 2022, the Utility's nuclear and non-nuclear generation operations achieved zero SIF-A incidents and reductions in DART. Challenged by a drought year, the Utility scheduled dispatch and rescheduled outages to maximize availability during the summer months when demand for electricity is highest. The Utility is working to implement a comprehensive non-nuclear generation asset management strategy and further mature its outage and project management capabilities. In 2022, the Utility achieved International Organization for Standardization ("ISO") 55001 certification for its electric operations and generation asset management systems. The Utility also achieved ISO 55001 re-certification for its gas operations asset management. ISO 55001 certification required the Utility to demonstrate that it has policies and procedures to manage its assets responsibly and effectively.

de-emphasised Material Effects of Compliance with Governmental Regulations The detailed discussion outlining 2021 compliance costs—including infrastructure upgrades, participation in the Wildfire Fund under AB 1054, and regulations regarding Diablo Canyon—has been removed from this section. The reference to Note 14 was also updated to Note 16.

FY 2021 10-K
Removed
Filed Feb 10, 2022

Material Effects of Compliance with Governmental Regulations As indicated above, the Utility's business is subject to the regulatory jurisdiction of various agencies at the federal, state, and local levels. Compliance with such extensive government regulations requires substantial expenditures and has had in the past and may continue to have in the future a material effect on PG&E Corporation's and the Utility's financial condition, results of operations, liquidity, cash flows and competitive position. Generally, the Utility expects to recover the cost of compliance with government regulations through rates in its GRC proceedings, or other proceedings. To the extent the Utility incurs costs above authorized or incurs additional types of costs not included in rates, the Utility would expect to apply for recovery of such costs. Such recovery would be subject to the CPUC's approval and could involve its reasonableness review. Costs incurred in 2021 included costs in connection with upgrading and maintaining the Utility's electric and natural gas infrastructure in accordance with CPUC and federal requirements, participating in the Wildfire Fund under AB 1054, execution of wildfire mitigation initiatives, the licensing and other regulations of the FERC, environmental regulations, clean energy standards, regulations regarding Diablo Canyon, and various other generation, distribution and storage regulations, the amount of which was substantial. If the Utility is unable to recover these costs or incurs fines or penalties as a result of non-compliance with such laws and regulations, PG&E Corporation's and the Utility's financial condition, results of operations, liquidity, cash flows and competitive position could be materially impacted. For more information, see Item 1A. Risk Factors, "Regulatory Matters" in Item 7. MD&A, and Notes 14 and 15 of the Notes to the Consolidated Financial Statements in Item 8. 22

FY 2022 10-K
Added
Filed Feb 23, 2023

Material Effects of Compliance with Governmental Regulations As indicated above, the Utility's business is subject to the regulatory jurisdiction of various agencies at the federal, state, and local levels. Compliance with such extensive government regulations requires substantial expenditures and has had in the past and may continue to have in the future a material effect on PG&E Corporation's and the Utility's financial condition, results of operations, liquidity, cash flows and competitive position. For more information about costs incurred to comply with government regulations and related material effects on PG&E Corporation and the Utility, see Item 1A. Risk Factors, "Regulatory Matters" in Item 7. MD&A, and Notes 15 and 16 of the Notes to the Consolidated Financial Statements in Item 8.

de-emphasised Safety The safety strategy shifted from focusing on "systems and culture" to emphasizing "workforce and public safety," which now includes targeting mitigations for the highest risk work. Additionally, the detailed description of COVID-19 response measures, such as remote work policies, virtual ergonomic evaluations, and benefit updates, was removed entirely from the disclosure.

FY 2021 10-K
Removed
Filed Feb 10, 2022

All PG&E Corporation or Utility officer compensation currently is funded by shareholders. Safety The Utility has developed a five-year workforce safety strategy that includes two major pillars: systems and culture. Systems refers to risk management, equipment, processes and procedures. Culture refers to employee engagement, adherence to established requirements, a sense of urgency for safety, and leadership. Focus areas in the Utility's workplace safety strategy include: an enterprise safety management system, enhanced risk management, strengthening the contractor management program, improvement of safety technical standards, ergonomics, safety audits, improving data management and reporting systems, and enhancing safety leadership training. For employees and contractors performing medium- and high-risk work, the Utility's safety metrics include the number of SIF-A incidents and the SIF-P rate, which measures events that could have resulted in a SIF-A per 200,000 hours worked. In 2021, the Utility had five SIF-A events, which resulted in three fatalities and three serious injuries, and a SIF-P rate of 0.11, which was 10% higher than the SIF-P rate in 2020. The requirement for contractors to report SIF-P events was implemented in June 2020. Additionally, the Utility measures DART. In 2021, the Utility's DART was 1.01, which was 25% lower than in 2020 and its lowest rate in the past five years. Throughout the COVID-19 pandemic, PG&E Corporation and the Utility have continued to monitor activities at the Centers for Disease Control and Prevention and the World Health Organization, PG&E Corporation and the Utility have updated their protocols and actions in accordance with guidance from these organizations, following state and local health and safety regulations, and in consultation with the Utility's medical director. PG&E Corporation and the Utility have also remained focused on protecting the health and safety of their employees, contractors and the Utility's customers, while continuing to perform critical utility work, and have continued to monitor and track the impact of the pandemic, modifying or adopting new policies in support of their employees' health and safety as pandemic conditions and governmental response have changed. For example, PG&E Corporation and the Utility have directed employees to work remotely from home where possible, implemented face coverings, physical distancing policies, and required a daily health check when an employee works outside his or her home, required virtual ergonomic evaluations to ensure that employees working from home so do safely and ergonomically, provided additional COVID-19 safety resources for employees who perform utility work in the field, and updated several of their employee benefits as a result of COVID-19, including healthcare benefits and interim time off and leave policies that support the care and new educational environment of children during the pandemic.

FY 2022 10-K
Added
Filed Feb 23, 2023

All PG&E Corporation and Utility officer compensation currently is funded by shareholders. Safety The Utility's strategy to deliver on safety outcomes focuses on workforce, and public safety. In 2023, in addition to deploying the safety management system, the Utility targets mitigations to the highest risk work. The Utility's safety metrics include the number of SIF-A incidents and the SIF-P rate, which measures events that could have resulted in a SIF-A per 200,000 hours worked. In 2022, the Utility had seven SIF-A incidents, which resulted in three fatalities and four serious injuries, and a SIF-P rate of 0.11. Additionally, the Utility measures DART. In 2022, the Utility's DART was 0.67, which was 34% lower than in 2021 and its lowest rate in the past five years. Throughout the COVID-19 pandemic, PG&E Corporation and the Utility have continued to monitor activities at the Centers for Disease Control and Prevention and the World Health Organization. PG&E Corporation and the Utility have updated their protocols and actions in accordance with guidance from these organizations, following state and local health and safety regulations, and in consultation with the Utility's medical director. PG&E Corporation and the Utility have also remained focused on protecting the health and safety of their employees, contractors and the Utility's customers, while continuing to perform critical utility work, and have continued to monitor and track the impact of the pandemic, modifying or adopting new policies in support of their employees' health and safety as pandemic conditions and governmental response have changed.

reworded PG&E Corporation's and the Utility's operating revenues, income, and total assets can be found below in Item 8. Financial Statements and Supplementary Data.

FY 2021 10-K
Removed
Filed Feb 10, 2022

PG&E Corporation's and the Utility's operating revenues, income, and total assets can be found below in Item 8. Financial Statements and Supplementary Data. The principal executive offices of PG&E Corporation and the Utility are located at 77 Beale Street, P.O. Box 770000, San Francisco, California 94177. PG&E Corporation's telephone number is (415) 973-1000 and the Utility's telephone number is (415) 973-7000. This is a combined Annual Report on Form 10-K for PG&E Corporation and the Utility. Each of PG&E Corporation and the Utility is a separate entity, with distinct creditors and claimants, and is subject to separate laws, rules, and regulations. Over the past several years, Northern California has experienced major wildfires. For more information about material wildfires, see Item 7. MD&A, and Note 14 of the Notes to the Consolidated Financial Statements in Item 8. This 2021 Form 10-K contains forward-looking statements that are necessarily subject to various risks and uncertainties. For a discussion of the significant risks that could affect the outcome of these forward-looking statements and PG&E Corporation's and the Utility's future financial condition, results of operations, liquidity, and cash flows, see Item 1A. Risk Factors and "Forward-Looking Statements" above.

FY 2022 10-K
Added
Filed Feb 23, 2023

PG&E Corporation's and the Utility's operating revenues, income, and total assets can be found below in Item 8. Financial Statements and Supplementary Data. The principal executive offices of PG&E Corporation and the Utility are located at 300 Lakeside Drive, Oakland, California 94612. PG&E Corporation's telephone number is (415) 973-1000 and the Utility's telephone number is (415) 973-7000. This is a combined Annual Report on Form 10-K for PG&E Corporation and the Utility. Each of PG&E Corporation and the Utility is a separate entity, with distinct creditors and claimants, and is subject to separate laws, rules, and regulations. 11 Over the past several years, Northern California has experienced major wildfires. For more information about material wildfires, see Item 7. MD&A, and Note 15 of the Notes to the Consolidated Financial Statements in Item 8. This 2022 Form 10-K contains forward-looking statements that are necessarily subject to various risks and uncertainties. For a discussion of the significant risks that could affect the outcome of these forward-looking statements and PG&E Corporation's and the Utility's future financial condition, results of operations, liquidity, and cash flows, see Item 1A. Risk Factors and "Forward-Looking Statements" above.

reworded State Regulation

FY 2021 10-K
Removed
Filed Feb 10, 2022

State Regulation California's AB 32, the Global Warming Solutions Act of 2006, provided for the gradual reduction of state-wide GHG emissions to 1990 levels by 2020. The CARB has approved various regulations to achieve the 2020 target, including GHG emissions reporting and a state-wide, comprehensive cap-and-trade program that sets gradually declining limits (or "caps") on the amount of GHGs that may be emitted by major GHG emission sources within different sectors of the economy. The cap-and-trade program's first compliance period, which began on January 1, 2013, applied to the electric generation and large industrial sectors. In the subsequent compliance period, which began on January 1, 2015, the scope of the regulation was expanded to include the natural gas and transportation sectors, effectively covering all of the state economy's major sectors through 2020. The Utility's compliance obligation as a natural gas supplier applies to the GHG emissions attributable to the combustion of natural gas delivered to the Utility's customers other than large natural gas delivery customers that are separately regulated as covered entities and have their own compliance obligation. In 2017, AB 398 extended the cap-and-trade program through January 1, 2031. During each year of the program, the CARB issues emission allowances (i.e., the rights to emit GHGs) equal to the amount of GHG emissions allowed for that year. Entities with a compliance obligation can obtain allowances from the CARB at quarterly auctions or from third parties or exchanges. Complying entities may also satisfy a portion of their compliance obligation through the purchase of offset credits (e.g., credits for GHG reductions achieved by third parties, such as landowners, livestock owners, and farmers, that occur outside of the entities' facilities through CARB-qualified offset projects such as reforestation or biomass projects). The Utility expects all costs and revenues associated with the GHG cap-and-trade program to be passed through to customers. SB 32 (2016) requires that CARB ensure a 40% reduction in GHGs by 2030 compared to 1990 levels. The California RPS program that requires utilities to gradually increase the amount of renewable energy delivered to their customers is also expected to help reduce GHG emissions in California. In September 2018, SB 100 was signed into law, which accelerated California's 50% RPS target to December 31, 2026, increased the RPS target to 60% by December 31, 2030, and further amended the RPS statute to set a policy of meeting 100% of retail sales from eligible renewables and zero-carbon resources by December 31, 2045. Additionally, EO B-55-18 set a statewide goal to achieve economy-wide carbon neutrality by 2045 and to maintain net negative emissions thereafter. The Utility will be an active participant in regulatory proceedings to determine how the state will achieve carbon neutrality. For the percentage of the Utility's estimated total net deliveries of electricity to customers in 2021, including estimated GHG-free and renewable energy percentages, see "Electric Utility Operations-Electricity Resources" below.

FY 2022 10-K
Added
Filed Feb 23, 2023

State Regulation California's Global Warming Solutions Act of 2006 originally provided for the gradual reduction of state-wide GHG emissions to 1990 levels by 2020. The CARB has approved various regulations to achieve the 2020 target, including GHG emissions reporting and a state-wide, comprehensive cap-and-trade program that sets gradually declining limits (or "caps") on the amount of GHGs that may be emitted by major GHG emission sources within different sectors of the economy. The cap-and-trade program applies to the electric generation, large industrial, natural gas, petroleum, and transportation sectors. The Utility's compliance obligation as a natural gas supplier applies to the GHG emissions attributable to the combustion of natural gas delivered to the Utility's customers other than large natural gas delivery customers that are separately regulated as covered entities and have their own compliance obligation. The cap-and-trade program has been extended through 2030. During each year of the program, the CARB issues emission allowances (i.e., the rights to emit GHGs) equal to the amount of GHG emissions allowed for that year. Entities with a compliance obligation can obtain allowances from the CARB at quarterly auctions or from third parties or exchanges. Complying entities may also satisfy a portion of their compliance obligation through the purchase of offset credits (e.g., credits for GHG reductions achieved by third parties, such as landowners, livestock owners, and farmers, that occur outside of the entities' facilities through CARB-qualified offset projects such as reforestation or biomass projects). The Utility expects all costs and revenues associated with the GHG cap-and-trade program to be passed through to customers. 20 California law requires that the CARB ensure a 40% reduction in GHGs by 2030 compared to 1990 levels. The California RPS program that requires utilities to gradually increase the amount of renewable energy delivered to their customers is also expected to help reduce GHG emissions in California. California's RPS targets are 50% by December 31, 2026 and 60% by December 31, 2030, and the State has set a policy of meeting 100% of retail sales from eligible renewables and zero-carbon resources by December 31, 2045. In 2022, AB 1279 was signed into law, codifying a statewide goal to achieve economy-wide carbon neutrality by 2045 and to maintain net negative emissions thereafter. Additionally in 2022, SB 1020 established targets that renewable and zero-carbon resources will supply 90% of utilities' retail sales to customers by 2035 and 95% of retail sales by 2040. The Utility will be an active participant in regulatory proceedings to determine how the state will achieve carbon neutrality. For the percentage of the Utility's estimated total net deliveries of electricity to customers in 2022, including estimated GHG-free and renewable energy percentages, see "Electric Utility Operations-Electricity Resources" below.

reworded Emissions Data

FY 2021 10-K
Removed
Filed Feb 10, 2022

Emissions Data PG&E Corporation and the Utility track and report their annual environmental performance results across a broad spectrum of areas. The Utility reports its GHG emissions to the CARB and the EPA on a mandatory basis. On a voluntary basis, the Utility reports a more comprehensive emissions inventory to The Climate Registry, a non-profit organization. The Utility's third-party verified voluntary GHG inventory reported to The Climate Registry for 2020, which is the most recent data available, totaled more than 44 million metric tons of CO2 equivalent, the majority of which came from customer natural gas use. The following table shows the 2020 GHG emissions data the Utility reported to the CARB under AB 32, which is the most recent data available. PG&E Corporation and the Utility also publish additional GHG emissions data in their annual Corporate Sustainability Report.

FY 2022 10-K
Added
Filed Feb 23, 2023

Emissions Data PG&E Corporation and the Utility track and report their annual environmental performance results across a broad spectrum of areas. The Utility reports its GHG emissions to the CARB and the EPA on a mandatory basis. On a voluntary basis, the Utility reports a more comprehensive emissions inventory to The Climate Registry, a non-profit organization. The Utility's third-party verified voluntary GHG inventory reported to The Climate Registry for 2021, which is the most recent data available, totaled Scope 1 and 2 emissions of approximately 4.6 million metric tons of CO2 equivalent (MMT CO2e) and Scope 3 emissions of approximately 42 MMT CO2e, the majority of which came from customer natural gas use. The following table shows the 2021 GHG emissions data the Utility reported to the CARB, which is the most recent data available. PG&E Corporation and the Utility also publish additional GHG emissions data in their annual Corporate Sustainability Report.

reworded (1) Includes nitrous oxide and methane emissions from the Utility's generating stations.

FY 2021 10-K
Removed
Filed Feb 10, 2022

Distribution Fugitive Natural Gas Emissions 497,512 Customer Natural Gas Use (3) 40,304,583 (1) Includes nitrous oxide and methane emissions from the Utility's generating stations.

FY 2022 10-K
Added
Filed Feb 23, 2023

Distribution fugitive natural gas emissions 589,343 Customer natural gas use (3) 41,563,483 (1) Includes nitrous oxide and methane emissions from the Utility's generating stations.

reworded (2) Includes emissions from compressor stations and storage facilities that are reportable to CARB.

FY 2021 10-K
Removed
Filed Feb 10, 2022

(2) Includes emissions from compressor stations and storage facilities that are reportable to CARB. (3) Includes emissions from the combustion of natural gas delivered to all entities on the Utility's distribution system, with the exception of gas delivered to other natural gas local distribution companies. The Utility utilized the CEC's Power Source Disclosure program methodology to calculate the CO2 emissions rate associated with the electricity delivered to retail customers in 2020. This resulted in a third-party verified CO2 emissions rate of 160 pounds of CO2 per MWh. 25

FY 2022 10-K
Added
Filed Feb 23, 2023

(2) Includes emissions from compressor stations and storage facilities that are reportable to CARB. (3) Includes emissions from the combustion of natural gas delivered to all entities on the Utility's distribution system, with the exception of gas delivered to other natural gas local distribution companies. The Utility utilized the CEC's Power Source Disclosure program methodology to calculate the CO2 emissions rate associated with the electricity delivered to retail customers in 2021. This resulted in a third-party verified CO2 emissions rate of 99 pounds of CO2 per MWh.

reworded General Rate Cases

FY 2021 10-K
Removed
Filed Feb 10, 2022

See "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC proceedings. Base Revenues General Rate Cases The GRC is the primary proceeding in which the CPUC determines the amount of base revenue requirements that the Utility is authorized to collect from customers to recover the Utility's anticipated costs related to its electric distribution, natural gas distribution, and Utility-owned electric generation operations and return on rate base. In the past, the CPUC has generally conducted a GRC every three years. Starting with the 2023 GRC, the CPUC will conduct a GRC every four years that includes the Utility's costs of its gas transmission and storage facilities. The CPUC approves the annual revenue requirements for the first year (or "test year") of the GRC period and typically authorizes the Utility to receive annual increases in revenue requirements for the subsequent years of the GRC period (known as "attrition years"). Attrition year rate adjustments are generally authorized for cost increases related to invested capital and inflation. Parties in the Utility's GRC include the Public Advocates Office of the CPUC (formerly known as Office of Ratepayer Advocates or ORA) and TURN, which generally represent the overall interests of residential customers, as well as numerous intervenors, that represent other business, community, customer, environmental, and union interests. For more information about the Utility's GRC, see "Regulatory Matters - 2020 General Rate Case" and "Regulatory Matters - 2023 General Rate Case" in Item 7. MD&A.

FY 2022 10-K
Added
Filed Feb 23, 2023

See "Regulatory Matters" in Item 7. MD&A for more information on specific CPUC proceedings. 23 Base Revenues General Rate Cases The GRC is the primary proceeding in which the CPUC determines the amount of base revenue requirements that the Utility is authorized to collect from customers to recover the Utility's anticipated costs related to its electric distribution, natural gas distribution, and Utility-owned electric generation operations and return on rate base. In the past, the CPUC has generally conducted a GRC every three years. Starting with the 2023 GRC, the CPUC now conducts a GRC every four years that includes the Utility's costs of its gas transmission and storage facilities. The CPUC approves the annual revenue requirements for the first year (or "test year") of the GRC period and typically authorizes the Utility to receive annual increases in revenue requirements for the subsequent years of the GRC period (known as "attrition years"). Attrition year rate adjustments are generally authorized for cost increases related to invested capital and inflation. Parties in the Utility's GRC include the Public Advocates Office of the CPUC (formerly known as Office of Ratepayer Advocates or ORA) and TURN, which generally represent the overall interests of residential customers, as well as numerous intervenors that represent other business, community, customer, environmental, and union interests. For more information about the Utility's GRC, see "Regulatory Matters - 2023 General Rate Case" in Item 7. MD&A.

reworded Program-Specific Memorandum Account and Balancing Account Costs

FY 2021 10-K
Removed
Filed Feb 10, 2022

Program-Specific Memorandum Account and Balancing Account Costs Periodically, costs arise outside of the CPUC GRC rate requests or that have been deliberately excluded therefrom. These costs may result from catastrophic events, changes in regulation, new programs, or extraordinary changes in operating practices. The Utility may seek authority to track incremental costs in a memorandum account and the CPUC may authorize recovery of costs tracked in memorandum accounts if the costs are deemed reasonable. For instance, these accounts allow the Utility to track the costs associated with work related to disaster and wildfire response, and other wildfire prevention-related costs. Recovery of the costs tracked in these memorandum accounts in rates requires CPUC authorization in separate proceedings for which the Utility may be unable to predict the outcome. Alternatively, the Utility may seek authority to track incremental costs related to these non-GRC programs in balancing accounts. The CPUC may authorize recovery of costs tracked in the balancing accounts on either a "one-way" basis, which only allows actual costs to be recovered up to a pre-established cap, or a "two-way" basis, which allows actual costs to be recovered, subject to CPUC review. For more information, see "Regulatory Matters - Cost Recovery Proceedings" in Item 7. MD&A and Note 4 of the Notes to the Consolidated Financial Statements in Item 8. 27

FY 2022 10-K
Added
Filed Feb 23, 2023

Program-Specific Memorandum Account and Balancing Account Costs Periodically, costs arise outside of the CPUC GRC proceedings or that have been deliberately excluded therefrom. These costs may result from catastrophic events, changes in regulation, new programs, or extraordinary changes in operating practices. The Utility may seek authority to track incremental costs in a memorandum account, and the CPUC may authorize recovery of costs tracked in memorandum accounts if the costs are deemed reasonable. For instance, these accounts allow the Utility to track the costs associated with work related to disaster and wildfire response, and other wildfire prevention-related costs. Recovery of the costs tracked in these memorandum accounts in rates requires CPUC authorization in separate proceedings for which the Utility may be unable to predict the outcome. Alternatively, the Utility may seek authority to track incremental costs related to these non-GRC programs in balancing accounts. The CPUC may authorize recovery of costs tracked in the balancing accounts on either a "one-way" basis, which typically only allows actual costs to be recovered up to a pre-established cap, or a "two-way" basis, which typically allows actual costs to be recovered, and in some cases subject to further CPUC review. For more information, see "Regulatory Matters - Cost Recovery Proceedings" in Item 7. MD&A and Note 4 of the Notes to the Consolidated Financial Statements in Item 8. 24

reworded Electricity Procurement Costs

FY 2021 10-K
Removed
Filed Feb 10, 2022

Revenues to Recover Energy Procurement and Other Pass-Through Costs Electricity Procurement Costs California IOUs are responsible for procuring electrical capacity required to meet bundled customer demand, plus applicable reserve margins, that are not satisfied from their own generation facilities and existing electric contracts. The utilities are responsible for scheduling and bidding electric generation resources, including certain electricity procured from third parties into the wholesale market, to meet customer demand according to which resources are the least expensive (i.e., using the principles of "least-cost dispatch"). In addition, the utilities are required to obtain CPUC approval of their BPPs based on long-term demand forecasts. In October 2015, the CPUC approved the Utility's most recent comprehensive BPP. It was revised since its initial approval and will remain in effect as revised until superseded by a subsequent CPUC-approved plan. California law allows electric utilities to recover the costs incurred in compliance with their CPUC-approved BPPs without further after-the-fact reasonableness review by the CPUC. The CPUC may disallow costs associated with electricity purchases if the costs were not incurred in compliance with the CPUC-approved plan or if the CPUC determines that the utility failed to follow the principles of least-cost dispatch. Additionally, the CPUC may disallow the value of lost generation due to unplanned outages at utility-owned generation facilities. The Utility recovers its electric procurement costs annually primarily through balancing accounts. See Note 4 of the Notes to the Consolidated Financial Statements in Item 8. Each year, the CPUC reviews the Utility's forecasted procurement costs related to power purchase agreements, derivative instruments, GHG emissions costs, and generation fuel expense, and approves a forecasted revenue requirement. The CPUC may adjust the Utility's retail electric rates more frequently if the forecasted aggregate over-collections or under-collections in the Energy Resource Recovery Account, net of Portfolio Allocation Balancing Account balances, exceed five percent of its prior year electric procurement and Utility-owned generation revenues. The CPUC performs an annual compliance review of the procurement transactions recovered in various balancing accounts, including the Energy Resource Recovery Account and the Portfolio Allocation Balancing Account. The CPUC has approved various power purchase agreements that the Utility has entered into with third parties in accordance with the Utility's CPUC-approved BPP, to meet mandatory renewable energy targets, and to comply with RA requirements. For more information, see "Electric Utility Operations - Electricity Resources" below as well as Note 15 of the Notes to the Consolidated Financial Statements in Item 8. The Utility is also responsible, as the central procurement entity ("CPE") for its distribution service area, for seeking to procure the entire amount of required local RA on behalf of all load serving entities in its distribution service area. The decision grants the Utility, acting as CPE, discretion to defer procurement of local resources to the CAISO's backstop mechanisms if bid costs are deemed unreasonably high. The Utility, as the CPE, will not be assessed fines or penalties for failing to procure resources to meet the local RA requirements and deferring local procurement to the CAISO backstop mechanism, as long as the CPE exercised reasonable efforts to secure capacity and certain specified requirements are met. In connection with its CPE function, the Utility is responsible for making compliance demonstrations to the CPUC and the CAISO. The Utility recovers its administrative and procurement costs associated with its CPE function through a balancing account. Each year, the CPUC reviews the Utility's forecasted administrative costs related to the CPE function and approves a forecasted revenue requirement associated with the administrative costs. The CPUC performs an annual compliance review of the CPE function, including procurement transactions with terms of five years or less (for which costs incurred in compliance with certain prescribed criteria are deemed reasonable and pre-approved without further after-the-fact reasonableness review). Procurement transactions with terms exceeding five years are reviewed separately. The CPUC may disallow costs associated with the CPE function that were not incurred in compliance with the CPUC's decisions and guidance. The CPUC has also approved the Power Charge Indifference Adjustment ("PCIA"). The PCIA is a cost recovery mechanism to ensure that customers who switch from the Utility's bundled service to a non-Utility provider, such as a DA or CCA provider, pay their share of the above market costs associated with long-term power purchase commitments and Utility-owned generation made on their behalf.

FY 2022 10-K
Added
Filed Feb 23, 2023

Revenues to Recover Energy Procurement and Other Pass-Through Costs Electricity Procurement Costs California IOUs are responsible for procuring electrical capacity required to meet bundled customer demand, plus applicable reserve margins. The utilities are responsible for scheduling and bidding electric generation resources, including certain electricity procured from third parties into the wholesale market, to meet customer demand according to which resources are the least expensive (i.e., using the principles of "least-cost dispatch"). In addition, the utilities are required to obtain CPUC approval of their Bundled Procurement Plans ("BPPs") based on long-term demand forecasts. In October 2015, the CPUC approved the Utility's most recent comprehensive BPP. It has been revised since its initial approval, and the revised version will remain in effect, subject to any further revisions, until superseded by a subsequent CPUC-approved plan. California law allows electric utilities to recover the costs incurred in compliance with their CPUC-approved BPPs without further after-the-fact reasonableness review by the CPUC. The CPUC may disallow costs associated with electricity purchases if the costs were not incurred in compliance with the CPUC-approved plan or if the CPUC determines that the utility failed to follow the principles of least-cost dispatch. Additionally, the CPUC may disallow the value of lost generation due to unplanned outages at utility-owned generation facilities. The Utility recovers its electric procurement costs annually primarily through balancing accounts. See Note 4 of the Notes to the Consolidated Financial Statements in Item 8. Each year, the CPUC reviews the Utility's forecasted procurement costs related to power purchase agreements, derivative instruments, GHG emissions costs, and generation fuel expense, and approves a forecasted revenue requirement. The CPUC may adjust the Utility's retail electric rates more frequently if the forecasted aggregate over-collections or under-collections in the Energy Resource Recovery Account, net of bundled service customer Portfolio Allocation Balancing Account balances, exceed five percent of its prior year electric procurement and Utility-owned generation revenues. The CPUC performs an annual compliance review of the procurement transactions recovered in various balancing accounts, including the Energy Resource Recovery Account and the Portfolio Allocation Balancing Account. The CPUC has approved various power purchase agreements that the Utility has entered into with third parties in accordance with the Utility's CPUC-approved BPP, to meet mandatory renewable energy targets, and to comply with RA requirements. For more information, see "Electric Utility Operations - Electricity Resources" below as well as Note 16 of the Notes to the Consolidated Financial Statements in Item 8. The Utility is also responsible, as the central procurement entity ("CPE") for its distribution service area, for seeking to procure the entire amount of required local RA on behalf of all CPUC-jurisdictional LSEs in its distribution service area. CPUC decisions grant the Utility, acting as CPE, discretion to defer procurement of local resources to the CAISO's backstop mechanisms if bid costs are deemed unreasonably high. The Utility, as the CPE, will not be assessed fines or penalties for failing to procure resources to meet the local RA requirements and deferring local procurement to the CAISO backstop mechanism, as long as the CPE exercised reasonable efforts to secure capacity and certain specified requirements are met. In addition, the Utility, as the CPE, has been ordered or authorized to seek to procure specific local capacity products pursuant to CPUC decisions. In connection with its CPE function, the Utility is responsible for making compliance demonstrations to the CPUC and the CAISO. The Utility recovers its administrative and procurement costs associated with its CPE function through a balancing account. Each year, the CPUC reviews the Utility's forecasted administrative costs related to the CPE function and approves a forecasted revenue requirement associated with the administrative costs. The CPUC performs an annual compliance review of the CPE function, including procurement transactions with terms of five years or less (for which costs incurred in compliance with certain prescribed criteria are deemed reasonable and pre-approved without further after-the-fact reasonableness review). Procurement transactions with terms exceeding five years are reviewed separately. The CPUC may disallow costs associated with the CPE function that were not incurred in compliance with the CPUC's decisions and guidance. The CPUC has also approved the Power Charge Indifference Adjustment ("PCIA"). The PCIA is a cost recovery mechanism to ensure that customers who switch from the Utility's bundled service to a non-Utility provider, such as a DA or CCA provider, pay their share of the above market costs associated with long-term power purchase commitments and Utility-owned generation made on their behalf.

reworded Employees and Contractors

FY 2021 10-K
Removed
Filed Feb 10, 2022

Employees and Contractors As of December 31, 2021, PG&E Corporation and the Utility had approximately 26,000 regular employees, 11 of whom were employees of PG&E Corporation. Of the Utility's regular employees, approximately 16,000 are covered by collective bargaining agreements with the local chapters of three labor unions: the International Brotherhood of Electrical Workers ("IBEW") Local 1245; the Engineers and Scientists of California ("ESC") IFPTE 20; and the Service Employees International Union Local 24/7 ("SEIU"). The collective bargaining agreements currently in effect for the IBEW Local 1245 and ESC Local 20 will expire on December 31, 2025. The agreements increase wages annually by 3.75% from 2022 through 2025 and maintain current contributions to specified benefits. The IBEW and ESC represent approximately 62% of the Utility's employee workforce and support several areas of the Utility's business, including gas and electric operations. The term of the SEIU bargaining agreement ended on December 31, 2021. The parties have reached an agreement which is pending ratification by the SEIU. The Utility enjoys stable and productive relationships with its unions and did not experience any work stoppages in 2021. PG&E Corporation's employees are primarily at the executive management level, which experienced significant employee turnover throughout the course of its Chapter 11 Cases in 2019 and 2020. The Utility generally has a stable workforce, which translated into low voluntary turnover during that period. The Utility's turnover rates for 2021 and 2020 were 5.8% and 4.7%, respectively. Approximately 41% of PG&E Corporation's and the Utility's employees have a tenure of more than 10 years, with an average tenure of 11 years. Currently, approximately 21% of PG&E Corporation's and the Utility's employees are eligible to retire. (PG&E Corporation and the Utility define retirement age as 55 years and older.)

FY 2022 10-K
Added
Filed Feb 23, 2023

Employees and Contractors As of December 31, 2022, PG&E Corporation had 10 employees and the Utility had approximately 26,000 regular employees. Of the Utility's regular employees, approximately 16,000 are covered by collective bargaining agreements with the local chapters of three labor unions: the International Brotherhood of Electrical Workers ("IBEW") Local 1245; the Engineers and Scientists of California ("ESC") IFPTE 20; and the Service Employees International Union Local 24/7 ("SEIU"). The collective bargaining agreements in effect for the IBEW Local 1245; ESC Local 20; and SEIU, United Service Workers West will expire on December 31, 2025. The agreements increase wages annually by 3.75% from 2022 through 2025 and maintain current contributions to specified benefits. The IBEW, ESC, and SEIU represent approximately 62% of the Utility's employee workforce and support several areas of the Utility's business, including gas and electric operations. The Utility enjoys stable and productive relationships with its unions and did not experience any work stoppages in 2022. PG&E Corporation's employees are primarily at the executive management level, which experienced significant employee turnover throughout the course of its Chapter 11 Cases in 2019 and 2020. The Utility generally has a stable workforce, which translated into low voluntary turnover during that period. The Utility's turnover rates for 2022 and 2021 were 7.1% and 5.8%, respectively. Approximately 42% of PG&E Corporation's and the Utility's employees have a tenure of more than 10 years, with an average tenure of 11 years. Approximately 19% of PG&E Corporation's and the Utility's employees are eligible to retire. (PG&E Corporation and the Utility define retirement age as 55 years and older.)

reworded Planet

FY 2021 10-K
Removed
Filed Feb 10, 2022

For more information, see "Human Capital" below. Planet The planet element of the triple bottom line represents PG&E Corporation's and the Utility's commitment to protect and serve the environment. This commitment extends beyond compliance with various state and federal environmental, health, and safety laws and regulations. Management believes that integrating and managing climate change and other environmental considerations in the companies' business strategies creates long-term value for PG&E Corporation and the Utility, and for their customers, communities, coworkers, and other stakeholders. Mitigating and adapting to the impacts of climate change presents opportunities for growth for the Utility's business and economic opportunity for the communities it serves. The Utility strives to be prepared to continue to deliver safe, clean, affordable, and reliable energy in the face of increasingly severe and extreme climate-driven natural hazards. To build resilience to these hazards, the Utility is working to systematically integrate the consideration of forward-looking climate data and tools in its decision-making. PG&E Corporation and the Utility also work with policymakers and regulators to advance effective climate adaptation policy in California, and work directly with local governments and communities on adaptation solutions. PG&E Corporation and the Utility are an important enabler of California's effort to reduce GHG emissions. California has set a goal to achieve economy-wide carbon neutrality no later than 2045. SB 100 increased California's RPS target to 60% by the end of 2030 and requires 100% of retail sales to come from eligible renewables or zero-carbon resources by the end of 2045. The impacts of climate change on the Utility's infrastructure are already a reality. Record-breaking extreme heat and heat waves are increasingly a regular occurrence throughout California. Peak loads are expected to increase with increasing temperatures due to direct impacts of ambient temperatures on equipment and direct impacts on electricity demand driven by rising air conditioning installation and usage. The Utility's assets on the coast and in or near watersheds face potential increased exposures to coastal, riverine, and precipitation-related flooding because of climate-driven changes in precipitation and sea-level rise. Climate change will also continue to intensify the potential for wildfires throughout California. The worsening conditions across California increase the likelihood and severity of wildfires, including those where the Utility's equipment may be alleged to be associated with the fire's ignition. Reducing risk will be even more important as climate change continues to exacerbate the risks facing the Utility. A key element of preparing the Utility for the physical risks of climate change is a system-wide CVA of the Utility's assets, operations, and services, which the Utility expects to file with the CPUC in 2024. The CVA is expected to improve the Utility's understanding of its exposure to climate hazards and the sensitivity of assets and operations to these hazards. 15 The electric power industry is undergoing transformative change driven by technological advancements enabling customer choice (for example, customer-owned generation and energy storage) and state climate policy supporting a decarbonized economy. California utilities also are experiencing increasing deployment by customers and third parties of distributed energy resources, such as on-site solar generation, energy storage, fuel cells, energy efficiency, and load management technologies. These developments will require sustained investments in grid modernization, renewable integration projects, energy efficiency programs, energy storage options, and EV infrastructure. To this end, the CPUC is conducting proceedings to evaluate changes to the planning and operation of the electric distribution grid in order to prepare for higher penetration of distributed energy resources and consider future grid modernization and grid reinforcement investments; evaluate if traditional grid investments can be deferred by distributed energy resources, and if feasible, what, if any, compensation to utilities would be appropriate for enabling those investments; and clarify the role of the electric distribution grid operator. PG&E Corporation and the Utility continue to pursue policies and programs that enable safe, reliable, and affordable clean and resilient energy for their customers. As a result of actions already taken by PG&E Corporation and the Utility, the companies have: •Exceeded California's renewable portfolio standards goal for each utility (including the Utility) to deliver 33 percent of eligible renewable energy by the end of 2020, and delivered clean electricity to customers in 2021 that was more than 90% GHG free.

FY 2022 10-K
Added
Filed Feb 23, 2023

For more information, see "Human Capital" below. Planet The planet element of the triple bottom line represents PG&E Corporation's and the Utility's commitment to protect and serve the environment. This commitment extends beyond compliance with various state and federal environmental, health, and safety laws and regulations. PG&E Corporation and the Utility believe that integrating and managing climate change and other environmental considerations in the companies' business strategies creates long-term value for PG&E Corporation and the Utility, and for their customers, communities, coworkers, and other stakeholders. Mitigating and adapting to the impacts of climate change presents opportunities for growth for the Utility's business and economic opportunity for the communities it serves. 12 The Utility strives to be prepared to continue to deliver safe, clean, affordable, and reliable energy in the face of increasingly severe and extreme climate-driven natural hazards. To build resilience to these hazards, the Utility is working to systematically integrate the consideration of forward-looking climate data and tools in its decision-making. PG&E Corporation and the Utility also work with policymakers and regulators to advance effective climate adaptation policy in California, and work directly with local governments and communities on adaptation solutions. PG&E Corporation and the Utility have committed to helping heal the planet. PG&E Corporation's and the Utility's Climate Strategy Report, which is available to the public, describes the companies' climate goals and plans to meet those goals. To meet their longer-term climate goals, PG&E Corporation and the Utility intend to scale their efforts to decarbonize the electric system to accommodate a shift to vehicle electrification, integrate a proliferation of distributed energy resources, and achieve increased penetration of renewable energy combined with investments in the grid and energy storage. PG&E Corporation and the Utility also plan to transition the gas system to cleaner fuels, increasingly target natural gas delivery for hard-to-electrify customer sectors, and support efforts to accelerate building electrification. The objective is to do so in an orderly manner to achieve a positive customer and community experience, while reducing natural gas system investments in targeted electrified communities. The impacts of climate change on the Utility's infrastructure are already a reality. Record-breaking extreme heat and heat waves are increasingly a regular occurrence throughout California. Peak electric loads are expected to increase with increasing temperatures due to direct impacts of ambient temperatures on equipment and direct impacts on electricity demand driven by rising air conditioning installation and usage, and increasingly driven in the future from widespread progress in adoption of beneficial electrification technologies. The Utility's assets on the coast and in or near watersheds face potential increased exposures to coastal, riverine, and precipitation-related flooding because of climate-driven changes in precipitation and sea-level rise. Climate change will also continue to intensify the potential for wildfires throughout California. The worsening conditions across California increase the likelihood and severity of wildfires, including those where the Utility's equipment may be alleged to be associated with the fire's ignition. Reducing risk will be even more important as climate change continues to exacerbate the risks facing the Utility. A key element of preparing the Utility for the physical risks of climate change is an updated and more detailed system-wide CVA of the Utility's assets, operations, and services, which the Utility expects to file with the CPUC in 2024. The CVA is expected to improve the Utility's understanding of its exposure to climate hazards and the sensitivity of assets and operations to these hazards. PG&E Corporation and the Utility continue to pursue policies and programs that enable safe, reliable, and affordable clean and resilient energy for their customers. As a result of actions already taken by PG&E Corporation and the Utility, the companies have:

reworded Human Capital Management

FY 2021 10-K
Removed
Filed Feb 10, 2022

The Utility's contractors and subcontractors include approximately 35,300 individuals from approximately 1,560 contractor companies. Human Capital Management PG&E Corporation's and the Utility's human capital resource objectives are to build and retain an engaged, well trained, diverse, and equitable workforce. PG&E Corporation's and the Utility's Boards of Directors are responsible for overseeing management's development and execution of PG&E Corporation's and the Utility's human capital strategy. To build employee engagement, the Utility has a variety of both executive-level and employee-led initiatives and programs. PG&E Corporation's and the Utility's executive teams meet regularly to discuss and evaluate the state of employee talent, determine which programs are driving engagement and performance, and clarify the specific skills, behaviors, and values that should be cultivated. Each year, the Utility honors employees whose work embodies safety, diversity and inclusion, environmental leadership, and community service. The Utility conducts a biennial employee engagement survey, quarterly pulse surveys, and voluntary upward feedback surveys to measure and track employee engagement progress. Every year, PG&E Corporation and the Utility offer or require technical, leadership, and employee training, which includes a range of technical training for employees on the knowledge and skills required to perform their jobs safely using approved tools and work procedures. In addition, employees are required to complete an annual compliance and ethics training and a Code of Conduct training, both of which are intended to promote a culture in which employees are encouraged to speak up with any concerns or ideas for continuous improvement. In addition, the Utility offers a variety of other trainings and education opportunities. Among other programs, the Utility provides career opportunities through its Power Pathway™ workforce development program. Launched in 2008, PowerPathway is a workforce development model to enlarge the talent pool of local, qualified, diverse candidates for skilled craft and utility industry jobs through training program partnerships with educational, community-based and government organizations. PowerPathway helps people throughout the Utility service territory, including women and military veterans, prepare and compete for high demand jobs in the utility and energy industry. Students receive approximately eight weeks of industry-informed curriculum to ensure the academic, job specific, employability skills and physical training necessary to effectively compete for entry-level employment. Programs may also include hands-on training and on-the-job training. PG&E Corporation and the Utility also provide integrated solutions and programs that cover employee health and wellness and that encompass physical, emotional, and financial health, including an on-site health clinic, an annual health screening, and health management tools and resources, in addition to more traditional programs. 30 PG&E Corporation's and the Utility's financial incentives offered to employees include a Short-Term Incentive Plan ("STIP"), an at-risk part of employee compensation designed to reward eligible employees for achieving specific performance goals. The 2021 STIP was focused on company objectives of safety, customer impact, and financial health.

FY 2022 10-K
Added
Filed Feb 23, 2023

The Utility's contractors and subcontractors include approximately 42,000 individuals from approximately 1,200 contractor companies. Human Capital Management PG&E Corporation's and the Utility's human capital resource objectives are to build and retain an engaged, well trained, diverse, and equitable workforce. PG&E Corporation's and the Utility's Boards of Directors are responsible for overseeing management's development and execution of PG&E Corporation's and the Utility's human capital strategy. To build employee engagement, the Utility has a variety of both executive-level and employee-led initiatives and programs. PG&E Corporation's and the Utility's executive teams meet regularly to discuss and evaluate the state of employee talent, determine which programs are driving engagement and performance, and clarify the specific skills, behaviors, and values that should be cultivated. Each year, the Utility honors employees whose work embodies safety, diversity, equity, inclusion, belonging, environmental leadership, and community service. The Utility conducts an annual employee engagement survey to measure and improve employee engagement progress. Every year, PG&E Corporation and the Utility offer or require technical, leadership, and employee training, which includes a range of technical training for employees on the knowledge and skills required to perform their jobs safely using approved tools and work procedures. In addition, employees are required to complete an annual compliance and ethics training and a Code of Conduct training, both of which are intended to promote a culture in which employees are encouraged to speak up with any concerns or ideas for continuous improvement. In addition, the Utility offers a variety of other trainings and education opportunities. Among other programs, the Utility provides career opportunities through its PowerPathway™ workforce development program. Launched in 2008, PowerPathway is a workforce development model to enlarge the talent pool of local, qualified, diverse candidates for skilled craft and utility industry jobs through training program partnerships with educational, community-based and government organizations. PowerPathway helps people throughout the Utility's service area, including women and military veterans, prepare and compete for high demand jobs in the utility and energy industry. Students receive approximately eight weeks of industry-informed curriculum to ensure the academic, job specific, employability skills and physical training necessary to effectively compete for entry-level employment. Programs may also include hands-on training and on-the-job training. PG&E Corporation and the Utility also provide integrated solutions and programs that cover employee health and wellness and that encompass physical, emotional, and financial health, including an on-site health clinic, an annual health screening, and health management tools and resources, in addition to more traditional programs. 27 PG&E Corporation's and the Utility's financial incentives offered to employees include a Short-Term Incentive Plan ("STIP"), an at-risk part of employee compensation designed to reward eligible employees for achieving specific performance goals. The 2022 STIP was focused on company objectives of safety, customer impact, and financial health.

reworded Diversity, Equity, Inclusion, and Belonging

FY 2021 10-K
Removed
Filed Feb 10, 2022

Diversity and Inclusion PG&E Corporation's and the Utility's goal is to foster a diverse, equitable, and inclusive environment that enables all of their coworkers to bring their best selves to work so that they can provide exceptional customer service. These efforts are led by PG&E Corporation's and the Utility's Executive Vice President, People, Shared Services and Supply Chain, with support from the executive team. The People and Compensation Committee of PG&E Corporation's Board of Directors reviews the companies' diversity and inclusion practices and performance. Key elements of PG&E Corporation's and the Utility's approach include active programming to heighten cultural competency, encourage understanding and appreciation of diversity, and integrate thoughtful content into training and performance support materials. Additionally, the Utility's 11 Employee Resource Groups and three Engineering Network Groups execute enterprise-wide programming, certain coworkers lead efforts within their departments, and other specialized teams facilitate dialogue across the companies. These efforts foster employee belonging and support an environment of inclusion that values and respects diversity in the workforce. In 2021, women, minorities, and military veterans accounted for approximately 27%, 48% and 7%, respectively, of total PG&E Corporation and Utility employees. Approximately 8% of the Utility's employees are younger than 30, 60% are between the ages of 30 and 49, and 32% are 50 or older. 31

FY 2022 10-K
Added
Filed Feb 23, 2023

Diversity, Equity, Inclusion, and Belonging PG&E Corporation's and the Utility's goal is to foster a diverse, equitable, and inclusive environment that enables all of their coworkers to bring their best selves to work so that they can provide exceptional customer service. These efforts are led by PG&E Corporation's and the Utility's Executive Vice President, People, Shared Services and Supply Chain, with support from the executive team. The People and Compensation Committee of PG&E Corporation's Board of Directors reviews the companies' diversity, equity, inclusion, and belonging practices and performance. Key elements of PG&E Corporation's and the Utility's approach include active programming to heighten cultural competency, encourage understanding and appreciation of diversity, and integrate thoughtful content into training and performance support materials. Additionally, the Utility's 11 Employee Resource Groups and three Engineering Network Groups execute enterprise-wide available programming, certain coworkers lead efforts within their departments, and other specialized teams facilitate dialogue across the companies. These efforts foster employee belonging and support an environment of inclusion that values and respects diversity in the workforce. In 2022, women, minorities, and military veterans accounted for approximately 26%, 49% and 7%, respectively, of total PG&E Corporation and Utility employees. Approximately 8% of the Utility's employees are younger than 30, 62% are between the ages of 30 and 49, and 30% are 50 or older.

reworded Electric Utility Operations

FY 2021 10-K
Removed
Filed Feb 10, 2022

Electric Utility Operations The Utility generates electricity and provides electric transmission and distribution services throughout its service territory in northern and central California to residential, commercial, industrial, and agricultural customers. The Utility provides "bundled" services (i.e., electricity, transmission, and distribution services) to customers in its service territory. Customers also can obtain electricity from alternative providers such as municipalities or CCAs, as well as from self-generation resources, such as rooftop solar installations. For more information, see "Regulatory Matters" in Item 7. MD&A.

FY 2022 10-K
Added
Filed Feb 23, 2023

Electric Utility Operations The Utility generates electricity and provides electric transmission and distribution services throughout its service area in northern and central California to residential, commercial, industrial, and agricultural customers. The Utility provides electricity, transmission and distribution services in its service area. Customers also can obtain electricity from alternative providers such as municipalities or CCAs, as well as from self-generation resources, such as rooftop solar installations. For more information, see "Regulatory Matters" in Item 7. MD&A.

reworded Percent of customer retail sales (estimated procurement)CEC reporting methodology adjustment(2)

FY 2021 10-K
Removed
Filed Feb 10, 2022

The total estimated electricity generated, procured, and sold (net), as of December 31, 2021 was 33,149 GWh (1) and comprised of the following: Percent of Bundled Retail Sales (estimated procurement)CEC Reporting Methodology Adjustment(2)

FY 2022 10-K
Added
Filed Feb 23, 2023

The total estimated electricity generated, procured, and sold (net), as of December 31, 2022 was 30,307 GWh (1) and comprised of the following: Percent of customer retail sales (estimated procurement)CEC reporting methodology adjustment(2)

reworded Renewable Energy Resources

FY 2021 10-K
Removed
Filed Feb 10, 2022

Renewable Energy Resources California law established an RPS that requires LSEs, such as the Utility, to gradually increase the amount of renewable energy they deliver to their customers. SB 350 increased the amount of renewable energy that must be delivered by most LSEs, including the Utility, to their customers from 33% of their total annual retail sales by the end of the 2017-2020 compliance period, to 50% of their total annual retail sales by the end of the 2028- 2030 compliance period, and in each three-year compliance period thereafter, unless changed by legislative action. SB 350 provides compliance flexibility and waiver mechanisms, including increased flexibility to apply excess renewable energy procurement in one compliance period to future compliance periods. In September 2018, the California Governor signed SB 100 into law, increasing from 50% to 60% of California's electricity portfolio that must come from renewables by 2030; and established state policy that 100% of all retail electricity sales must come from RPS-eligible or carbon-free resources by 2045. The Utility may in the future incur additional costs to procure renewable energy to meet the new renewable energy targets, which the Utility expects will continue to be recoverable through rates as "pass-through" costs. The Utility also may be subject to penalties for failure to meet the higher targets. The CPUC is required to open a new rulemaking proceeding to adopt regulations to implement the higher renewable targets. Renewable generation resources, for purposes of the RPS requirements, include bioenergy such as biogas and biomass, certain hydroelectric facilities (30 MW or less), wind, solar, and geothermal energy. RPS requirements are based on procurement, which aligns with the methodology presented in the first column of the table above. Procurement from renewable energy sources was estimated as 50% in 2021.

FY 2022 10-K
Added
Filed Feb 23, 2023

Renewable Energy Resources California law established an RPS that requires LSEs, such as the Utility, to gradually increase the amount of renewable energy they deliver to their customers. SB 350 increased the amount of renewable energy that must be delivered by most LSEs, including the Utility, to their customers from 33% of their total annual retail sales by the end of the 2017-2020 compliance period, to 50% of their total annual retail sales by the end of the 2028-2030 compliance period, and in each three-year compliance period thereafter, unless changed by legislative action. SB 350 provides compliance flexibility and waiver mechanisms, including increased flexibility to apply excess renewable energy procurement in one compliance period to future compliance periods. In September 2018, the California Governor signed SB 100 into law, increasing from 50% to 60% of California's electricity portfolio that must come from renewables by 2030; and established state policy that 100% of all retail electricity sales must come from RPS-eligible or carbon-free resources by 2045. The Utility may in the future incur additional costs to procure renewable energy to meet the new renewable energy targets, which the Utility expects will continue to be recoverable through rates as "pass-through" costs. The Utility also may be subject to penalties for failure to meet the higher targets. 29 Renewable generation resources, for purposes of the RPS requirements, include bioenergy such as biogas and biomass, certain hydroelectric facilities (30 MW or less), wind, solar, and geothermal energy. RPS requirements are based on procurement, which aligns with the methodology presented in the first column of the table above. Procurement from renewable energy sources was estimated to comprise 40% of total annual retail sales in 2022.

reworded TypePercent of Customer Retail Sales (estimated procurement)(1) (2)

FY 2021 10-K
Removed
Filed Feb 10, 2022

The estimated total renewable deliveries as of December 31, 2021 shown above was 16,387 GWh and comprised of the following: TypePercent of Bundled Retail Sales (estimated procurement)(1) (2)

FY 2022 10-K
Added
Filed Feb 23, 2023

The estimated total renewable deliveries as of December 31, 2022, shown above was 12,163 GWh and comprised of the following: TypePercent of Customer Retail Sales (estimated procurement)(1) (2)

reworded (1) Estimated renewable procurement amounts are expected to be consistent with Power Content Label reporting and adjustments, based on current CEC guidelines.

FY 2021 10-K
Removed
Filed Feb 10, 2022

Biopower4 % Geothermal5 % RPS-Eligible Small Hydroelectric2 % Solar28 % Wind11 % Total50 % (1) Estimated renewable procurement amounts are expected to be consistent with Power Content Label reporting and adjustments, based on current CEC guidelines. (2) Estimated renewable procurement percentages above and renewable compliance percentages are expected to be consistent; however, final RPS compliance reporting may result in some differences between the two percentages.

FY 2022 10-K
Added
Filed Feb 23, 2023

Biopower5 % Geothermal- % RPS-Eligible Small Hydroelectric2 % Solar24 % Wind9 % Total40 % (1) Estimated renewable procurement amounts are expected to be consistent with Power Content Label reporting and adjustments, based on current CEC guidelines. (2) Estimated renewable procurement percentages above and renewable compliance percentages are expected to be consistent; however, final RPS compliance reporting is subject to a different methodology and may result in some differences between the two percentages.

reworded Energy Storage

FY 2021 10-K
Removed
Filed Feb 10, 2022

Energy Storage Energy storage improves system reliability and supports California's decarbonization goals by integrating increased levels of renewable energy. The CPUC has established a multi-year energy storage procurement framework, under which the Utility was required to procure 580 MW of qualifying storage capacity by the end of 2020, with all energy storage projects required to be operational by the end of 2024. As of December 31, 2021, the Utility was on track to meet its storage goals by the end of 2024. Additionally, the Utility has been actively procuring energy storage to meet critical reliability needs. The CPUC previously approved more than 1,100 MW of storage to come online in 2022 and 2023. In January 2022, the Utility also requested CPUC approval for another 1,600 MW of storage to be completed by the summer of 2024, which would bring the Utility's total energy storage system capacity to more than 3,330 MW. Finally, the Utility expects to solicit 200 MW of long-duration storage, which is storage with at least eight hours of discharge capacity, in 2022 to have these resources online between 2026 and 2028. 33

FY 2022 10-K
Added
Filed Feb 23, 2023

Energy Storage Energy storage improves system reliability and supports California's decarbonization goals by integrating increased levels of renewable energy. The CPUC has established a multi-year energy storage procurement framework, under which the Utility was required to procure 580 MW of qualifying storage capacity by the end of 2020, with all energy storage projects required to be operational by the end of 2024. As of December 31, 2022, the Utility was on track to meet its storage goals by the end of 2024. Additionally, the Utility has been actively procuring energy storage to meet critical reliability needs. The CPUC previously approved more than 1,100 MW of storage to come online in 2022 and 2023. In January 2022, the Utility also requested CPUC approval for another 1,600 MW of storage to be completed by the summer of 2024, which would bring the Utility's total energy storage system capacity to more than 3,330 MW. Finally, the Utility is soliciting 200 MW of long-duration storage, which is storage with at least eight hours of discharge capacity, to have these resources online between 2026 and 2028.

reworded At December 31, 2022, the Utility owned the following generation facilities, all located in California, listed by energy source and further described below:

FY 2021 10-K
Removed
Filed Feb 10, 2022

Owned Generation Facilities At December 31, 2021, the Utility owned the following generation facilities, all located in California, listed by energy source and further described below:

FY 2022 10-K
Added
Filed Feb 23, 2023

Owned Generation Facilities At December 31, 2022, the Utility owned the following generation facilities, all located in California, listed by energy source and further described below:

reworded Conventional16 counties in northern and central California99 2,645

FY 2021 10-K
Removed
Filed Feb 10, 2022

Generation TypeCounty LocationNumber of UnitsNet Operating Capacity (MW) Nuclear (1): Diablo CanyonSan Luis Obispo2 2,240 Hydroelectric (2): Conventional16 counties in northern and central California100 2,648

FY 2022 10-K
Added
Filed Feb 23, 2023

Generation TypeCounty LocationNumber of UnitsNet Operating Capacity (MW) Nuclear (1): Diablo CanyonSan Luis Obispo2 2,240 Hydroelectric (2): Conventional16 counties in northern and central California99 2,645

reworded Electricity Transmission

FY 2021 10-K
Removed
Filed Feb 10, 2022

Electricity Transmission At December 31, 2021, the Utility owned approximately 18,000 circuit miles of interconnected transmission lines operating at voltages ranging from 60 kV to 500 kV. The Utility also operated 33 electric transmission substations with a capacity of approximately 70,000 MVA. The Utility's electric transmission system is interconnected with electric power systems in the Western Electricity Coordinating Council, which includes many western states, the Canadian provinces of Alberta and British Columbia, and parts of Mexico.

FY 2022 10-K
Added
Filed Feb 23, 2023

Electricity Transmission As of December 31, 2022, the Utility owned approximately 18,000 circuit miles of interconnected transmission lines operating at voltages ranging from 60 kV to 500 kV. The Utility also operated 33 electric transmission substations with a capacity of approximately 65,000 MVA. The Utility's electric transmission system is interconnected with electric power systems in the Western Electricity Coordinating Council, which includes many western states, the Canadian provinces of Alberta and British Columbia, and parts of Mexico.

reworded Electricity Operating Statistics

FY 2021 10-K
Removed
Filed Feb 10, 2022

Electricity Operating Statistics The following table shows certain of the Utility's operating statistics from 2019 to 2021 for electricity sold or delivered, including the classification of revenues by type of service. No single customer of the Utility accounted for 10% or more of consolidated revenues for electricity sold in 2021, 2020 or 2019.

FY 2022 10-K
Added
Filed Feb 23, 2023

Electricity Operating Statistics The following table shows certain of the Utility's operating statistics from 2020 to 2022 for electricity sold or delivered, including the classification of revenues by type of service. No single customer of the Utility accounted for 10% or more of consolidated revenues for electricity sold in 2022, 2021 or 2020.

reworded Natural Gas Utility Operations

FY 2021 10-K
Removed
Filed Feb 10, 2022

(3) These amounts represent revenues authorized to be billed. Natural Gas Utility Operations The Utility provides natural gas transportation services to "core" customers (i.e., small commercial and residential customers) and to "non-core" customers (i.e., industrial, large commercial, and natural gas-fired electric generation facilities) that are connected to the Utility's gas system in its service territory. Core customers can purchase natural gas procurement service (i.e., natural gas supply) from either the Utility or non-utility third-party gas procurement service providers (referred to as "core transport agents"). When core customers purchase gas supply from a core transport agent, the Utility continues to provide gas delivery, metering and billing services to customers. When the Utility provides both transportation and procurement services, the Utility refers to the combined service as "bundled" natural gas service. Currently, more than 96% of core customers, representing approximately 85% of the annual core market demand, receive bundled natural gas service from the Utility. 35 The Utility generally does not provide procurement service to non-core customers, which must purchase their gas supplies from third-party suppliers, unless the customer is a natural gas-fired generation facility with which the Utility has a power purchase agreement that includes its generation fuel expense. The Utility offers backbone gas transmission, gas delivery (local transmission and distribution), and gas storage services as separate and distinct services to its non-core customers. Access to the Utility's backbone gas transmission system is available for all natural gas marketers and shippers, as well as non-core customers. The Utility also delivers gas to off-system customers (i.e., outside of the Utility's service territory) and to third-party natural gas storage customers.

FY 2022 10-K
Added
Filed Feb 23, 2023

(3) These amounts represent revenues authorized to be billed. Natural Gas Utility Operations The Utility provides natural gas transportation services to "core" customers (i.e., small commercial and residential customers) and to "non-core" customers (i.e., industrial, large commercial, and natural gas-fired electric generation facilities) that are connected to the Utility's gas system in its service area. Core customers can purchase natural gas procurement service (i.e., natural gas supply) from either the Utility or non-utility third-party gas procurement service providers (referred to as "core transport agents"). When core customers purchase gas supply from a core transport agent, the Utility continues to provide gas delivery, metering, and billing services to customers. When the Utility provides both transportation and procurement services, the Utility refers to the combined service as "bundled" natural gas service. More than 96% of core customers, representing approximately 85% of the annual core market demand, receive bundled natural gas service from the Utility. The Utility generally does not provide procurement service to non-core customers, which must purchase their gas supplies from third-party suppliers, unless the customer is a natural gas-fired generation facility with which the Utility has a power purchase agreement that includes its generation fuel expense. The Utility offers backbone gas transmission, gas delivery (local transmission and distribution), and gas storage services as separate and distinct services to its non-core customers. Access to the Utility's backbone gas transmission system is available for all natural gas marketers and shippers, as well as non-core customers. The Utility also delivers gas to off-system customers (i.e., outside of the Utility's service area) and to third-party natural gas storage customers. 32

reworded Natural Gas System Assets

FY 2021 10-K
Removed
Filed Feb 10, 2022

Natural Gas System Assets The Utility owns and operates an integrated natural gas transmission, storage, and distribution system that includes most of northern and central California. At December 31, 2021, the Utility's natural gas system consisted of approximately 43,800 miles of distribution pipelines, over 6,200 miles of backbone and local transmission pipelines, and various storage facilities. The Utility owns and operates eight natural gas compressor stations on its backbone transmission system and one small station on its local transmission system that are used to move gas through the Utility's pipelines. The Utility's backbone transmission system, composed primarily of Lines 300, 400, and 401, is used to transport gas from the Utility's interconnection with interstate pipelines, other local distribution companies, and California gas fields to the Utility's local transmission and distribution systems. The Utility has firm transportation agreements for delivery of natural gas from western Canada to the United States-Canada border with TransCanada NOVA Gas Transmission, Ltd. interconnecting downstream with TransCanada Foothills Pipe Lines Ltd., B.C. System. The Foothills system interconnects at the border to the pipeline system owned by Gas Transmission Northwest, LLC, which provides natural gas transportation services to a point of interconnection with the Utility's natural gas transportation system on the Oregon-California border near Malin, Oregon. The Utility also has firm transportation agreements with Ruby Pipeline, LLC to transport natural gas from the U.S. Rocky Mountains to the interconnection point with the Utility's natural gas transportation system in the area of Malin, Oregon, at the California border. Similarly, the Utility has a firm transportation agreement with Transwestern Pipeline Company, LLC to transport natural gas from supply points in the southwestern United States to interconnection points with the Utility's natural gas transportation system in the area of California near Topock, Arizona. (For more information regarding the Utility's natural gas transportation agreements, see Note 15 of the Notes to the Consolidated Financial Statements in Item 8.) The Utility owns and operates three underground natural gas storage fields and has a 25% interest in a fourth storage field, all of which are connected to the Utility's gas transmission system. In 2019, the CPUC approved the discontinuation, through closure or sale, of operations at two of the Utility's owned and operated gas storage fields, Pleasant Creek and Los Medanos. The Utility expects to sell Pleasant Creek in 2022 in accordance with the CPUC's final decision in the 2019 GT&S rate case. The Utility intends to retain the Los Medanos field to further support system supply reliability as proposed in the 2023 GRC. The Utility owns and operates compressors and other facilities at these storage fields that are used to inject gas into the fields for storage and later for withdrawal. In addition, four independent storage operators are interconnected to the Utility's Northern California gas transmission system. In 2021, the Utility continued upgrading transmission pipeline to allow for the use of in-line inspection tools and continued its work on the final recommendation from the NTSB's 2010-11 San Bruno investigation to hydrostatically test all high consequence pipeline mileage. The Utility currently plans to complete this NTSB recommendation by 2022 for remaining short pipeline segments that include tie-in pieces, fittings or smaller diameter off-takes from the larger transmission pipelines. 36

FY 2022 10-K
Added
Filed Feb 23, 2023

Natural Gas System Assets The Utility owns and operates an integrated natural gas transmission, storage, and distribution system that includes most of northern and central California. At December 31, 2022, the Utility's natural gas system consisted of approximately 44,000 miles of distribution pipelines, over 6,300 miles of backbone and local transmission pipelines, and various storage facilities. The Utility owns and operates eight natural gas compressor stations on its backbone transmission system and one compressor station on its local transmission system that are used to move gas through the Utility's pipelines. The Utility's backbone transmission system is used to transport gas from the Utility's interconnection with interstate pipelines, other local distribution companies, and California gas fields to the Utility's local transmission and distribution systems. The Utility has firm transportation agreements for the transportation of natural gas from various natural gas supply points and interconnection points to the Utility's natural gas transportation system. These agreements provide transportation service from western Canada to the United States-Canada border, from the United States-Canada border to an interconnection point with the Utility's natural gas transportation system at the Oregon-California border, from the U.S. Rocky Mountains to an interconnection point with the Utility's natural gas transportation system at the Oregon-California border, and from supply points in the southwestern United States to interconnection points with the Utility's natural gas transportation system in the area of California near Topock, Arizona. (For more information regarding the Utility's natural gas transportation agreements, see Note 16 of the Notes to the Consolidated Financial Statements in Item 8.) The Utility owns and operates three underground natural gas storage fields and has a 25% interest in a fourth storage field, all of which are connected to the Utility's gas transmission system. In 2019, the CPUC approved the discontinuation, through closure or sale, of operations at two of the Utility's owned and operated gas storage fields, Pleasant Creek and Los Medanos. The Utility expects to sell Pleasant Creek in 2023 in accordance with the CPUC's final decision in the 2019 GT&S rate case. The Utility intends to retain the Los Medanos field to further support system supply reliability as proposed in the 2023 GRC. The Utility owns and operates compressors and other facilities at these storage fields that are used to inject gas into the fields for storage and later for withdrawal. In addition, four independent storage operators are interconnected to the Utility's Northern California gas transmission system. In 2022, the Utility continued upgrading transmission pipeline to allow for the use of in-line inspection tools and substantially completed its work on the final recommendation from the NTSB's 2010-11 San Bruno investigation to confirm testing or perform a hydrostatic test for all Class 3 and Class 4 pipelines and all high consequence pipeline mileage. 33

reworded Natural Gas Operating Statistics

FY 2021 10-K
Removed
Filed Feb 10, 2022

Natural Gas Operating Statistics The following table shows the Utility's operating statistics from 2019 through 2021 (excluding subsidiaries) for natural gas, including the classification of revenues by type of service. No single customer of the Utility accounted for 10% or more of consolidated revenues for bundled gas sales in 2021, 2020 or 2019.

FY 2022 10-K
Added
Filed Feb 23, 2023

Natural Gas Operating Statistics The following table shows the Utility's operating statistics from 2020 through 2022 (excluding subsidiaries) for natural gas, including the classification of revenues by type of service. No single customer of the Utility accounted for 10% or more of consolidated revenues for bundled gas sales in 2022, 2021 or 2020.

reworded Trends in Market Demand and Competitive Conditions in the Electricity Industry

FY 2021 10-K
Removed
Filed Feb 10, 2022

(2) These amounts represent revenues authorized to be billed. Competition Trends in Market Demand and Competitive Conditions in the Electricity Industry California law allows qualifying non-residential electric customers of IOUs to purchase electricity from energy service providers rather than from the utilities up to certain annual limits specified for each utility. This arrangement is known as DA. In 2018, the California legislature passed a bill to expand the annual statewide DA cap by 4,000 GWh and directed the CPUC to consider whether DA should be further expanded. In addition, California law permits cities, counties, and certain other public agencies that have qualified to become a CCA to generate or purchase electricity for their local residents and businesses. By law, a CCA can procure electricity for all of its residents and businesses that do not affirmatively elect to continue to receive electricity generated or procured by a utility. In 2019, the CPUC issued an order implementing the 4,000 GWh increase for DA transactions, including an apportionment to the Utility's service area of approximately 1,873 GWh. On June 24, 2021, the CPUC adopted a decision further implementing the 2018 legislation. In that decision, the CPUC recommended against further legislative expansion of DA at this time. Although a CPUC staff report issued in September 2020 had recommended expanding DA at a rate of ten percent each year, the CPUC ultimately found that recent reliability events and the current integrated resource planning forecasted needs for additional generation prevented a need for further DA reopening. The CPUC found that expanded DA would result in further fragmentation of the electric market in California and raise electric system reliability concerns. Additionally, the CPUC based its recommendation in part on DA providers' primary reliance on unspecified power sources, which it found may not support California's climate goals. 37 The Utility continues to provide transmission, distribution, metering, and billing services to DA customers at the election of their energy service provider. The CCA customers continue to obtain transmission, distribution, metering, and billing services from the Utility. In addition to collecting charges for transmission, distribution, metering, and billing services that it provides, the Utility is able to collect charges intended to recover the generation-related costs that the Utility incurred on behalf of DA and CCA customers while they were the Utility's customers. The Utility remains the electricity provider of last resort for these customers. Section 387 of the Public Utilities Code allows for a request to transfer the responsibilities of the provider of last resort obligation from IOUs to other entities. The Utility is also impacted by the increasing viability of distributed generation and energy storage. The levels of self-generation of electricity by customers (primarily solar installations) and the use of customer NEM, which allows self-generating customers employing qualifying renewable resources to receive bill credits at the full retail rate, are increasing, putting upward rate pressure on remaining customers. New NEM customers are required to pay an interconnection fee, utilize time of use rates, and are required to pay certain non-bypassable charges to help fund some of the costs of low income, energy efficiency, and other programs that other customers pay. Significantly higher bills for remaining customers may result in a decline of the number of such customers as they may seek alternative energy providers or adopt self-generation technologies. See "Rising rates for the Utility's customers could result in circumstances in which the Utility is unable to fully recover costs or earn its authorized ROE" in Item 1A. Risk Factors and "Regulatory Matters-OIR to Revisit Net Energy Metering Tariffs" in Item 7. MD&A. Further, in some circumstances, governmental entities such as cities and irrigation districts may have authority under the state constitution or state statute to provide retail electric service directly to consumers. Those entities may rely upon FERC open access tariffs and Utility infrastructure to deliver energy to them at wholesale rates for resale at retail to existing or potential new Utility customers. These entities may also seek to acquire the Utility's transmission or distribution facilities through eminent domain for use in serving electricity at retail to existing or potential new Utility customers. During the Chapter 11 Cases, multiple entities communicated their interest in acquiring Utility assets through voluntary sales. It is also expected that some publicly-owned utilities will construct duplicate or new transmission or distribution facilities to serve existing or potential new Utility customers. In some instances, microgrid formation is a key factor in a community's choice to engage governmental entities. The Utility also competes for the opportunity to develop and construct certain types of electric transmission facilities within, or interconnected to, its service territory through a competitive bidding process managed by the CAISO. The effect of such types of retail competition generally is to reduce the number of utility customers, leading to a reduction in the Utility's rate base.

FY 2022 10-K
Added
Filed Feb 23, 2023

(2) These amounts represent revenues authorized to be billed. Competition Trends in Market Demand and Competitive Conditions in the Electricity Industry The Utility expects customer electric load to increase in coming years primarily as a result of electrification of buildings and transportation. The Utility is not able to predict how quickly this electrification will occur. The Utility expects customer demand for gas to decrease in the coming years, primarily in response to policies supporting California's climate goals. California law allows qualifying non-residential electric customers of IOUs to purchase electricity from energy service providers rather than from the utilities up to certain annual limits specified for each utility. This arrangement is known as DA. In addition, California law permits cities, counties, and certain other public agencies that have qualified to become a CCA to generate or purchase electricity for their local residents and businesses. By law, a CCA can procure electricity for all of its residents and businesses that do not affirmatively elect to continue to receive electricity generated or procured by a utility. The Utility continues to provide transmission, distribution, metering, and billing services to DA customers at the election of their energy service provider. The CCA customers continue to obtain transmission, distribution, metering, and billing services from the Utility. In addition to collecting charges for transmission, distribution, metering, and billing services that it provides, the Utility is able to collect charges intended to recover the generation-related costs that the Utility incurred on behalf of DA and CCA customers while they were the Utility's customers. The Utility remains the electricity provider of last resort for these customers. Section 387 of the Public Utilities Code allows for a request to transfer the responsibilities of the provider of last resort obligation from IOUs to other entities. 34 The Utility is also impacted by the increasing viability of distributed generation and energy storage. The levels of self-generation of electricity by customers (primarily solar installations) and customer enrollment in NEM, which allows self-generating customers employing qualifying renewable resources to receive bill credits at the full retail rate, are increasing, putting upward rate pressure on remaining customers. New NEM customers, as well as customers interconnecting on the successor to the NEM tariffs, are required to pay an interconnection fee, utilize time of use rates, and are required to pay certain non-bypassable charges to help fund some of the costs of low income, energy efficiency, and other programs that other customers pay. Significantly higher bills for remaining customers may result in a decline of the number of such customers as they may seek alternative energy providers or adopt self-generation technologies. See "Rising rates for the Utility's customers could result in circumstances in which the Utility is unable to fully recover costs or earn its authorized ROE" in Item 1A. Risk Factors and "Regulatory Matters - OIR to Revisit Net Energy Metering Tariffs" in Item 7. MD&A. Further, in some circumstances, governmental entities such as cities and irrigation districts may have authority under the state constitution or state statute to provide retail electric service directly to consumers. Those entities may rely upon FERC open access tariffs and Utility infrastructure to deliver energy to them at wholesale rates for resale at retail to existing or potential new Utility customers. These entities may also seek to acquire the Utility's transmission or distribution facilities through eminent domain for use in serving electricity at retail to existing or potential new Utility customers. As a result, the Utility could lose customers (residential, commercial, and industrial) in the municipality. See "Jurisdictions may attempt to acquire the Utility's assets through eminent domain" in Item 1A. Risk Factors. It is also expected that some publicly-owned utilities will build new or duplicate transmission or distribution facilities to serve existing or potential new Utility customers. In some instances, microgrid formation is a key factor in a community's choice to engage governmental entities. The effect of such types of retail competition generally is to reduce the number of utility customers, leading to a reduction in the Utility's rate base. The Utility also competes for the opportunity to develop and construct certain types of electric transmission facilities within, or interconnected to, its service area through a competitive bidding process managed by the CAISO.

reworded Performance: Underpinning the Triple Bottom Line Under System Hardening, the Utility exceeded its undergrounding plan by completing 180 miles of lines in 2022 and brought online two additional remote grids; consequently, the company reported that these measures significantly reduced both the size and number of CPUC-reportable ignitions and acres burned in 2022. Additionally, the Lean operating system deployment is expanding to include a fifth play, waste elimination, starting in 2023.

FY 2021 10-K
Removed
Filed Feb 10, 2022

In 2020, the Utility spent $3.9 billion with certified diverse suppliers, representing 38.9% of its total spend. Performance: Underpinning The Triple Bottom Line PG&E Corporation and the Utility are transitioning to the Lean operating system, which includes four basic "plays": visual management, operating reviews, problem solving and standard work. PG&E Corporation and the Utility have implemented the first two plays in 2021 and expect to roll out the second two plays in 2022. Visual management allows teams to see how they are performing against their most important metrics using real-time data. During 2021, PG&E Corporation and the Utility have set up over 2,000 daily operating reviews, beginning with crews closest to the work and cascading up to senior leadership. These brief meetings help the Utility identify gaps and quickly develop plans to support the teams performing the work and give the Utility more visibility, control and predictability in its operations. For instance, the Lean operating system helped the Utility identify patterns in the conditions of ignitions and led to the implementation of EPSS. PG&E Corporation's and the Utility's performance is also driven by an increased focus on alignment on shared outcomes among its leadership and within the organization. PG&E Corporation and the Utility have implemented a regional operating model to place more co-workers and operational leadership closer to their customers. The purposes of regionalization are to address local issues faster; reduce outage response times; create faster interconnections for customers connecting solar or distributed energy to the grid; and build stronger relationships and information flow between the companies and their customers. California has experienced unprecedented weather conditions in recent years and the Utility's service territory remains susceptible to additional wildfire activity. In response, the Utility has implemented operational changes and investments that reduce wildfire risk, including: •Enhanced Powerline Safety Settings: In 2021, the Utility implemented the EPSS program, which adjusts the sensitivity of circuit protection devices on certain power lines to de-energize them more rapidly in the event of a disturbance to help prevent potential ignitions. After EPSS was initiated, CPUC-reportable ignitions were reduced substantially on EPSS-enabled circuits, compared to the prior three-year average. •Public Safety Power Shutoffs: The PSPS program proactively de-energizes power lines in response to forecasted weather conditions. Since its inception in late 2017, the PSPS program has become more targeted because the Utility has developed more granular risk models, including adding consideration of vegetation management and maintenance tag statuses for scoping PSPS events. The Utility has also installed sectionalizers for more strategic de-energizations of circuits and transmission lines. •Vegetation management: The Utility inspects its overhead electric distribution and transmission facilities on an annual basis to identify and clear vegetation that might grow or fall into utility equipment. In addition, the Utility operates an EVM program for distribution facilities in HFTD areas. The Utility is also increasing oversight and engagement with the contractors supporting vegetation management work. •Asset inspections: Since 2018, the Utility has reoriented its asset inspections programs toward asset condition and consequence risk, particularly wildfire risk, and have become more thorough, standardized, digitized, and verifiable. The Utility uses risk-informed inspection cycles. In 2021, the Utility continued to refine its risk modeling, including further incorporating data from asset inspections. 18 •System hardening: System hardening entails replacing or eliminating existing distribution lines in HFTDs and installing stronger and more resilient equipment. Hardening methods include replacing bare overhead conductor with covered conductor and installing stronger poles, removing the line and serving our customers through remote grids, or converting the line from overhead to underground. In 2021, the Utility announced a commitment to underground 10,000 miles of electric distribution lines in HFTDs, which will eliminate ignition risks from overhead vegetation or wind-induced equipment failures in those areas and help reduce the need for vegetation management. Even as the Utility works to mitigate wildfire risk, it also works to reduce the impact of those mitigations on its customers, including making the PSPS program less disruptive through sectionalizing devices for both distribution and transmission lines, temporary generation applications, and implementation of microgrid pilot technologies. For example, in 2021, the CPUC authorized the Utility to prepare 10 substations to form microgrids in the event of PSPS outages impacting the transmission lines feeding those substations, in addition to nine other distribution microgrids that the Utility made ready to operate in 2021. Two of the distribution microgrids piloted battery storage and a linear generator in a hybrid configuration with diesel generation to assist in energizing the microgrids when needed. Through these and other mitigation actions, PSPS events in 2021 impacted 78% fewer customers on average than PSPS events in 2019. The Utility also brought online its first "remote grid" in 2021, which allows distribution lines in HFTDs to be removed and replaced with locally sited resources. Remote grids can reduce costs and fire risks, while maintaining service to impacted customers. The Utility is pursuing the development of additional remote grid projects.

FY 2022 10-K
Added
Filed Feb 23, 2023

In 2021, the Utility spent $4.01 billion with certified diverse suppliers, representing 38.7% of its total spend. Performance: Underpinning the Triple Bottom Line PG&E Corporation and the Utility use the Lean operating system, which includes four basic "plays:" visual management; operating reviews; problem solving; and standard work. Visual management allows teams to see how they are performing against their most important metrics using real-time data. PG&E Corporation and the Utility hold daily, weekly, and monthly operating reviews designed to align the performance of workers closest to the work with the goals and objectives of senior leadership. These brief meetings help the Utility identify gaps and quickly develop plans to support the teams performing the work and give the Utility more visibility, control and predictability in its operations. Problem solving involves a structured approach to identifying, containing, analyzing, and solving problems in order to capitalize on opportunities. Standard work reduces costs and increases productivity by ensuring a consistent company-wide method for completing a task. For instance, the Lean operating system helped the Utility identify patterns in the conditions of ignitions and led to the implementation of EPSS and drove significant benefit and understanding in how PG&E Corporation and the Utility manage customer satisfaction. PG&E Corporation's and the Utility's performance is also driven by an increased focus on alignment on shared outcomes among its leadership and within the organization. In 2023, PG&E Corporation's and the Utility's Lean deployment will focus on a fifth play, waste elimination, which enables the companies to identify and eliminate inefficiencies in both process and workflow in a sustainable manner, as well as the continued adoption of a performance playbook and improvements to financial visibility and controls. PG&E Corporation and the Utility have implemented a regional service model to bring the Utility closer to the hometowns it serves. Through the regional service model, the Utility has restructured its service area into five regions, with leaders in each region to deliver improved public and employee safety, customer service, and operational reliability outcomes. PG&E Corporation and the Utility are committed to designing an electric system that is resilient to climate change, decarbonized, and optimized to local and system needs. California has experienced unprecedented weather conditions in recent years and the Utility's service area remains susceptible to additional wildfire activity. In response, the Utility has implemented operational changes and investments that reduce wildfire risk, including: •Enhanced Powerline Safety Settings: EPSS adjusts the sensitivity of circuit protection devices on selected power lines to de-energize them more rapidly in the event of a disturbance to help prevent potential ignitions. After EPSS was initiated, both the size and number of CPUC-reportable ignitions were reduced substantially on EPSS-enabled circuits, compared to the prior three-year average. 15 •Public Safety Power Shutoffs: The PSPS program proactively de-energizes power lines in response to forecasted weather conditions. Since its inception in late 2017, the PSPS program has become more targeted because the Utility has developed more granular risk models, including adding consideration of vegetation management and maintenance tag statuses for scoping PSPS events. The Utility has also installed sectionalizers for more targeted de-energizations of circuits and transmission lines. In 2022, the Utility did not have any PSPS events. •Vegetation management: The Utility inspects its overhead electric distribution and transmission facilities on an annual basis to identify and clear vegetation that might grow or fall into utility equipment. The Utility is also increasing oversight and engagement with the contractors supporting vegetation management work. •Asset inspections: Since 2018, the Utility has reoriented its asset inspections programs toward asset condition and consequence risk, particularly wildfire risk, and these programs have become more thorough, standardized, digitized, and verifiable. The Utility uses risk-informed inspection cycles. In 2022, the Utility continued to refine its risk modeling, including further incorporating data from asset inspections. As a result of the improved inspection program, the Utility's inspections in recent years have begun to more thoroughly identify equipment conditions. •System hardening: System hardening entails repairing, replacing, or eliminating existing power lines in HFTDs and installing stronger and more resilient equipment. As the Utility's asset inspections have identified more equipment conditions, the Utility has hardened its system by correcting significantly more equipment conditions than in prior years. Hardening methods include replacing bare overhead conductor with covered conductor and installing stronger poles, removing lines, and serving customers through remote grids, or converting lines from overhead to underground. In 2021, the Utility announced a program to underground 10,000 miles of electric distribution lines in high wildfire risk areas. In 2022, the Utility undergrounded 180 miles of lines, which exceeded its plan to underground 175 miles of lines. Undergrounding can substantially reduce ignition risk and improve reliability during storms or periods of high wildfire risk. The Utility also brought online two additional "remote grids" in 2022, which allow distribution lines in HFTDs to be removed and replaced with locally sited resources. Remote grids can reduce costs and fire risks, while maintaining service to participating customers. As a result of these measures, the Utility significantly reduced both the size and number of CPUC-reportable ignitions and number of acres burned in 2022, compared to prior years.